Fifth Circuit Allows Texas Commission to Limit PURPA Sales

Sep 12, 2014

Reading Time : 3 min

Under a PUCT rule implementing FERC’s PURPA regulations, the Legally Enforceable Obligation pricing option is available only to QFs that can provide “firm power.”  The PUCT rule defines “firm power” as “power or power-producing capacity . . . that is available pursuant to a legally enforceable obligation for scheduled availability over a specified term.”  QFs unable to meet this requirement can charge the utility only the current or “as-available” price.

In a 2007 complaint filed with the PUCT, Exelon argued that it had formed a Legally Enforceable Obligation with Southwestern Public Service Company (“Southwestern”), and that Southwestern therefore owed Exelon payment under rates that ranged from $0.035/kWh to $0.090/kWh—rates that significantly exceeded the applicable as-available rates. Southwestern argued that no Legally Enforceable Obligation was formed because Exelon’s wind generation could not provide “firm power.” Exelon alleged that its power was in fact firm.  In its 2009 order, the PUCT ultimately sided with Southwestern, finding that the Exelon wind entities did not comply with the conditions for creating a Legally Enforceable Obligation and, therefore, that the appropriate rate was the as-available rate.

Subsequently, Exelon filed a Petition for Declaratory Order with FERC, asking FERC to determine whether all QFs are entitled to the Legally Enforceable Obligation pricing option under FERC’s regulations. In November 2009, FERC issued an order finding that the PUCT decision was inconsistent with FERC’s regulations implementing PURPA and that QFs may form Legally Enforceable Obligations even with non-firm power. FERC noted that its regulations make no distinction between firm and non-firm power in the QF context. Upon receiving this favorable order from FERC, Exelon filed suit in federal district court seeking declaratory and injunctive relief against the PUCT. The district court granted Exelon’s motion for summary judgment, finding that the PUCT could not impose the firm power condition on the creation of a Legally Enforceable Obligation.

The Fifth Circuit reversed.  First, the Fifth Circuit vacated the portions of the district court judgment regarding the PUCT’s 2009 order and directed the district court to dismiss those claims for lack of subject matter jurisdiction. The court reasoned that, under PURPA, state courts have exclusive jurisdiction over “as-applied” challenges, which are claims asserting that a state agency’s implementation of PURPA is unlawful as it applies to an individual petitioner. The Fifth Circuit held that Exelon’s claims regarding the PUCT’s 2009 order fell within this category and thus determined that the federal district court lacked jurisdiction.

Exelon had also challenged the underlying PUCT regulation itself, arguing that the regulation failed to implement FERC’s regulation, as determined by FERC in its November 2009 Declaratory Order. In a divided opinion, the majority held that Exelon failed to show that the PUCT was implementing FERC’s PURPA regulations improperly. Because FERC’s regulation did not explicitly mandate that all QFs must be able to form Legally Enforceable Obligations, the Fifth Circuit held that Texas was within its discretion to set reasonable parameters on its implementation of FERC’s regulations, such as limiting Legally Enforceable Obligations to firm power QFs.  The court held that FERC’s Declaratory Order advising that all QFs should be able to form Legally Enforceable Obligations was merely an “informal guidance letter,” which only had persuasive value at best. The majority also relied on canons of statutory construction, reasoning that Exelon’s reading of FERC’s regulations would render certain sections superfluous.  Specifically, the court concluded that if all QFs, regardless of whether they provided firm or non-firm power, were eligible to form Legally Enforceable Obligations, the as-available pricing mechanisms in FERC’s regulations would be duplicative.

In a partial dissent, Judge Edward Prado argued that the plain language of the PUC rule conflicts with the FERC regulations implementing PURPA and, even if the language were not in conflict, the court should defer to FERC’s interpretation of its own regulation.


1 QFs are cogenerators that meet certain operating and efficiency standards or small, renewable power production facilities.

2 The Supreme Court has explained that the law avoids thorny 10th Amendment issues because technically states can implement PURPA simply by adjudicating disputes arising under the statute.  See FERC v. Mississippi, 456 U.S. 742, 760 (1982).

Share This Insight

© 2024 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.