Sound Bites from Infocast Wind Finance 2015

Feb 17, 2015

Reading Time : 7 min

Further, the best guess of the speakers is that the IRS will publish the updated guidance in March.  In addition, it is arguably a good sign that industry representatives have not been invited by the IRS to have a meeting to either (a) defend the request for moving the deadline to the end of 2016 or (b) discus alternative proposals.

Compliance with PTC Eligibility Start of Construction Requirements

The representatives from financial institutions on the tax equity panel had consensus that investors have a hierarchy of start of construction transactions as to their comfort that the project, in fact, qualifies for PTCs:

1. Projects that “incurred” 5 percent of the total cost prior to 2015 to meet the safe harbor provided for in IRS Notice 2013-29 that will be placed in service prior to the end of 2015 (or the end of 2016 if the IRS issues favorable guidance) to avoid the “continuous efforts” requirement.

2. Projects that undertook “significant physical work” prior to 2015 that will be placed in service prior to the end of 2015 (or the end of 2016 if the IRS issues favorable guidance) to avoid the “continuous construction” requirement.

3. Projects that “incurred” 5 percent of the total cost prior to 2015 to meet the safe harbor provided for in IRS Notice 2013-29 that will not meet the placed-in-service safe harbor deadline, so they must meet the “continuous efforts” requirement.

4. Projects that undertook “significant physical work” prior to 2015 that will not meet the placed-in-service safe harbor deadline, so they must meet the “continuous construction” requirement.

“There are a lot of projects [to be placed in service] in 2015 for [J.P. Morgan] to deal with in due course.  We are interested in working on [projects to be placed in service in 2016] but signing an equity capital contribution agreement for those projects will be in the second half of 2015.”

Yale Henderson, Managing Director – Energy Investments, J.P. Morgan Capital Corporation

“The PTC start of construction rules result in PTC-eligible projects being condensed in big companies that can write a check at the end of the year of $150 million [to meet the 5 percent safe harbor].  I’m not sure that is healthy for the industry.”

Paul Gaynor, EVP North America & Global Wind, SunEdison

Significant Physical Work Protocols

“The more roads, excavations and transformers, the better chance of your project moving up the hierarchy of projects that financial institutions have in the back of their minds.”

Yale Henderson

“The more construction the better, the better the record keeping the better”

Jack Cargas, a Managing Director – Renewable Energy Finance, Bank of America

Messrs. Cargas and Henderson each stated their institutions preferred 5 percent safe harbor projects but had invested in significant physical work projects (i.e., projects that did not meet the five percent safe harbor).  And that their institutions did not have bright-line standards as to the minimum physical work required but were prepared to decline projects where the physical work seemed to be too minimal.

“One guy and a shovel at year end is not enough.”

Jack Cargas

“Weaker facts on physical work of a significant physical nature are helped by performing continuous construction.  That shows the project did not just lay fallow until it obtained a PPA or a tax equity commitment.”

Yale Henderson

“Developers should try to meet continuous construction, even if they believe they will meet the placed-in-service deadline.”.

Tim Howell, Managing Director & Commercial Leader Power & Renewables, GE Energy Financial Services

Tax Equity After-Tax Returns

 “In 2014, the range of after-tax returns was between 7.35 percent and 9 percent.  The project that got 7.35 percent was a strong portfolio of projects with power purchase agreements (PPA).  The 9 percent project was quite large and used a hedge, rather than a PPA.  Hedge deals are generally in the range of 8 to 9 percent.”

Matthew Cammack, Senior Director, CCA Group

 “Other key economic features are the size of the tax equity investor’s deficit restoration cap, what level of haircuts on expected production are included in the model as a matter of conservatism, the tax equity investor’s outside flip date if the project performs below expectation and the tax equity investor’s right to a cash step-up if performance is under expectation.”

Matthew Cammack    

 “Returns should be 6 percent after-tax.  Returns are over-priced.  The headline return rate has been unchanged even as there are more tax equity investors in the market and a longer history of the deals performing.”

Megan Schultz, V.P. – Finance, Invenergy

“But we [tax equity investors] take the risk of having ten years of tax capacity.”

Yale Henderson

“Much of the tax equity investor’s return is from tax capacity, which is outside the transaction.  The tax benefits have limited value to the sponsor. It is not a zero-sum game.” 

Jack Cargas

“The right metric to [measure the profitability of a transaction to a tax equity investor] is not to compare the [after-tax return] to [the tax equity investor’s] cost of capital.”

Jack Cargas

“After the flip, these projects are going to pay taxes like a champion and most of that tax cost will be borne by the developer.”

Bernardo Goarmon,  EVP – Finance,  EDP Renewables North America

Depth of the Tax Equity Market

“Most tax investors are comfortable at $50 to $75 million per investment.”

Matthew Cammack

 “Institutions [that invest in tax equity] are writing bigger checks [than in prior years] on a per-project basis.”

Jack Cargas

“If we [(Bank of America)] like a project, we really like a project.  We’ve been able to write somewhat larger checks.”

Jack Cargas

“JP Morgan is generally comfortable investing $100 million per project.  We’ll go larger in larger portfolios.”

Yale Henderson

“GE EFS’s maximum investment per project site is $150 million.”

Tim Howell

 “Mid American is making pure tax equity investments as opposed to prior years when it would only buy projects outright.”

Matthew Cammack    

 “I wouldn’t say there is a deep secondary market for tax equity.  It is pretty complicated to sell down.”

Tim Howell

“Most tax equity investors want to establish relationships with developers by making direct investments.”

Yale Henderson

Tax Equity Structuring

“I haven’t seen a pre-paid PPA deal in years.”

Jack Cargas

“There’s no good reason for a levered partnership [(i.e., to give the lender a mortgage over the wind farm)].  Our last levered deal was 2008.  The premium then for a levered deal was 250 to 300 bps.”

Yale Henderson

“There are very few tax equity investors who will do levered partnerships.”

Matthew Cammack

“I give all the credit [for back leverage replacing the senior secured debt] to the project finance debt market’s ability to accommodate back leverage.  There is not a huge economic driver for project level debt.”

Yale Henderson

“I don’t think levered tax equity deals exist [any more].  I don’t know a project finance lender who would agree to forbear for 10  years (i.e., the period PTCs are available).”

Megan Schultz

PTC v. ITC for Wind2

 “Of the 24 wind deals closed last year, there were only three ITC projects and one of those was a partnership flip.”

Matthew Cammack

 “With the new [higher performing turbine] technology, ITC does not make sense.”

Tim Howell

PPA v. Hedge v. Merchant

“We’re seeing an increase in the number of hedge transactions.  The hedge provider is often Merrill Lynch Commodities in transactions in which Bank of America is a tax equity investor.  Based on our reading of the section 45 rules, if the tax equity investor is related to the hedge provider, then the tax equity investor may not provide more than 49.9 percent of the tax equity.  So in those deals, there must be at least two tax equity investors.”

Jack Cargras

“The key to hedge deals is a liberal and robust tracking account to address under performance, which is basically a loan from the hedge provider to the project.”

Yale Henderson

“We’ve done some merchant deals.  We focus on minimizing the cash we get in those deals.”

Yale Henderson

“The hedge transactions have been done in ERCOT.  There’s talk of doing a hedge transaction in PJM in the near future.”

Jack Cargas

“A lot of tax equity investors won’t do hedges.  Most of the deals we did last year were hedges, but the tax equity investors were us and the hedge provider.”

Tim Howell

“We’re looking at offtake arrangements with industrial companies.  Those contracts are somewhere between a PPA and a hedge.”

Megan Schultz

“A project gives up 30 to 40 percent of the value the merchant curve is showing when it enters into a PPA or a hedge.”

Michael Storch, EVP & Chief Commercial Officer, Enel Green Power North America

“A developer must put up a great deal of capital just to meet the requirement to get a PPA with a utility.”

Michael Storch

Market for Sponsor (i.e., Cash Equity)

“Canadian pension funds are offering a great cost of capital for minority positions in both operating and development projects.  Therefore, so far EDPR has not yet transacted with a YieldCo.”

Steve Irvin, EVP, EDP Renewables North America

“GE EFS invested a billion dollars in renewables last year; half of that was cash equity.”

Tim Howell

“If you have a portfolio with proven technology, long-term PPAs, and no curtailment or environmental issues, then it is a most liquid market.”

Paul Gaynor


1 This post was prepared without the benefit of a recording or transcript and some quotes were edited for readability purposes. If there are any misquotes please contact the author for a correction.

2 Wind projects are eligible for either a PTC of $23 per MwH for ten years or a one-time 30 percent investment tax credit (ITC).

Share This Insight

Previous Entries

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

Speaking Energy

April 15, 2025

On April 9, 2025, President Trump issued an executive order (EO)1 directing several federal agencies and subagencies that regulate energy, environmental, and conservation matters,2 including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), to establish conditional sunset dates for “regulations governing energy production.” The stated objective of the EO is to require agencies to periodically reexamine their regulations to ensure that they continue to serve the public good. For FERC, the order covers regulations promulgated under the Federal Power Act (FPA), the Natural Gas Act (NGA) and the Powerplant and Industrial Fuel Use Act (FUA)3, as amended, while DOE must consider regulations promulgated under the Atomic Energy Act (AEA), the National Appliance Energy Conservation Act, the Energy Policy Act of 1992 (EPAct 1992), the Energy Policy Act of 2005 (EPAct 2005) and the Energy Independence and Security Act of 2007 (EISA), as amended (collectively the Covered Regulations).4 To the extent the DOE has been directed to promulgate regulations under various sections of the NGA, FPA and FUA, and FERC has been directed to promulgate regulations specific to the statutes attributed to the DOE in the EO, the EO is silent. The EO expressly does not apply to those “regulatory permitting regimes authorized by statute.”5

...

Read More

Speaking Energy

April 10, 2025

On April 8, 2025, President Trump issued an Executive Order (EO) directing the Department of Energy (DOE) to take steps to expand the use of its emergency authority under Federal Power Act (FPA) Section 202(c) to require the retention of generation resources deemed necessary to maintain resource adequacy within at risk-regions of the bulk power system regulated by the Federal Energy Regulatory Commission (FERC).1 The EO appears to envision a more active role for DOE in overseeing and supporting the resource adequacy of the grid that deviates from the historic use of Section 202(c) and touches on issues at the intersection of state and federal authority over resource planning.

...

Read More

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.