9th Circuit Finds That FERC Acted Arbitrarily and Capriciously by Awarding Incentive Adders to PG&E for Membership in CAISO

Jan 10, 2018

Reading Time : 2 min

The court’s reasoning was straightforward. FERC stated in Order No. 679 that it “will approve, when justified, requests for ROE-based incentives for public utilities that join and/or continue to be a member of” a transmission organization.5 But FERC also stated that it would not create a “generic adder for such membership” and that it would consider incentives on a case-by-case basis.6 The justification that FERC gave for offering such incentives is that “continuing membership [in a transmission organization] is generally voluntary”7 and that such incentives would induce utilities to join, and remain members of, transmission organizations. However, as the court observed, an incentive adder “cannot ‘induce’ behavior that is already legally mandated,”8 and FERC itself has previously refused to award incentives for legally mandated behavior.9

The court concluded that FERC essentially treated ROE adders for transmission organization membership as “generic” by awarding one to PG&E without consideration of PG&E’s case-specific circumstances (i.e., that it is not free to leave CAISO). In doing so, it arbitrarily and capriciously departed without explanation from its stated policy that such adders were to be awarded on a case-by-case basis.

The 9th Circuit’s decision will have an immediate impact for both PG&E and other California utilities. For example, on December 29, 2017, FERC authorized an ROE adder for CAISO membership for Southern California Edison Company, which, like PG&E, is required to seek CPUC authorization to leave CAISO.10 The decision may also impact utilities elsewhere; FERC has routinely granted requests for ROE adders based on transmission organization membership with little consideration of case-specific factors. Thus, utilities located in other transmission organizations may find themselves in the same position as CAISO utilities, at least if state law prevents the utility from leaving the transmission organization at will.

 


1 Ca. Pub. Utils. Comm’n v. FERC, No. 16-70481, 2018 WL 315575 (9th Cir. Jan. 8, 2018) (“9th Cir. Order”).

2 Promoting Transmission Investment Through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057 (“Order 679”), order on reh’g, Order No. 679-A, 117 FERC ¶ 61,345 (2006), order on reh’g, Order No. 679-B, 119 FERC ¶ 61,062 (2007).

3 Order No. 679 at P 326.

4 Id. at P 331.

5 9th Cir. Order at *5 (emphasis in original) (citing Order No. 679 at P 326) .

6 Id.

7 Order No. 679 at P 331.

8 9th Cir. Order at *5.

9 Id. at *7.

10 See S. Cal. Edison Co., 161 FERC ¶ 61,309 (2017).

Share This Insight

Previous Entries

Speaking Energy

March 19, 2026

International trade policy has emerged as a dominant force shaping the oil & gas sector, with sweeping tariffs imposed on products from virtually every nation using authorities including IEEPA, Section 232 and Section 301. President Trump's "America First Trade Policy" leverages duties as negotiation tools to secure bilateral deals featuring significant oil & gas purchase commitments, making trade considerations essential for any cross-border transaction. Energy dominance serves as a cornerstone of the administration's economic and national security strategy, placing the industry squarely in the spotlight. 

...

Read More

Speaking Energy

March 10, 2026

Federal energy regulators are assuming expanded roles as the administration prioritizes energy dominance and infrastructure development to meet unprecedented power demand. FERC Chairman Laura Swett has vowed to expedite data center interconnections while addressing jurisdictional challenges, warning that unmet electricity demand could drive data centers abroad and create national security risks. The agency is processing pipeline applications faster than in prior years and considering blanket authorizations for certain LNG and hydroelectric projects to streamline approvals. 

Pipeline projects previously stalled by Clean Water Act permits are being revitalized, particularly in northeastern states where historically high electricity prices have increased openness to natural gas infrastructure. The Department of Energy is expanding its emergency authority to require retention of generation resources and has granted major LNG export approvals, signaling commitment to expanding U.S. export capacity under a streamlined framework that deprioritizes climate considerations.  

The Administration is bullish on the opportunities for the U.S. energy industry in Venezuela and eager to support companies willing to navigate the political risk inherent in the operations at the moment. Early meetings with President Trump and industry leaders showed the path forward may be longer and more complex than anticipated by the President. 

As permitting reforms advance and the pendulum swings toward fossil fuel favorability, the regulatory and policy landscape is fundamentally reshaping energy infrastructure development timelines and investment opportunities. 

Oil & Gas in 2026: Energy Policy & Regulation 

Delve into the complete regulatory & policy outlook at our Oil & Gas in 2026 report.

...

Read More

Speaking Energy

March 3, 2026

Macroeconomic turbulence and volatile commodity markets significantly influenced oil & gas M&A activity throughout 2025, with deals showing renewed momentum only in the year's second half.  

...

Read More

Speaking Energy

February 24, 2026

On February 19, 2026, the Federal Energy Regulatory Commission (FERC) issued an order rescinding the soft price cap for bilateral spot market energy sales in the Western Electricity Coordinating Council (WECC) region.1 As previously covered, on July 15, 2025, FERC initiated a Federal Power Act Section 206 proceeding following the D.C. Circuit’s decision finding that FERC must apply the Mobile-Sierra public interest standard before ordering refunds for above-cap bilateral sales and vacating FERC’s orders requiring refunds for certain bilateral spot market transactions in the WECC region that exceeded the $1,000 MWh soft price cap.2 FERC’s Order follows through on the proposal it made last July to eliminate the WECCs soft price cap and marks a recognition that Western wholesale markets have evolved over the past two decades to become sufficiently competitive to render the soft price cap unnecessary.  

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.