D.C. Circuit Concludes Again That FERC Has the Authority to Correct Its Own Errors

May 31, 2017

Reading Time : 3 min

Background

Chehalis Power Generating, L.P. (“Chehalis”) provided reactive power service to BPA free of charge until 2005. In 2005, Chehalis filed a rate schedule with FERC under Section 205 of the Federal Power Act (FPA) setting forth the rates that it would henceforth charge BPA for reactive power service. Chehalis’ submittal referred to the rate schedule as an “initial” rate, because Chehalis had not previously charged for reactive power service. However, FERC decided to treat Chehalis’ reactive power schedule as a “changed rate,” reasoning that an initial rate schedule must “involve a new customer and a new service.”2  The distinction between an “initial” and a “changed” rate is significant, because, under FPA Section 205, FERC can permit a rate change to go into effect while it considers whether the rate is just and reasonable. If FERC then determines that the rate is too high, it may order refunds of the difference between the rate charged and the just and reasonable rate. However, FERC interprets this refund authority under Section 205 to be limited to “changed” rates—initial rates are not subject to refund under FPA Section 205.

FERC found Chehalis’ proposed rate for reactive power service to be unjust and unreasonable, and thus directed it to refund the excess revenues it had collected. Chehalis appealed. The D.C. Circuit remanded the case to FERC, directing the Commission to explain why Chehalis’ proposed rate schedule for reactive power qualified as a “changed rate” when Chehalis had not previously filed a rate for reactive power.3  FERC eventually concluded that, although Chehalis’ rate schedule was a “changed rate,” because Chehalis should have filed a rate schedule when it started providing reactive power service—even if the rate was zero—its precedent on the issue was unclear. As such, FERC found that “it would be appropriate” for Chehalis to recover the refunds that it had paid to BPA.4  However, because BPA is anonjurisdictional utility, FERC concluded that it lacked the authority to order BPA to return the refunded amounts.5

TNA Merchant Projects, Inc. v. FERC          

It is well established that FERC lacks jurisdiction under the FPA to order a nonjurisdictional utility (e.g., a governmental entity, such as BPA, a municipal utility or a cooperative) to pay refunds to its customers.6  However, in the D.C. Circuit’s recent TNA decision, the court drew a distinction between refunds and recoupment, explaining that FERC’s lack of refund authority under FPA Section 205 does not prevent it from correcting its own mistakes by authorizing Chehalis to recoup the money it paid to BPA due to FERC’s error and ordering BPA to return the money. The court observed that FPA Section 309, which grants FERC broad remedial authority, “affords [FERC] broad authority to ‘remedy its errors’ and correct unjust situations.”7  The court cited its 2016 decision in Xcel Energy Servs. Inc. v. FERC, which likewise emphasized the Commission’s authority to correct its own errors.8

TNA is, in many ways, a companion case to Xcel. In Xcel, the court found that FERC’s inability to establish a retroactive refund date does not prohibit FERC from correcting its own mistakes, either by retroactively suspending rates under FPA Section 205 or by invoking its authority under FPA Section 309. In both cases, the court refused to accept FERC’s claim that it was statutorily prohibited from undoing the damage done by its own orders.

In addition to finding that FERC had the authority to order recoupment, the court did not disturb FERC’ s finding that Chehalis should have filed an initial rate schedule even when it was not charging for reactive power service. The court reasoned that, at this point in the proceedings, weighing in on that dispute would not affect the rights of the parties one way or the other.

The court remanded the case to FERC to determine the amount of recoupment to which Chehalis is entitled.


1TNA Merch. Projects, Inc. v. FERC, No. 13-1008 (D.C. Cir. May 19, 2017), https://www.ferc.gov/legal/court-cases/opinions/2017/13-1008opn.pdf.
2Chehalis Power Generating, L.P., 112 FERC ¶ 61,144, at P 23 (2005).
3TNA Merch. Projects, Inc. v. FERC, 616 F.3d 588, 593 (D.C. Cir. 2010).
4Chehalis Power Generating, L.P., 145 FERC ¶ 61,052, at P 14 (2013).
5Chehalis Power Generating, L.P., 153 FERC ¶ 61,194 (2015).
6Transmission Agency of N. Cal. v. FERC, 495 F.3d 663, 674 (D.C. Cir. 2007); Bonneville Power Admin. v. FERC, 422 F.3d 908, 926 (9th Cir. 2005).
7TNA Merch. Projects, Inc. v. FERC, No. 13-1008, at 9 (D.C. Cir. May 19, 2017).
8Xcel Energy Servs. Inc. v. FERC, 815 F.3d 947, 956 (D.C. Cir. 2016).




 

 

Share This Insight

Previous Entries

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.