FERC Assesses Significant Civil Penalty Against Natural Gas Pipeline for Allegedly Violating Certificate

Jan 10, 2019

Reading Time : 4 min

Overview of the Project and the Alleged Violation

The AIM Project involves an expansion of Algonquin’s pipeline system throughout the northeast, including in New York, Connecticut and Massachusetts. In May 2015, FERC issued a Certificate for the AIM Project pursuant to Section 7 of the Natural Gas Act. The Certificate adopted environmental conditions from a final Environmental Impact Statement. Part of the AIM Project involved new pipeline facilities that cross the Hudson River by boring a hole and installing pipe underneath the river using a horizontal directional drilling (HDD) technique.

On August 27, 2016, underground on the western slope of the Hudson River near the HDD exit hole where Algonquin expected the pipe to emerge as it was being pulled back, the drill stem became disconnected from the pipe. Algonquin believed that the stem was lost in the vicinity of an off right-of-way area that included wetlands and was not identified in the Certificate as an approved workspace. Algonquin decided to try to retrieve the drill stem via excavation using heavy construction equipment. Prior to Algonquin entering the off right-of-way area, FERC’s on-site compliance manager became aware of the issue and told Algonquin that construction to retrieve the drill stem could not occur without an approved variance from the Commission. The FERC compliance manager also gave Algonquin instructions about environmental mitigation steps that would need to be followed when work began. While Algonquin followed all of these steps, it began preparatory work in the off right-of-way area before receiving a variance from the Commission based on an apparent misunderstanding by some personnel that work could begin while Algonquin was seeking the variance. Algonquin stopped work when it became clear that the disconnect had not occurred where originally anticipated and that more extensive excavation work would be needed. Algonquin subsequently obtained a variance from the Commission and acted with due diligence to maintain and improve the environmental integrity of the off right-of-way area.

FERC found that Algonquin violated the Certificate when it entered into the wetlands without an approved variance. However, FERC determined that the violation affected a “relatively small area, approximately 381 square feet,” did not “result in significant or permanent environmental damage,” and did not unjustly enrich Algonquin in any way.2

Implications

New area of enforcement? The Order marks the first instance of FERC bringing an enforcement case against a pipeline for violating a certificate since FERC received substantial enforcement authority in 2005. There is some reason to think that this is an increasing area of enforcement focus, not just an outlier. In 2017, FERC disclosed that it had directed Enforcement to investigate potential certificate noncompliance by another pipeline developer.3  Also, FERC’s most recent Annual Report on Enforcement notes—where previous Annual Reports had not—that Enforcement’s Division of Investigations is collaborating with other FERC offices on potential enforcement matters regarding pipeline certificates.4 Further, increasing opposition by environmental groups to natural gas infrastructure development (and increased advocacy by such groups at FERC) could lead to more allegations of compliance violations.

Focus on environmental harm. The Order also reflects a focus by the Commission and Enforcement on environmental harm—here, unauthorized work in, and the risk of damage to, wetlands areas. The nonmonetary sanctions imposed by the settlement also have an environmental focus, with FERC requiring Algonquin to submit semiannual environmental compliance monitoring reports. While many environmental groups have criticized FERC’s certificate process and natural gas infrastructure policies, the Order reflects that FERC—including through Enforcement—takes environmental requirements imposed through that process seriously.

Basis for the large penalty amount unclear. The $400,000 fine strikes us as relatively high for this violation, at least without additional explanation that does not appear in the settlement.  In particular, the violation occurred over a short time period, affected a small area, did not cause any lasting harm, and did not benefit Algonquin.  The settlement language arguably sends mixed messages with respect to Algonquin’s understanding of when construction work not covered by a certificate could begin, stating on the one hand that Algonquin knew that FERC requires variances prior to commencing such work, but on the other that some personnel “appeared to believe that work could begin while the variance approval was being sought.”5  Based on the facts as discussed in the Order, and the penalty itself, it is not clear why the Commission thought a fine of this size was appropriate, or how it was calculated under the Commission’s Penalty Guidelines (though the Order does state that Enforcement considered the Guidelines when determining the penalty).  Nonetheless, the Order cautions that pipeline personnel should seek clarification and guidance from the Office of Energy Projects before commencing construction activity if there are questions about certificate compliance.6  That message, plus the size of the fine, suggests FERC is trying to send a warning to pipelines that it expects strict compliance with certificate conditions. 


1 Algonquin Gas Transmission, LLC, 166 FERC ¶ 61,012 (2019) (“Order”).

2 Order, Stipulation and Consent Agreement at P 11.

3 Letter from Terry L. Turpin, Dir., FERC Office of Energy Projects, to Joey Mahmoud, Senior V.P., Rover Pipeline LLC (June 1, 2017) (“Turpin Letter”).

4 FERC Office of Enforcement, 2018 Report on Enforcement at 34 (2018), https://www.ferc.gov/legal/staff-reports/2018/11-15-18-enforcement.pdf.

5 Order at P 5.

6 Id. at P 9, n.1.

Share This Insight

Previous Entries

Speaking Energy

July 8, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to ISO New England Inc. (ISO-NE) directing ISO-NE and ISO-NE participating transmission owners to show cause as to why ISO-NE’s tariff should not be found to be unjust and unreasonable (ISO New England Inc., 195 FERC ¶ 61,215 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

July 7, 2026

On June 29, 2026, the Supreme Court granted a petition for certiorari in Leonard Hoffmann v. WBI Energy Transmission, Inc. (Hoffmann), which presents the question whether section 7 of the Natural Gas Act (NGA) requires pipeline companies using federal eminent domain authority to pay landowners’ attorney’s fees in states where landowners can recover those fees under state law. In the decision giving rise to the Supreme Court’s review, the U.S. Court of Appeals for the Eighth Circuit held that a group of ranchers were not entitled to recover their $383,300 in attorney’s fees incurred while negotiating their compensation—creating a circuit split with four other courts of appeals. Hoffmann will be heard during the Court’s October 2026 Term, and marks the second time in five years that the Court has agreed to interpret NGA section 7.

...

Read More

Speaking Energy

July 6, 2026

On June 29, 2026, the United States Supreme Court issued Trump v. Slaughter, fundamentally reshaping presidential removal authority over independent regulatory agencies. The decision overruled a 90-year-old precedent established in Humphrey’s Executor v. United States, which had upheld the constitutionality of commissioner removal protections in the Federal Trade Commission Act (FTC Act). As written, the FTC Act permits a commissioner’s removal “only for inefficiency, neglect of duty, or malfeasance in office.” In Slaughter, the Court was asked to reevaluate this standard following the President’s removal of a Democratic-appointed FTC commissioner from office in 2025 without cause. Finding for the President, the Court held that removal was permissible because the FTC Act’s for-cause removal protections for commissioners violate the separation of powers, specifically, the President’s removal power under Article II. The Court explained that the FTC exercises executive power because it promulgates binding rules, investigates and enforces those rules through administrative adjudications, and brings civil enforcement actions in federal court. It found that because it exercises these executive powers, its commissioners “must therefore be controlled by the Chief Executive, in whom such power is vested.” While previous recent cases addressing the scope of the Removal Power, Seila Law LLC v. Consumer Financial Protection Bureau and Collins v. Yellen purported to preserve some kernel of Humphrey’s, the Court made clear that “[i]f anything more is left of Humphrey’s, we overrule it.”

...

Read More

Speaking Energy

June 25, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to the California Independent System Operator Corporation (CAISO) directing CAISO and CAISO transmission owners to show cause as to why CAISO’s tariff should not be found to be unjust and unreasonable (California Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (the Order)) because it fails to sufficiently:

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.