FERC Directs NERC to Propose Mandatory Reliability Standards Regarding Physical Security Risks to the Bulk-Power System

Mar 10, 2014

Reading Time : 4 min

Three-Step Approach

The FERC did not impose a “one size fits all” approach to protecting physical security, but directed NERC to include in the Reliability Standards a three-step approach to addressing physical security risks.

Step One:  Risk Assessment and Identification of “Critical Facilities”

First, the FERC directed that the Reliability Standards “should require owners or operators of the Bulk-Power System to perform a risk assessment” to identify their “critical facilities,” i.e., those which, “if rendered inoperable or damaged, could have a critical impact on the operation of the interconnection through instability, uncontrolled separation or cascading failures.”  The FERC did not require a specific type of risk assessment, but stated that the methodologies used to determine “critical facilities” should be “based on objective analysis, technical expertise, and experienced judgment.”  In addition, the Reliability Standards “should allow owners or operators to consider resilience of the grid in the risk assessment when identifying critical facilities, and the elements that make up those facilities, such as transformers that typically require significant time to repair or replace.”

Step Two:  Threat and Vulnerability Evaluation

Second, the FERC directed that the Reliability Standards should require owners or operators of “critical facilities” to evaluate potential threats and vulnerabilities to those facilities based on factors such as location, size, function, existing protections, and “attractiveness as a target.”  Thus, the FERC stated, the Reliability Standards should require owners or operators to tailor their threat and vulnerability evaluation “to the unique characteristics of the identified critical facilities and the type of attacks that can be realistically contemplated.”

Step Three:  Security Plans

Third, the FERC directed that the Reliability Standards should require owners or operators of critical facilities to develop, validate, and implement security plans “designed to protect against attacks to those . . . facilities based on the assessment of the potential threats and vulnerabilities to their physical security.”  The Reliability Standards “need not dictate specific steps an entity must take to protect against attacks,” but must require owners and operators of critical facilities to have plan that provides “an adequate level of protection against the potential physical threats and vulnerabilities they face.”

Confidentiality, Independent and Periodic Review, and Implementation

Because of the sensitive nature of the information related to all three steps, the FERC also required NERC to include in the proposed Reliability Standards a procedure to “ensure confidential treatment of sensitive or confidential information but still allow for the [FERC], NERC and the Regional Entities to review and inspect any information that is needed to ensure compliance with the Reliability Standards.”

In addition, the FERC noted that the risk assessments, threat and vulnerability evaluations, and security plans should be independently reviewed by an entity other than the owner or operator, such as the FERC, NERC, a Regional Entity, Reliability Coordinator, or other entity with appropriate expertise, and that the proposed Reliability Standards should require that all three “be periodically reevaluated and revised to ensure their continued effectiveness.”

The FERC did not impose an implementation timeline for the Reliability Standards, but required NERC to “develop an implementation plan that requires owners or operators of the Bulk-Power System to implement the Reliability Standards in a timely fashion, balancing the importance of protecting the Bulk-Power System from harm while giving the owners or operators adequate time to meaningfully implement the requirements.”

Commissioner Norris’s Concurrence and Concerns

In a separate statement, Commissioner Norris expressed support for the order, but noted several areas of concern.  First, Commissioner Norris noted that the procedural approach the FERC selected, which, due to the its ex parte rules, will limit communication and engagement between industry and the FERC, as well as the “uniquely expedited nature” of the standards development process, could weaken that process.  To mitigate these issues, Commissioner Norris encouraged broad participation in the NERC standards development process and the forthcoming FERC rulemaking proceeding.  Commissioner Norris also cautioned parties to “be mindful of the Commission’s expectation that the number of critical facilities identified will be relatively small compared to the number of facilities that comprise the Bulk-Power System and [to] strive for balance between the measures related to physical security and the costs for consumers.”

Second, Commissioner Norris expressed his concern regarding the sensitivity of information regarding the physical vulnerabilities of the power grid and urged Congress to expeditiously create a clearly-defined Freedom of Information Act exemption to facilitate the exchange of information important to the Reliability Standards development process among industry, the FERC, and NERC without fear of disclosure.

Third, Commissioner Norris expressed his concern that recent efforts to protect reliability have focused too narrowly on physical security.  Instead, Commissioner Norris argued, equal focus on and dedication of resources to other threats, including cyber-attacks, geomagnetic disturbances, electromagnetic pulses, and natural disasters, are necessary.

Finally, Commissioner Norris cautioned against overreaction to the widely-reported April 2013 attack on PG&E’s Metcalf Substation, which has received significant attention in recent months from legislators and regulators (as we discussed in prior posts available here, and here).  Specifically, Commissioner Norris noted that he remains concerned that “recent momentum will result in the electricity sector potentially spending billions of dollars erecting physical barriers to protect our grid infrastructure,” with “most if not all of those costs . . . passed through to ratepayers.”  Instead, Commissioner Norris believes that “the more prudent approach is to focus on building a smarter and more agile grid, incorporating better communication and coordination, to mitigate against the multiple forms of risks that we face,” as well as to “more readily integrate intermittent resources, increase demand-side management capabilities, enhance the competitiveness of the wholesale energy market and more.”

Potential Implications

Ultimately, the effect of the FERC’s order will depend on the outcomes of the NERC standards development process and FERC rulemaking proceeding.  For owners and operators of facilities that are part of the Bulk-Power System that already have assessed the risks to and vulnerabilities of their critical facilities and implemented protective measures, the Reliability Standards, as ultimately adopted, might not require significant further action or costs.  For other entities, the costs of compliance with the new Reliability Standards could be significant.  Either way, because of the expedited timeline for NERC to develop and propose the standards, NERC-registered entities should be sure to voice their concerns in the NERC and FERC proceedings.

Share This Insight

Previous Entries

Speaking Energy

July 8, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to ISO New England Inc. (ISO-NE) directing ISO-NE and ISO-NE participating transmission owners to show cause as to why ISO-NE’s tariff should not be found to be unjust and unreasonable (ISO New England Inc., 195 FERC ¶ 61,215 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

July 7, 2026

On June 29, 2026, the Supreme Court granted a petition for certiorari in Leonard Hoffmann v. WBI Energy Transmission, Inc. (Hoffmann), which presents the question whether section 7 of the Natural Gas Act (NGA) requires pipeline companies using federal eminent domain authority to pay landowners’ attorney’s fees in states where landowners can recover those fees under state law. In the decision giving rise to the Supreme Court’s review, the U.S. Court of Appeals for the Eighth Circuit held that a group of ranchers were not entitled to recover their $383,300 in attorney’s fees incurred while negotiating their compensation—creating a circuit split with four other courts of appeals. Hoffmann will be heard during the Court’s October 2026 Term, and marks the second time in five years that the Court has agreed to interpret NGA section 7.

...

Read More

Speaking Energy

July 6, 2026

On June 29, 2026, the United States Supreme Court issued Trump v. Slaughter, fundamentally reshaping presidential removal authority over independent regulatory agencies. The decision overruled a 90-year-old precedent established in Humphrey’s Executor v. United States, which had upheld the constitutionality of commissioner removal protections in the Federal Trade Commission Act (FTC Act). As written, the FTC Act permits a commissioner’s removal “only for inefficiency, neglect of duty, or malfeasance in office.” In Slaughter, the Court was asked to reevaluate this standard following the President’s removal of a Democratic-appointed FTC commissioner from office in 2025 without cause. Finding for the President, the Court held that removal was permissible because the FTC Act’s for-cause removal protections for commissioners violate the separation of powers, specifically, the President’s removal power under Article II. The Court explained that the FTC exercises executive power because it promulgates binding rules, investigates and enforces those rules through administrative adjudications, and brings civil enforcement actions in federal court. It found that because it exercises these executive powers, its commissioners “must therefore be controlled by the Chief Executive, in whom such power is vested.” While previous recent cases addressing the scope of the Removal Power, Seila Law LLC v. Consumer Financial Protection Bureau and Collins v. Yellen purported to preserve some kernel of Humphrey’s, the Court made clear that “[i]f anything more is left of Humphrey’s, we overrule it.”

...

Read More

Speaking Energy

June 25, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to the California Independent System Operator Corporation (CAISO) directing CAISO and CAISO transmission owners to show cause as to why CAISO’s tariff should not be found to be unjust and unreasonable (California Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (the Order)) because it fails to sufficiently:

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.