FERC Issues White Paper on Cybersecurity Incentives

Jun 23, 2020

Reading Time : 2 min

Background

Earlier this year, the Commission proposed to revise its existing transmission incentives policy under Section 219 of the Federal Power Act (FPA).1 Left out of that proposal was cybersecurity, an issue the Commission decided to address independently in a separate proceeding.2 The White Paper initiates that effort. Specifically, the White Paper discusses augmenting the current Critical Infrastructure Protection (CIP) Reliability Standards with an incentive-based approach pursuant to FPA Section 219.

The Commission’s CIP Reliability Standards, promulgated under FPA Section 215, have served as FERC’s primary tool for regulating cybersecurity practices. They require certain users, owners and operators of the bulk electric system to comply with requirements to safeguard critical transmission system assets. FERC categorizes assets according to the risk to the bulk electric system—high, medium or low—if the assets are compromised, with different requirements applying depending on the risk category. Most of the requirements apply to the high- and medium-risk categories.3   

In the Commission’s view, these standards establish an effective “technical baseline for cybersecurity practices,” but have limitations. For example, these mandatory standards are not particularly nimble in the face of rapidly evolving threats, nor do they apply to the full suite of operational technologies that can have an impact on the grid’s security. The incentive-based approach contemplated in the White Paper is intended to encourage utilities to adopt best practices and make voluntary investments in cybersecurity.

The White Paper

The White Paper proposes two approaches for identifying investments eligible for incentives. Under the first approach, a utility could seek incentive treatment for applying CIP Reliability Standards requirements to transmission facilities that are not subject to those requirements. For example, the utility could propose to apply standards applicable to high- and medium-risk assets to low-risk assets. This approach has the benefit of using an existing, familiar set of requirements.

The second approach would be based on an entirely different set of standards—the cybersecurity framework developed by the National Institute of Standards and Technology (NIST). Under this approach, an applicant would have to demonstrate that a cybersecurity investment meets NIST security controls and would exceed the requirements of the CIP Reliability Standards.

The Commission notes in the White Paper that utilities could be eligible for a return on equity (ROE) adder as high as 200 basis points under these contemplated reforms, although any such incentive treatment may be subject to a sunset provision.4 Given how quickly cybersecurity threats and best practices evolve, FERC proposes no more than three to five years as an appropriate sunset period. Moreover, the Commission notes the possibility that certain investments eligible for incentives may eventually become mandatory, in which case the incentive treatment would end at the earlier of the sunset date and the date when such investment(s) become mandatory.

As noted above, interested parties are invited to provide comments on the issues discussed in the White Paper. Parties may also address in their comments the 11 specific questions provided at the end of the White Paper.5


1 Elec. Transmission Incentives Policy Under Section 219 of the Fed. Power Act, Notice of Proposed Rulemaking, 170 FERC ¶ 61,204 (2020).

2 Id. P 5.

3 See White Paper, Appendix – CIP Reliability Standards Impact-Level Summary.

4 Non-ROE incentive rate treatment may be considered as well. Id. at 13.

5 See id. at 26-27.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.