PTC “Start of Construction” Clarifying Guidance Expected in a Week or Two

Jul 18, 2014

Reading Time : 1 min

The guidance is in response to requests from the wind industry for further clarification as to two issues. First, what level of physical work was required for projects, which did not opt to satisfy the 5 percent safe harbor, to be deemed to have started construction in 2013 as is necessary for PTC eligibility? Second, what level of legal stake must a developer have had in a project in 2013 to have purchased equipment pursuant to a master supply agreement with a manufacturer that is subsequently transferred to the project in order to enable the project to satisfy the 5 percent safe harbor?

Release of the clarifying guidance in the next week or two would be good news for the wind industry. It is already late in 2014 for projects to have time to raise the financing necessary to complete construction in order to be in placed in service by the end of 2015 as the safe harbor for PTC eligibility requires.

One can only hope that the government lawyers who have principal responsibility for the clarifying guidance have lined up the required approvals from their colleagues at Treasury and the IRS. Otherwise, summer vacation schedules of one or more senior tax officials could delay the guidance beyond the next week or two. Due to vacation schedules, July and August are traditionally slow periods for the issuance of tax guidance.


1 Bloomberg GE Earnings Call Transcript (Jul. 18, 2013).

Share This Insight

Previous Entries

Speaking Energy

June 25, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to the California Independent System Operator Corporation (CAISO) directing CAISO and CAISO transmission owners to show cause as to why CAISO’s tariff should not be found to be unjust and unreasonable (California Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (the Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 24, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to New York Independent System Operator, Inc. (NYISO) directing NYISO and NYISO transmission owners to show cause as to why NYISO’s tariff should not be found to be unjust and unreasonable (New York Independent System Operator, Inc., 195 FERC ¶ 61,216 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Midcontinent Independent System Operator, Inc. (MISO) directing MISO and MISO transmission owners to show cause as to why MISO’s tariff should not be found to be unjust and unreasonable (Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to PJM Interconnection, L.L.C. directing PJM and PJM transmission owners to show cause as to why PJM’s tariff should not be found to be unjust and unreasonable (PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (the Order)) because it fails to sufficiently:

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.