CAISO Proposes Queue Delay And Structural Changes To Interconnection Study Process

Mar 13, 2023

Reading Time : 5 min

On March 6, 2023, the California Independent System Operator Corp. (“CAISO”) released an Issue Paper and Straw Proposal outlining proposed modifications to its interconnection procedures in light of the significant volume of interconnection requests currently pending in its queue and that are expected in the coming years, including immediate adjustments to the study schedule for customers submitting requests as part of CAISO’s upcoming study cluster and long-term structural reforms that could have the effect of materially altering the landscape for companies seeking to develop resources within California.1

In the issue paper, the CAISO notes that it has been inundated in recent years with interconnection requests being developed to meet California’s decarbonization goals, with “[m]any of these requests . . . not located in areas considered optimal for additional transmission development, as determined by regulators and load-serving entities.”2 Although it has pursued several rounds of revisions to its interconnection rules over the past several years, the CAISO states that it has become clear that “more extreme measures are needed to make the [interconnection process] a viable process in light of the state’s vastly accelerated new resource procurement targets.”3

In order to address these issues, CAISO proposes to reimagine its interconnection process and pursue a two track reform:

  • Track 1 will focus on immediate adjustments to the schedule for the upcoming queue cluster that is scheduled to open on April 3, 2023—Queue Cluster 15 (“QC15”)—which it claims are necessary to allow CAISO to finish processing the requests currently being studied through Queue Cluster 14 (“QC14”).
  • Track 2 will focus on longer-term structural reforms to the interconnection process that would have the effect of prioritizing the processing of interconnection requests located in zones that have available transmission capacity or where transmission facilities are expected to be constructed through the regional planning process.

Track 1: Delaying QC15

CAISO states that “[s]imply layering a massive influx of new [QC15] interconnection requests,” on the existing QC14 projects being studied “is not an effective way to advance interconnection proposals.”4 At the same time, CAISO states that it would be inappropriate to delay the timeline for the submission of requests in QC15.  Accordingly, CAISO states that it will maintain the window for the submission of interconnection requests that is scheduled to open in April 2023.  However, CAISO plans to postpone the validation of QC15 interconnection requests until the QC14 phase II studies and results meetings have been completed.  Based on the current schedule, CAISO states that it does not anticipate resuming processing QC15 until approximately April 1, 2024.5

CAISO states that it intends to commence scoping and validation meetings once QC14 is complete, but that it will finalize the schedule for validation, studies, posting, and processing the requests as part of Track 2 of this initiative.6 CAISO also states that it anticipates providing customers in QC15 the opportunity to “refresh” their interconnection request (e.g., modify their original request) or withdraw for minimal or no cost at any time until study work begins.7

Although the issue paper does not fully detail the longer-term implications of a one-year delay in the validation of requests in QC15, CAISO acknowledges that its proposal could create timing challenges for developers.  CAISO singles out offshore wind resources as a class of developer that could be most impacted by the proposed delay given the long development timeline of these resources.  Accordingly, CAISO states that it plans to evaluate whether it may be possible to study offshore wind and certain other long-lead time resources through a separate process.8

Track 2: Structural Reforms

Track 2 of the initiative “will focus on the transformative changes to the interconnection process needed to achieve” the strategic objectives set out in a December 2022 Memorandum of Understanding (“MOU”) signed by CAISO, the California Public Utilities Commission (“CPUC”), and the California Energy Commission that established a framework for greater coordination among the agencies on resource and transmission planning.9 In order to achieve these objectives, CAISO states that the interconnection process must be redesigned to:

  • prioritize interconnection customers that seek to utilize available capacity or that are located in zones with planned capacity additions that have been identified in the transmission planning process based on state resource planning;
  • limit the project capacity studied within these priority zones to reasonable amounts that support the state’s resource planning goals; and
  • ensure that the study results that are obtained through the interconnection process provide load-serving entities with information that supports their resource procurement functions.10

Although CAISO does not propose a definitive framework for the types of reforms that it plans to make, it does outline a number of potential design elements that CAISO believes have the potential to achieve the intended objectives:  

  • Accepting or processing only interconnection requests where the transmission system has available existing or planned capacity identified in the CAISO’s transmission plan based on CPUC portfolios;11
  • Limit the number of interconnection requests in a study area based on the transmission capacity being planned for that location;12
  • Require projects to have a power purchase agreement to be shortlisted to proceed to phase II studies;13 and
  • Only open a new interconnection request window when warranted as opposed to on an annual basis.14

Notably, CAISO states that it plans to pursue development and implementation of its proposal on a timeline that would allow it to apply these reforms to interconnection requests in QC15.

Next Steps

CAISO is holding a conference call to discuss the Issue Paper on March 13, 2023, with comments due by March 27, 2023.  After taking comments, CAISO plans on issuing a final proposal and draft tariff language for Track 1 by April 10, 2023, with the goal of presenting the proposal for approval by the CAISO Board of Governors on May 17, 2023.

Conclusion

The merits of CAISO’s proposal undoubtedly will be the subject of debate in its stakeholder process.  It is worth noting, however, that CAISO’s proposal to prioritize processing interconnection requests in designated regions within its footprint and to limit the submission of interconnection requests represents a departure from the current manner in which interconnection requests are ordered and studied.  Currently, transmission providers generally prioritize interconnection requests based on the order in which they received or based on a “first-ready, first-served” approach that prioritizes interconnection customers that demonstrate that they are making progress towards the development of their projects.  Additionally, interconnection customers generally are free to request interconnection service at any point on the grid without any impact on the relative queue priority of their projects.  In contrast, CAISO’s proposal would prioritize requests based on location and potentially limit the ability of project developers to obtain interconnection service at other locations or even in more favored locations.  CAISO’s proposal illustrates the challenges that grid operators and market participants are facing as the energy transition strains existing regulatory paradigms and processes.


1 California Independent System Operator, 2023 Interconnection Process Enhancements (March 6, 2023), http://www.caiso.com/InitiativeDocuments/Issue-Paper-and-Straw-Proposal-Interconnecton-Process-Enhancements-2023-Mar132023.pdf (“Issue Paper”).

2 Issue Paper at 3.

3 Id. at 4.

4 Id. at 6.

5 Id. at 9.

6 Id. at 9-10.

7 Id. at 9.

8 Id. at 11.

9 Id.

10 Id. at 12.

11 Id. at 12-13.

12 Id. at 13-14.

13 Id. at 14.

14 Id. at 14-15.

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.