FERC Approves Settlement with Bitcoin Mining Company for Violations of PJM Must-Offer Requirements

February 11, 2025

Reading Time : 2 min

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

Stronghold is a Bitcoin-focused crypto asset mining company whose primary business is to purchase power plants, install Bitcoin mining operations and subsequently sell power in the wholesale markets or mine Bitcoin, depending on which option is more profitable. Stronghold and its subsidiary, Scrubgrass Reclamation Company, L.P. (Scrubgrass), own and operate the Scrubgrass power plant in northwest Pennsylvania. From 2018 to 2022, Scrubgrass operated as a capacity resource and had received a capacity supply obligation of 85 MW. As a capacity resource, Scrubgrass was required to (1) offer its installed capacity into the PJM day-ahead and real-time markets each day if it was not on outage or derate; and (2) be available for scheduling and dispatch unless the resource indicated that it would only be available during emergencies. According to OE, Stronghold violated these obligations during the period from June 2021 through May 2022 by reducing the quantity of energy offered into the markets when it determined that it would be more favorable to use the output from the plant to mine Bitcoin rather than sell energy into the market.

Notably, OE staff also alleged that Stronghold violated the PJM tariff by using energy sourced from the PJM markets to power its Bitcoin operations. Specifically, staff alleged that Stronghold “bought power from PJM at wholesale rates under the guise of Station Power but did not use the power for Station Power.”3 Neither the Commission’s order nor the Agreement clearly identifies the tariff provisions that Stronghold violated by purchasing energy from the PJM markets to support its Bitcoin operations or any communications that Stronghold had with PJM about these purchases. However, the PJM tariff defines “Station Power” as “energy used for operating the electric equipment on the site of a generation facility . . . or for the heating, lighting, air-conditioning and office equipment needs of buildings on the site of such a generation facility that are used in the operation, maintenance, or repair of the facility.”4 Presumably, OE determined that these purchases did not fall within the definition of Station Power because they were made to support Bitcoin mining rather than plant operations. This is consistent with guidance issued by PJM in March 2024 confirming that “[c]o-located load is not equivalent to Station Power load.”5

Pursuant to the Agreement, Stronghold admitted to certain violations and paid approximately $1.4 million to resolve the investigation, including approximately $741,000 in civil penalties and $679,000 in disgorgement to PJM. It also agreed to provide compliance training to relevant personnel and assume compliance reporting obligations.


1 Stronghold Digital Mining Inc., 190 FERC ¶ 61,059 (2025) (“Order”).

2 See, e.g., PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024).

3 Order, Stipulation and Consent Agreement at P 14.

4 PJM Tariff, Part I, Section 1 (defining “Station Power”).

5 PJM Guidance on Co-Located Load (Updated Apr. 17, 2024), available at: pjm-guidance-on-co-located-load.ashx.

Share This Insight

Previous Entries

Speaking Energy

July 8, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to ISO New England Inc. (ISO-NE) directing ISO-NE and ISO-NE participating transmission owners to show cause as to why ISO-NE’s tariff should not be found to be unjust and unreasonable (ISO New England Inc., 195 FERC ¶ 61,215 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

July 7, 2026

On June 29, 2026, the Supreme Court granted a petition for certiorari in Leonard Hoffmann v. WBI Energy Transmission, Inc. (Hoffmann), which presents the question whether section 7 of the Natural Gas Act (NGA) requires pipeline companies using federal eminent domain authority to pay landowners’ attorney’s fees in states where landowners can recover those fees under state law. In the decision giving rise to the Supreme Court’s review, the U.S. Court of Appeals for the Eighth Circuit held that a group of ranchers were not entitled to recover their $383,300 in attorney’s fees incurred while negotiating their compensation—creating a circuit split with four other courts of appeals. Hoffmann will be heard during the Court’s October 2026 Term, and marks the second time in five years that the Court has agreed to interpret NGA section 7.

...

Read More

Speaking Energy

July 6, 2026

On June 29, 2026, the United States Supreme Court issued Trump v. Slaughter, fundamentally reshaping presidential removal authority over independent regulatory agencies. The decision overruled a 90-year-old precedent established in Humphrey’s Executor v. United States, which had upheld the constitutionality of commissioner removal protections in the Federal Trade Commission Act (FTC Act). As written, the FTC Act permits a commissioner’s removal “only for inefficiency, neglect of duty, or malfeasance in office.” In Slaughter, the Court was asked to reevaluate this standard following the President’s removal of a Democratic-appointed FTC commissioner from office in 2025 without cause. Finding for the President, the Court held that removal was permissible because the FTC Act’s for-cause removal protections for commissioners violate the separation of powers, specifically, the President’s removal power under Article II. The Court explained that the FTC exercises executive power because it promulgates binding rules, investigates and enforces those rules through administrative adjudications, and brings civil enforcement actions in federal court. It found that because it exercises these executive powers, its commissioners “must therefore be controlled by the Chief Executive, in whom such power is vested.” While previous recent cases addressing the scope of the Removal Power, Seila Law LLC v. Consumer Financial Protection Bureau and Collins v. Yellen purported to preserve some kernel of Humphrey’s, the Court made clear that “[i]f anything more is left of Humphrey’s, we overrule it.”

...

Read More

Speaking Energy

June 25, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to the California Independent System Operator Corporation (CAISO) directing CAISO and CAISO transmission owners to show cause as to why CAISO’s tariff should not be found to be unjust and unreasonable (California Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (the Order)) because it fails to sufficiently:

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.