FERC Approves Settlement with Bitcoin Mining Company for Violations of PJM Must-Offer Requirements

February 11, 2025

Reading Time : 2 min

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

Stronghold is a Bitcoin-focused crypto asset mining company whose primary business is to purchase power plants, install Bitcoin mining operations and subsequently sell power in the wholesale markets or mine Bitcoin, depending on which option is more profitable. Stronghold and its subsidiary, Scrubgrass Reclamation Company, L.P. (Scrubgrass), own and operate the Scrubgrass power plant in northwest Pennsylvania. From 2018 to 2022, Scrubgrass operated as a capacity resource and had received a capacity supply obligation of 85 MW. As a capacity resource, Scrubgrass was required to (1) offer its installed capacity into the PJM day-ahead and real-time markets each day if it was not on outage or derate; and (2) be available for scheduling and dispatch unless the resource indicated that it would only be available during emergencies. According to OE, Stronghold violated these obligations during the period from June 2021 through May 2022 by reducing the quantity of energy offered into the markets when it determined that it would be more favorable to use the output from the plant to mine Bitcoin rather than sell energy into the market.

Notably, OE staff also alleged that Stronghold violated the PJM tariff by using energy sourced from the PJM markets to power its Bitcoin operations. Specifically, staff alleged that Stronghold “bought power from PJM at wholesale rates under the guise of Station Power but did not use the power for Station Power.”3 Neither the Commission’s order nor the Agreement clearly identifies the tariff provisions that Stronghold violated by purchasing energy from the PJM markets to support its Bitcoin operations or any communications that Stronghold had with PJM about these purchases. However, the PJM tariff defines “Station Power” as “energy used for operating the electric equipment on the site of a generation facility . . . or for the heating, lighting, air-conditioning and office equipment needs of buildings on the site of such a generation facility that are used in the operation, maintenance, or repair of the facility.”4 Presumably, OE determined that these purchases did not fall within the definition of Station Power because they were made to support Bitcoin mining rather than plant operations. This is consistent with guidance issued by PJM in March 2024 confirming that “[c]o-located load is not equivalent to Station Power load.”5

Pursuant to the Agreement, Stronghold admitted to certain violations and paid approximately $1.4 million to resolve the investigation, including approximately $741,000 in civil penalties and $679,000 in disgorgement to PJM. It also agreed to provide compliance training to relevant personnel and assume compliance reporting obligations.


1 Stronghold Digital Mining Inc., 190 FERC ¶ 61,059 (2025) (“Order”).

2 See, e.g., PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024).

3 Order, Stipulation and Consent Agreement at P 14.

4 PJM Tariff, Part I, Section 1 (defining “Station Power”).

5 PJM Guidance on Co-Located Load (Updated Apr. 17, 2024), available at: pjm-guidance-on-co-located-load.ashx.

Share This Insight

Previous Entries

Speaking Energy

February 10, 2026

The global energy sector enters 2026 amid major policy shifts, geopolitical tension and evolving market dynamics. The Trump administration’s reversal of Biden-era climate initiatives and renewed emphasis on domestic production have reshaped the policy landscape, offering a more favorable regulatory environment even as conflicts abroad, oil price volatility and shifting trade policies tempered deal activity through 2025.

...

Read More

Speaking Energy

January 22, 2026

On January 16, 2026, the National Energy Dominance Council (NDEC) and governors from each of the 13 states in PJM issued a Statement of Principles urging PJM Interconnection, L.L.C. (PJM) to hold an emergency backstop auction and take other measures to support the entry of new capacity to preserve the reliability of the PJM region. The Statement of Principles calls on PJM to expeditiously file with the Federal Energy Regulatory Commission (FERC or the Commission) tariff revisions that would overhaul aspects of PJM’s market rules to address rising electricity prices and growing reliability risks in the PJM region. The Statement of Principles comes at a time of growing concern that PJM will not have sufficient capacity in the coming years to meet demand due to the retirement of existing generation resources, the glacial pace of new entry and projected increased demand associated with data center development.

...

Read More

Speaking Energy

December 21, 2025

On December 19, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued its much-anticipated order on show cause proceeding concerning the co-location of generation and load within the PJM Interconnection, L.L.C. (PJM) market.[1] In the order, the Commission finds that PJM’s tariff is unjust and unreasonable because it does not provide sufficient clarity on the rates, terms, and conditions of service applicable to generators serving Co-Located Load and does not include transmission services appropriate for customers that are willing and able to limit their use of the transmission system in certain conditions. 

...

Read More

Speaking Energy

November 25, 2025

We are pleased to share the program materials and a recording of Akin’s recently presented webinar, “Navigating the Evolving Landscape of Corporate PPAs.”

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.