FERC Mandates New Supplemental Environmental Impact Statement to Align with Expected Court Litigation

December 5, 2024

Reading Time : 2 min

On November 27, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued Venture Global CP2 LNG, LLC,1 an order that sets aside, in part, the Commission’s prior authorization of the CP2 LNG Terminal and CP Express Pipeline Project (collectively, the CP2 Project) under sections 3 and 7 of the Natural Gas Act (NGA). In anticipation of future appellate challenges to its authorization of the CP2 Project, FERC ordered the initiation of a supplemental environmental impact statement (SEIS) process under the National Environmental Policy Act (NEPA) to assess the CP2 Project’s contribution to cumulative air impacts for nitrogen dioxide (NO2) and particulate matter less than 2.5 micrometers (PM2.5). Accordingly, FERC stated that it would not allow construction to commence on the CP2 Project’s proposed liquefied natural gas (LNG) export terminal and related feed gas pipeline until the SEIS process concluded and a subsequent order was issued. Concurrent with its Venture Global order, FERC issued a projected schedule for the NEPA process that does not conclude until July 24, 2025. Construction on the CP2 Project had been expected to be imminent, with the project sponsor seeking a partial authorization to proceed with construction only hours prior to Venture Global’s issuance.

FERC states that the primary motivation for initiating the new SEIS process is a remand order it received in July for a different LNG export terminal project in Healthy Gulf et al. v. FERC. In Healthy Gulf, the U.S. Court of Appeals for the District of Columbia (D.C. Circuit) found FERC’s cumulative effects determination for air quality to be deficient as related to that underlying project’s NO2and PM2.5impacts. Because FERC’s initial approval for the CP2 Project had used a similar air quality analysis, it deemed its approval to be vulnerable to legal challenges. And, FERC determined that it could not perform a new analysis without reopening the NEPA process for public comment to align with a subsequent D.C. Circuit decision, City of Port Isabel v. FERC.

Venture Global is particularly noteworthy because it may be the first time FERC has proactively stalled construction of a major infrastructure project, and initiated an SEIS on its own accord, without being ordered to do so by a federal court. It is also at odds with FERC’s order of October 1, 2024, denying a stay of construction sought by CP2 Project opponents, and other infrastructure projects that continue to move forward with construction or operation while FERC runs a subsequent SEIS process. The decision suggests that a string of losses in the D.C. Circuit—in Healthy Gulf, Port Isabel and New Jersey Conservation Foundation v. FERC—had a deep impact on FERC’s leadership, and increased its resolve to avoid similar outcomes in future cases. Moreover, because the decision was bipartisan, with all Commissioners voting in favor (apart from Commission Chang, who did not participate), a reversal on rehearing is unlikely.


1 189 FERC ¶ 61,148 (2024).

Share This Insight

Previous Entries

Speaking Energy

March 19, 2026

International trade policy has emerged as a dominant force shaping the oil & gas sector, with sweeping tariffs imposed on products from virtually every nation using authorities including IEEPA, Section 232 and Section 301. President Trump's "America First Trade Policy" leverages duties as negotiation tools to secure bilateral deals featuring significant oil & gas purchase commitments, making trade considerations essential for any cross-border transaction. Energy dominance serves as a cornerstone of the administration's economic and national security strategy, placing the industry squarely in the spotlight. 

...

Read More

Speaking Energy

March 10, 2026

Federal energy regulators are assuming expanded roles as the administration prioritizes energy dominance and infrastructure development to meet unprecedented power demand. FERC Chairman Laura Swett has vowed to expedite data center interconnections while addressing jurisdictional challenges, warning that unmet electricity demand could drive data centers abroad and create national security risks. The agency is processing pipeline applications faster than in prior years and considering blanket authorizations for certain LNG and hydroelectric projects to streamline approvals. 

Pipeline projects previously stalled by Clean Water Act permits are being revitalized, particularly in northeastern states where historically high electricity prices have increased openness to natural gas infrastructure. The Department of Energy is expanding its emergency authority to require retention of generation resources and has granted major LNG export approvals, signaling commitment to expanding U.S. export capacity under a streamlined framework that deprioritizes climate considerations.  

The Administration is bullish on the opportunities for the U.S. energy industry in Venezuela and eager to support companies willing to navigate the political risk inherent in the operations at the moment. Early meetings with President Trump and industry leaders showed the path forward may be longer and more complex than anticipated by the President. 

As permitting reforms advance and the pendulum swings toward fossil fuel favorability, the regulatory and policy landscape is fundamentally reshaping energy infrastructure development timelines and investment opportunities. 

Oil & Gas in 2026: Energy Policy & Regulation 

Delve into the complete regulatory & policy outlook at our Oil & Gas in 2026 report.

...

Read More

Speaking Energy

March 3, 2026

Macroeconomic turbulence and volatile commodity markets significantly influenced oil & gas M&A activity throughout 2025, with deals showing renewed momentum only in the year's second half.  

...

Read More

Speaking Energy

February 24, 2026

On February 19, 2026, the Federal Energy Regulatory Commission (FERC) issued an order rescinding the soft price cap for bilateral spot market energy sales in the Western Electricity Coordinating Council (WECC) region.1 As previously covered, on July 15, 2025, FERC initiated a Federal Power Act Section 206 proceeding following the D.C. Circuit’s decision finding that FERC must apply the Mobile-Sierra public interest standard before ordering refunds for above-cap bilateral sales and vacating FERC’s orders requiring refunds for certain bilateral spot market transactions in the WECC region that exceeded the $1,000 MWh soft price cap.2 FERC’s Order follows through on the proposal it made last July to eliminate the WECCs soft price cap and marks a recognition that Western wholesale markets have evolved over the past two decades to become sufficiently competitive to render the soft price cap unnecessary.  

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.