FERC Order No. 2023 on Generator Interconnection Reforms Published in Federal Register, Setting Effective Date and Current Compliance Deadline

September 6, 2023

Reading Time : 1 min

By: Stephen J. Hug, Emily P. Mallen, Ben N. Reiter, Angelica Gonzalez (Paralegal)

On September 6, 2023, the Federal Energy Regulatory Commission’s (FERC or the “Commission”) Order No. 2023, “Improvements to Generator Interconnection Procedures and Agreements” (the “Final Rule”), was published in the Federal Register. The Final Rule had been issued by FERC on July 28, 2023, and requests for rehearing and clarification have already been filed with the agency by numerous transmission owners, generation developers, trade associations and regional transmission organizations (RTOs) and independent system operators affected by the Final Rule. Akin hosted a webinar on the Final Rule on August 3, 2023, providing analysis on the Final Rule’s requirements to (1) increase how quickly requests in the interconnection queue are processed, (2) replace the previous “first-come, first-served” process with a “first-ready, first-served” cluster study process and (3) incorporate technological advancements in generation and transmission into the interconnection process. The published version of the Final Rule establishes an effective date for Order No. 2023 of November 6, 2023. 

Order No. 2023 requires transmission providers to submit compliance filings revising their tariffs to reflect the requirements of the Final Rule within 90 calendar days of publication in the Federal Register. Currently, the deadline for compliance filings is December 5, 2023. However, several RTOs have submitted a motion requesting that FERC extend the compliance deadline to 90 days after the Commission issues an order on rehearing.1 It remains to be seen whether FERC will be willing to grant an extension. Regardless of the timing of the compliance filings, it is likely that these filings will attract significant protests and comments, so market participants and other electric industry stakeholders will want to keep close tabs on developments in the region(s) in which they operate or plan to do business.


1 Improvements to Generator Interconnection Procedures & Agreements, Motion to Extend the Compliance Deadline and Request for Expedited Action of the Joint RTOs, Docket No. RM22-14-000 (filed Aug. 28, 2023).

Share This Insight

Previous Entries

Speaking Energy

June 25, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to the California Independent System Operator Corporation (CAISO) directing CAISO and CAISO transmission owners to show cause as to why CAISO’s tariff should not be found to be unjust and unreasonable (California Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (the Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 24, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to New York Independent System Operator, Inc. (NYISO) directing NYISO and NYISO transmission owners to show cause as to why NYISO’s tariff should not be found to be unjust and unreasonable (New York Independent System Operator, Inc., 195 FERC ¶ 61,216 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Midcontinent Independent System Operator, Inc. (MISO) directing MISO and MISO transmission owners to show cause as to why MISO’s tariff should not be found to be unjust and unreasonable (Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to PJM Interconnection, L.L.C. directing PJM and PJM transmission owners to show cause as to why PJM’s tariff should not be found to be unjust and unreasonable (PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (the Order)) because it fails to sufficiently:

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.