FERC Proposes to Eliminate Reactive Power Compensation for Generation Resources

March 25, 2024

Reading Time : 5 min

On March 21, 2024, the Federal Energy Regulatory Commission (FERC or the Commission) issued its Compensation for Reactive Power Within the Standard Power Factor Range Notice of Proposed Rulemaking,1 which proposes to prohibit generators from receiving compensation from transmission providers for providing reactive power within the standard power factor range or “deadband.” The NOPR, if adopted, would represent a departure from the Commission’s current policy that requires transmission providers to compensate generators for providing reactive power within the deadband if the transmission provider pays its own or affiliated generation for reactive power.2 The Commission’s proposal to eliminate reactive power compensation comes at a time when numerous markets are facing imminent resource adequacy shortfalls as a result of the retirement of existing generation resources.3

The NOPR explains that generators can provide reactive power—which is critical to ensuring system stability so that real power may be transmitted—within the deadband at “no cost” or de minimis costs that can be recovered through energy or capacity payments.4 Thus, according to the Commission, customers in regions where generators are compensated for reactive power may be paying for service “without a sufficient economic basis or justification.”5 The NOPR asserts that in these regions where generators are compensated for reactive power “the costs to transmission customers have increased substantially without any commensurate increase in benefits.”6 Accordingly, the NOPR preliminary finds that allowing transmission providers to compensate generators for reactive power within the deadband has resulted in unjust and unreasonable transmission rates because:

  1. Generators already provide reactive power within the standard power factor range at no cost or de minimis cost.7
  2. Compensation provided to generators for providing reactive power within the standard factor range may result in “undue compensation or other market distortions.8
  3. Generators are obligated to provide reactive power within the standard power factor range as a condition of interconnection and consistent with good utility practice.9

The NOPR credits statements made by parties in response to its November 18, 2021, Notice of Inquiry10that any incremental costs generators incur for providing reactive power “are typically captured in [their] resource offers”11and that the fact that generators are not compensated in California Independent System Operator Corporation, Southwest Power Pool Inc. and other regions indicates that “perhaps generators are adequately recovering their costs through some other means.”12

The NOPR identifies a number of issues with FERC's existing policy for providing reactive power, including that such compensation is not tied to a particular geographic need, the process for establishing resource specific reactive cost-of-service rates is “resource-intensive, time-intensive, and administratively burdensome for ratepayers, transmission providers, and market participants,” and the methodology for testing and verifying reactive capability is unduly burdensome.13 The NOPR also asserts, without elaboration, that allowing resources to recover the costs of providing reactive power within the deadband in organized competitive wholesale markets “risks overcompensation and market distortion in ways that did not exist prior to the existence of organized markets.”14

The NOPR provides a preemptory defense that eliminating reactive power compensation will not harm reliability. The Commission “preliminarily disagrees” with the argument that reactive power compensation is necessary given the increase of non-synchronous generating facilities because it “preliminarily find[s] that requiring transmission providers to continue paying for reactive power already required by a generating facility’s interconnection agreement is not necessary to ensure that generating facilities provide reactive power when required.”15

Similarly, the NOPR provides a preemptory defense against the argument that it will prevent generators from recovering their costs. The Commission discounts arguments that reactive power compensation is important for financing generation facilities stating that “although the prospect of receiving separate, fixed reactive power payments may be beneficial for developing certain generating facilities, resource developers continue to develop new generating facilities in regions without such payments.”16 The NOPR also asserts that independent power producers can recover their costs in other ways, “such as through higher power sales rates of their own.”17

Despite its preliminary findings, the NOPR seeks comment on, among other issues, the following:

  • The reliability impact of prohibiting transmission providers from including in their transmission rates any charges associated with the supply of reactive power within the standard power factor range from a generating facility in regions where generating facilities currently receive such compensation.18
  • Whether, and if so how, the elimination of separate reactive power payments will affect generating facilities’ ability to recover their costs in the markets that currently provide reactive power compensation within the standard power factor range.19
  • Whether, and if so how, eliminating separate reactive power compensation within the standard power factor range may affect investment decisions to build, or finish building, generation facilities, and whether, and if so how, the elimination could otherwise affect generators’ business decisions in those markets.20
  • If the Commission allows existing generation resources that have previously received compensation for reactive power supply to continue to receive compensation for a limited period while prohibiting new generation resources from receiving reactive power compensation, how should it determine eligibility for continued compensation in a manner that is just and reasonable and not unduly discriminatory or preferential.21

Comments on the NOPR are due 60 days after the date of publication of the NOPR in the Federal Register.


1 Compensation for Reactive Power Within the Standard Power Factor Range, 186 FERC ¶ 61,203 (2024) (NOPR).

2 Standardization of Generator Interconnection Agreements & Procs., Order No. 2003, 104 FERC ¶ 61,103 (2003), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh’g, Order No. 2003-B, 109 FERC ¶ 61,287 (2004), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401, at P 42 (2005), aff’d sub nom. Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007).

3 See e.g., Monitoring Analytics, LLC, State of the Market Report for PJM at 1 (Mar. 14, 2024), available at: https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2023.shtml (“One of the key challenges facing the PJM markets is the potentially high level of expected thermal resource retirements between now and 2030 with no clear source of replacement capacity. Although the exact numbers may vary, an estimated total of between 24,000 MW and 58,000 MW of thermal resources are at risk of retirement, including 4,285 MW of announced retirements, 19,635 MW of retirements as a result of state and federal environmental regulations, and 33,744 MW of retirements for economic reasons, based on expected forward prices.”);

4 NOPR at P 8.

5 Id. at P 25.

6 Id. at P 26.

7 Id. at P 29.

8 Id. at P 28.

9 Id. at P 29.

10 Reactive Power Capability Compensation, 177 FERC ¶ 61,118 (2021).

11 NOPR at P 31 (quoting Reactive Power Capability Compensation, Docket No. RM22-2-000, Comments of Southwest Power Pool Inc. (Feb. 22, 2022) (“Variable costs of generating reactive power are de minimis and are generally limited to changes in losses within the generating facility which are part of the overall efficiency of the resource and, as such, are typically captured in the resource offers submitted to the SPP Integrated Marketplace.”)).

12 Id. (quoting Reactive Power Capability Compensation, Docket No. RM22-2-000, Initial Comments of Old Dominion Electric Cooperative, Northern Virginia Electric Cooperative Inc. and Dominion Energy Services Inc. at 9 (Feb. 22, 2022)).

13 Id.at P 36.

14 Id. at P 39.

15 Id. at P 43.

16 Id. at P 45.

17 Id. at PP 15, 47.

18 Id. at P 47.

19 Id. at P 49.

20 Id.

21 Id. at P 56.

Share This Insight

Previous Entries

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.