5th Circuit Denies Louisiana Public Service Commission’s Petition for Review of FERC’s Entergy Bandwidth

Dec 1, 2014

Reading Time : 3 min

In the petition, LPSC challenged (1) FERC’s interpretation of Service Schedule MSS-3 of the System Agreement, which contains the formula rate, as requiring formula inputs to be the “actual amounts” reported on FERC Form 1 filings, (2) FERC’s “reversal” of its prior interpretation that annual bandwidth implementation proceedings could be used to challenge unjust and unreasonable cost inputs into the formula and, (3) FERC’s ruling that casualty loss deferred taxes should be included in the 2008 bandwidth calculations.  The 5th Circuit denied all of these appeals. 

First, upholding FERC’s interpretation that the tariff requires the “actual amounts” from FERC Form 1 filings, the court pointed to the plain language of Footnotes 1 and 2 of Service Schedule MSS-3, which states that “All Rate Base, Revenue and Expense items shall be based on the actual amounts on the Company’s books,” and “Rate Base values shall be based on the actual balances on the Company’s books.”2  The court concluded that FERC’s interpretation is “a plain reading of the System Agreement . . . and is not arbitrary or irrational.”3

Second, the 5th Circuit addressed LPSC’s challenge to FERC’s reversal of its position regarding the proper scope of bandwidth implementation proceedings, where FERC ultimately concluded that challenges to the justness and reasonableness of formula inputs cannot be raised in bandwidth implementation proceedings. Previously, FERC had indicated that it would review the justness and reasonableness of cost inputs in the annual bandwidth proceedings. 

The 5th Circuit upheld FERC’s actions, despite conceding that FERC’s “early orders” stated that challenges to formula inputs could be raised in bandwidth implementation proceedings.4  The 5th Circuit reasoned that FERC “corrected its previous interpretation in its very first ruling on an annual bandwidth proceeding . . . changed its interpretation in light of its gained experience conducting annual bandwidth proceedings, explained its new interpretation of the System Agreement, and consistently has interpreted the System Agreement after the change.” The court concluded that “FERC offered a reasoned explanation for its approach; no more is required.”5

Finally, the 5th Circuit denied LPSC’s appeal of FERC’s ruling that Entergy must include casualty loss Accumulated Deferred Income Taxes (ADIT) in its third bandwidth calculation.  LPSC challenged FERC’s decision on the grounds that (1) LPSC did not receive notice that casualty loss ADIT would be included, and (2) FERC failed to provide a rational basis for its inclusion.  Addressing each challenge, the 5th Circuit first found that LPSC did in fact have notice, stating, “After Entergy submitted its filing letter, FERC issued Op. No. 505, which, in response to LPSC’s challenge, held that Entergy must include storm-related NOL ADIT in eligible accounts in the bandwidth formula. . . LPSC was certainly on notice that Entergy’s justification for excluding casualty loss ADIT . . . was no longer valid.”6 The court then found that FERC’s decision was reasonable, since “FERC thoroughly explained its reasons for including casualty loss ADIT amounts in the bandwidth calculation,” citing the plain language of the System Agreement, which “which expressly requires that ADIT amounts recorded in FERC account 282 [including the casualty loss ADIT in this proceeding] be included in the bandwidth formula to the extent they are includable for cost-of-service purposes.”7

The 5th Circuit’s decision (as revised November 18, 2014) is available here.


1 La. Pub. Serv. Comm’n v. FERC, No. 13-60874, slip op. at 3 (5th Cir. Nov. 14, 2014); see also La. Pub. Serv. Comm’n v. Entergy Servs., Inc., 146 FERC ¶ 61,152 at P 3 (2014).

2 La. Pub. Serv. Comm’n v. FERC, No. 13-60874, slip op. at 13 (5th Cir. Nov. 14, 2014) (emphasis added).

3 Id. at 14.

4 Id. at 15.

5 Id. at 16.

6 Id. at 23 (emphasis in original).

7 Id. at 25.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.