5th Circuit Denies Louisiana Public Service Commission’s Petition for Review of FERC’s Entergy Bandwidth

Dec 1, 2014

Reading Time : 3 min

In the petition, LPSC challenged (1) FERC’s interpretation of Service Schedule MSS-3 of the System Agreement, which contains the formula rate, as requiring formula inputs to be the “actual amounts” reported on FERC Form 1 filings, (2) FERC’s “reversal” of its prior interpretation that annual bandwidth implementation proceedings could be used to challenge unjust and unreasonable cost inputs into the formula and, (3) FERC’s ruling that casualty loss deferred taxes should be included in the 2008 bandwidth calculations.  The 5th Circuit denied all of these appeals. 

First, upholding FERC’s interpretation that the tariff requires the “actual amounts” from FERC Form 1 filings, the court pointed to the plain language of Footnotes 1 and 2 of Service Schedule MSS-3, which states that “All Rate Base, Revenue and Expense items shall be based on the actual amounts on the Company’s books,” and “Rate Base values shall be based on the actual balances on the Company’s books.”2  The court concluded that FERC’s interpretation is “a plain reading of the System Agreement . . . and is not arbitrary or irrational.”3

Second, the 5th Circuit addressed LPSC’s challenge to FERC’s reversal of its position regarding the proper scope of bandwidth implementation proceedings, where FERC ultimately concluded that challenges to the justness and reasonableness of formula inputs cannot be raised in bandwidth implementation proceedings. Previously, FERC had indicated that it would review the justness and reasonableness of cost inputs in the annual bandwidth proceedings. 

The 5th Circuit upheld FERC’s actions, despite conceding that FERC’s “early orders” stated that challenges to formula inputs could be raised in bandwidth implementation proceedings.4  The 5th Circuit reasoned that FERC “corrected its previous interpretation in its very first ruling on an annual bandwidth proceeding . . . changed its interpretation in light of its gained experience conducting annual bandwidth proceedings, explained its new interpretation of the System Agreement, and consistently has interpreted the System Agreement after the change.” The court concluded that “FERC offered a reasoned explanation for its approach; no more is required.”5

Finally, the 5th Circuit denied LPSC’s appeal of FERC’s ruling that Entergy must include casualty loss Accumulated Deferred Income Taxes (ADIT) in its third bandwidth calculation.  LPSC challenged FERC’s decision on the grounds that (1) LPSC did not receive notice that casualty loss ADIT would be included, and (2) FERC failed to provide a rational basis for its inclusion.  Addressing each challenge, the 5th Circuit first found that LPSC did in fact have notice, stating, “After Entergy submitted its filing letter, FERC issued Op. No. 505, which, in response to LPSC’s challenge, held that Entergy must include storm-related NOL ADIT in eligible accounts in the bandwidth formula. . . LPSC was certainly on notice that Entergy’s justification for excluding casualty loss ADIT . . . was no longer valid.”6 The court then found that FERC’s decision was reasonable, since “FERC thoroughly explained its reasons for including casualty loss ADIT amounts in the bandwidth calculation,” citing the plain language of the System Agreement, which “which expressly requires that ADIT amounts recorded in FERC account 282 [including the casualty loss ADIT in this proceeding] be included in the bandwidth formula to the extent they are includable for cost-of-service purposes.”7

The 5th Circuit’s decision (as revised November 18, 2014) is available here.


1 La. Pub. Serv. Comm’n v. FERC, No. 13-60874, slip op. at 3 (5th Cir. Nov. 14, 2014); see also La. Pub. Serv. Comm’n v. Entergy Servs., Inc., 146 FERC ¶ 61,152 at P 3 (2014).

2 La. Pub. Serv. Comm’n v. FERC, No. 13-60874, slip op. at 13 (5th Cir. Nov. 14, 2014) (emphasis added).

3 Id. at 14.

4 Id. at 15.

5 Id. at 16.

6 Id. at 23 (emphasis in original).

7 Id. at 25.

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.