Mexico's Energy Industry

Jul 16, 2015

Reading Time : 1 min

Results of Ronda Uno, First Tender

On July 15, 2015, the First Tender initially published on December 11, 2014 (First Tender), came to a conclusion when the Comisión Nacional de Hidrocarburos (CNH) conducted the Opening and Presentation of Bid Proposals Ceremony. This historic event marked the official reopening of the Mexican energy industry to global participants after more than seventy (70) years.

Click here to read the full alert.

Share This Insight

Previous Entries

Speaking Energy

June 25, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to the California Independent System Operator Corporation (CAISO) directing CAISO and CAISO transmission owners to show cause as to why CAISO’s tariff should not be found to be unjust and unreasonable (California Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (the Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 24, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to New York Independent System Operator, Inc. (NYISO) directing NYISO and NYISO transmission owners to show cause as to why NYISO’s tariff should not be found to be unjust and unreasonable (New York Independent System Operator, Inc., 195 FERC ¶ 61,216 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Midcontinent Independent System Operator, Inc. (MISO) directing MISO and MISO transmission owners to show cause as to why MISO’s tariff should not be found to be unjust and unreasonable (Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to PJM Interconnection, L.L.C. directing PJM and PJM transmission owners to show cause as to why PJM’s tariff should not be found to be unjust and unreasonable (PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (the Order)) because it fails to sufficiently:

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.