PJM Alternative to Expanding MOPR Leaves Questions Unanswered

Aug 30, 2016

Reading Time : 3 min

PJM already applies the Minimum Offer Price Rule (MOPR) to mitigate the effect of new resources with out-of-market revenues on capacity prices. While some generators have proposed expanding the MOPR to cover existing resources that are receiving out-of-market revenues, PJM concludes in its recent proposal that the application of the MOPR to existing generation is likely to result in the commitment of more resources than are needed to maintain reliability because state regulators may keep a unit that is serving public policy goals running even if that unit fails to clear in the PJM auction. Moreover, such a scenario would require that load “pay twice” for capacity, since it would pay both the PJM capacity price for all of its capacity obligations and the retail rate charges that were implemented to fund the state program.

PJM is therefore proposing a two-stage approach to determine cleared commitments and clearing prices in the capacity auction. The first stage would be used to determine capacity commitments. Units receiving out-of-market revenues and a commensurate amount of local demand would be removed from the auction, and the units in question would be considered “committed” for the year. The auction mechanism would then be run using the remaining resources and demand. This stage would determine which of those remaining units (those without out-of-market revenues) would be committed to provide capacity for the year.

For the second stage of the auction, the units receiving out-of-market revenues and the related demand would be added back into the auction, together with the committed units without out-of-market revenues, to determine the capacity clearing prices. The units receiving out-of-market revenues would then be bid into the auction at a reference price approximating the unit’s going-forward costs. The resulting clearing price would be paid to all committed units without out-of-market revenues.

The units receiving out-of-market revenues, however, would not receive PJM capacity payments, and the related demand would not pay PJM for an equivalent amount of capacity from those units. PJM explains that:

[T]he subsidized resources that were held out of the first stage of the auction would receive no revenue from the PJM capacity market. Rather, the regulatory authority that had determined that these resources should be subsidized would determine how these resources would be compensated and be solely responsible for providing that compensation. Similarly, the related demand would also not be responsible for paying the clearing price for capacity resulting from the auction, because the regulatory agency subsidizing the resources would decide what price customers representing the related demand should pay for the capacity associated with the subsidized resource and charge that price in retail rates.3

PJM’s proposal is short—only six pages—and thus leaves additional details to be resolved. PJM observes that the most significant question to be resolved is what constitutes a “subsidized” unit. Because the proposal denies PJM capacity payments to subsidized units entirely, this is a crucial question. As written, it seems to create an economic disincentive for states to provide out-of-market revenues that are less than the anticipated PJM capacity price (i.e., any amounts that would be less than the amount that a generator could expect to receive in PJM capacity payments). It is also unclear whether the policy would apply to indirect subsidies, such as tax credits for renewables.

It is also not entirely clear how this proposal would work in practice. PJM specifies that related load would be removed from the auction and would not be responsible for capacity payments for the subsidized capacity, but it is not clear how PJM would determine which load-serving entities would be considered related load.  Another question is whether, under the Supreme Court’s decision in Hughes v. Talen Energy Marketing,4 state regulators would have the authority to determine the price for capacity, as PJM suggests.


 
1 Stu Bresler, PJM Interconnection, L.L.C., Potential Alternative Approach to Expanding the Minimum Offer Price Rule to Existing Resources (2016).

2 Grid 20/20: Focus on Public Policy Goals and Market Efficiency, http://www.pjm.com/committees-and-groups/stakeholder-meetings/symposiums-forums/grid-2020-public-policy-goals-mkt-efficiency.aspx (last visited Aug. 30, 2016).

3 PJM Proposal at 3.

4 136 S.Ct. 1288 (2016).

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.