The D.C. Circuit Clarifies the Timing for Filing Petitions for Review of FERC Orders

Feb 18, 2015

Reading Time : 4 min

The case arose from a hydroelectric relicensing proceeding.  The Smith Lake Improvement and Stakeholders Association (“Association”), composed primarily of persons owning property abutting Alabama Power Company’s (“Alabama Company”) Smith Lake Development, intervened in the Smith Lake relicensing proceeding at FERC.  The Association objected to Alabama Power’s proposal to maintain the lake at the same water levels as under its prior license.  FERC denied the Association’s proposed water-level change and issued a new license authorizing Alabama Power to operate under existing water-level benchmarks.  The Association timely filed for rehearing of the license order.  FERC affirmed the license order with regard to the water levels that interested the Association, but issued a clarification on another matter.  The Association then filed a second rehearing request, which FERC summarily denied, stating that its first rehearing request had addressed the Association’s arguments.  Sixty days after FERC’s summary denial of the second rehearing petition, the Association petitioned the D.C. Circuit for review.

The D.C. Circuit concluded that it lacked jurisdiction to hear the petition.  Under Section 313(b) of the Federal Power Act (FPA), a party petitioning for judicial review of a FERC order must file its petition within 60 days.5  However, although the Association had filed its petition within 60 days of the second rehearing order, the filing occurred 124 days after the first rehearing order.  As the court explained, it was the first rehearing order that started the 60-day clock, and the second request for rehearing did not toll it.

Under FPA 313(b), an appellate court has jurisdiction to review a FERC order only when a petitioner has exhausted its administrative remedies and then petitions the court for review within 60 days.  Normally, filing a petition for rehearing, and receiving an order denying rehearing from FERC, serves to exhaust administrative remedies.  However, “a second rehearing petition must be filed [with FERC] if—and only if—the first rehearing order modified the results of [FERC’s initial order] in a significant way.”6  The “significant” modification must also be a change in the outcome of the case, and not merely the reasoning.7  In Smith Lake, however, FERC’s first order on rehearing did not alter the outcome of the license order with regard to the issues of concern to the Association.  Therefore, the Association was not required to file a second request for rehearing to exhaust its administrative remedies.  Instead, pursuant to FPA 313(b), the Association had to file for review within 60 days of the first rehearing order.  Unfortunately for the Association, it chose to file another request for rehearing, perhaps because FERC’s first order on rehearing included a notation that “‘[t]he licensee’s failure to file a request for rehearing shall constitute acceptance of this order.’”8  In their statement accompanying the court’s denial of rehearing en banc, the judges noted that this was not the first time this had occurred, and it advised that “it would help interested parties to its decisions if FERC took greater care with this type of guidance.”9

In its briefs, the Association raised a further complication that the court attempted to address.  The Association described a “trap” where FERC, in an order on rehearing, does not change the outcome of its prior order, but does change its reasoning.  Under existing precedent, a party cannot “simultaneously seek both agency reconsideration and judicial review of an agency’s order.”10  However, FPA 313(b) states that a party cannot seek review of a FERC order if it has not previously objected to that order in a request for rehearing.11  So, what should a party do if the request for rehearing alters only the FERC’s reasoning, and the party objects to that new reasoning?

Drawing on precedent under the FPA’s sister statute, the Natural Gas Act, the D.C. Circuit concluded that the petitioner caught in this “trap” should petition for review, rather than seek rehearing.  “[W]hen a party seeks judicial review following a rehearing order that changes the reasoning without altering the result,”12 then that party may have reasonable grounds under the FPA for not having raised its objections earlier13 “and therefore be entitled to consideration of those arguments.”14  In the amended version of the order, the court clarified its discussion of the hypothetical situation where the party is unsure whether or not a change to the outcome in a rehearing order is “significant.”  In that case, the court urges parties to file a petition with the court, based again on having “reasonable grounds” for not having raised their arguments with the FERC a second time.


1 Smith Lake Improvement and Stakeholders Ass’n v. FERC, No. 13-1074 (D.C. Cir. Sept. 26, 2014). 

2 See Brief for Respondent, Smith Lake Improvement and Stakeholders Ass’n v. FERC, No. 13-1074.

3 Order, Smith Lake Improvement and Stakeholders Ass’n v. FERC, No. 13-1074.

4 The court also reissued the September opinion, amended to recognize that the requirement that requests for rehearing be filed at FERC within 30 days is a statutory, jurisdictional requirement.

5 16 U.S.C. 825l(b) (2012).

6 Smith Lake Improvement and Stakeholders Ass’n v. FERC, No. 13-1074, slip op. at 4 (D.C. Cir. Jan. 30, 2015) (“Amended Order”) (internal quotes omitted) (emphasis added).

7 Id.

8 Statement of Cir. Judges Brown and Wilkins and Senior Cir. Judge Silberman at 2, Smith Lake Improvement and Stakeholders Ass’n v. FERC, No. 13-1074 (quoting Alabama Power Co., 130 FERC ¶ 62,271, at 64,719 (2010)).

9 Id.

10 Tennessee Gas Pipeline Co. v. FERC, 9 F.3d 980, 980 (D.C. Cir. 1993).

11 16 U.S.C. 825l(b).

12 Amended Order at 6.

13 16 U.S.C. 825l(b) (2012).

14 Amended Order at 6-7. 

Share This Insight

Previous Entries

Speaking Energy

April 15, 2025

On April 9, 2025, President Trump issued an executive order (EO)1 directing several federal agencies and subagencies that regulate energy, environmental, and conservation matters,2 including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), to establish conditional sunset dates for “regulations governing energy production.” The stated objective of the EO is to require agencies to periodically reexamine their regulations to ensure that they continue to serve the public good. For FERC, the order covers regulations promulgated under the Federal Power Act (FPA), the Natural Gas Act (NGA) and the Powerplant and Industrial Fuel Use Act (FUA)3, as amended, while DOE must consider regulations promulgated under the Atomic Energy Act (AEA), the National Appliance Energy Conservation Act, the Energy Policy Act of 1992 (EPAct 1992), the Energy Policy Act of 2005 (EPAct 2005) and the Energy Independence and Security Act of 2007 (EISA), as amended (collectively the Covered Regulations).4 To the extent the DOE has been directed to promulgate regulations under various sections of the NGA, FPA and FUA, and FERC has been directed to promulgate regulations specific to the statutes attributed to the DOE in the EO, the EO is silent. The EO expressly does not apply to those “regulatory permitting regimes authorized by statute.”5

...

Read More

Speaking Energy

April 10, 2025

On April 8, 2025, President Trump issued an Executive Order (EO) directing the Department of Energy (DOE) to take steps to expand the use of its emergency authority under Federal Power Act (FPA) Section 202(c) to require the retention of generation resources deemed necessary to maintain resource adequacy within at risk-regions of the bulk power system regulated by the Federal Energy Regulatory Commission (FERC).1 The EO appears to envision a more active role for DOE in overseeing and supporting the resource adequacy of the grid that deviates from the historic use of Section 202(c) and touches on issues at the intersection of state and federal authority over resource planning.

...

Read More

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.