FERC Adopts New Regulations Allowing Higher-Priced Energy Offers in Organized Electricity Markets

Nov 21, 2016

Reading Time : 3 min

As we previously reported, in January of this year, FERC proposed to require each RTO/ISO to change its currently existing cap on a generation resource’s incremental offer into the energy markets to the higher of each resource’s specific cost-based incremental energy offer and $1,000/MWh (the current cap in most RTOs/ISOs). FERC also proposed to allow cost-based energy offers above $1,000/MWh to set the Locational Marginal Price (LMP) received by all generators that clear the market. However, under FERC’s proposal, the Market Monitoring Unit (MMU) or the RTO/ISO would be required to verify the costs comprising such a cost-based incremental energy offer before that offer could be used to calculate LMPs.

In Order No. 831, FERC adopted all of these proposals, directing each RTO/ISO to revise its current market rules to cap each resource’s incremental energy offer at the higher of $1,000/MWh or the resource’s MMU or RTO/ISO-verified, cost-based incremental energy offer. FERC also required that such offers, if verified by the MMU or RTO/ISO, be used to calculate the market clearing price received by all resources supplying energy. 

In an important change from the proposed rule, however, FERC also directed the RTOs/ISOs to adopt a “hard cap” on cost-based incremental energy offers at $2,000/MWh.  While the regulations adopted in Order No. 831 still allow generators to recover any verified costs that they incur above $2,000/MWh, the hard cap will prevent those resources from setting the market clearing price. If dispatched, such generators would instead receive an uplift payment to recover the difference between the market clearing price and their verified costs. 

Order No. 831 is arguably FERC’s most significant step to date in its ongoing efforts to improve “price formation” in the RTO/ISO markets. FERC states that its final reforms to the offer caps will “make it more likely” that market clearing prices will reflect the true marginal cost of production when short-run marginal costs exceed the $1,000/MWh caps currently in place in most RTOs/ISOs. The Commission acknowledges  that the inclusion of the $2,000/MWh hard cap may “diminish the ability [of the Final Rule] to address the shortcomings of current offer caps,” since it sets a limit on the ability of market prices to rise above that level even when generators with higher marginal costs are dispatched to provide energy. But FERC nonetheless concludes that the limits of the cost verification process – in particular, the practical difficulties of reliably verifying costs in advance in all circumstances – require that a cap be in place to protect customers.  

As noted above, these reforms should allow the energy market clearing prices received by all generators (and other resources providing energy) to rise when the marginal unit’s costs exceed $1,000 per MWh. How often that occurs, and how much additional overall revenue will accrue to electric generators (especially the merchant generation sector), remains to be seen. In addition, how the RTOs/ISOs each implement the required cost verification processes will be critical and will bear watching closely, since cost verification is required for the higher marginal cost offers to set the clearing price. Order No. 831 leaves the details of such processes – which could, like other market mitigation issues, prove controversial – to the RTOs/ISOs to develop in the first instance in their compliance filings.

Order No. 831 will become effective 75 days after it is published in the Federal Register.  RTO/ISO filings to revise their tariffs to comply with the rule will be 75 days after it becomes effective.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.