DC Circuit Embraces Seven County in FERC Pipeline Review Proceeding

August 6, 2025

Reading Time : 2 min

By: Emily P. Mallen, Sharmila P. Das, Stephen J. Hug, Corban A. Coffman, Ben N. Reiter, Barbara Deathe (Senior Paralegal Specialist)

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

Critically, the court embraced the U.S. Supreme Court’s Seven County Infrastructure Coalition v. Eagle County (Seven County) precedent, holding that FERC’s scope-of-review decisions were entitled to “substantial deference” so long as they fell within a “broad zone of reasonableness” and bore a “reasonably close causal relationship” to the federal action at issue. Applying Seven County, the court emphasized that FERC was not obligated to assess upstream or downstream environmental impacts—such as emissions from the broader pipeline—because those effects were not within its control or causally linked to its decision concerning the Border Pipeline. The court reiterated that judicial review of NEPA compliance must defer to the agency’s determination of the scope of its environmental analysis, provided it reasonably addresses the direct effects of the project at hand. This furthered the Seven County principle that NEPA does not serve as a substantive barrier to agency action, but rather ensures informed decision making within the bounds of agency authority.

The court also rejected the notion that the Connector Pipeline was subject to FERC jurisdiction under section 7 of the NGA, relying on precedent related to another Texas intrastate pipeline providing limited interstate service under section 311 of the Natural Gas Policy Act.

Implications for Judicial Review of Future FERC Orders

The ruling marks the first time a panel of judges on the D.C. Circuit embraced Seven County as applied to FERC pipeline reviews conducted under the NGA. It is a marked departure from prior D.C. Circuit decisions that curtailed NGA permits on NEPA sufficiency grounds, which Akin explained in a prior client alert on Seven County. Prior cases held that agencies should assess environmental effects of upstream or downstream projects outside of the agency’s jurisdiction as part of indirect and cumulative impact analyses for pipeline and energy infrastructure projects. If the court’s new line of reasoning holds, litigation risks to project developers may lessen. It could also expedite approvals for energy projects by reducing the scope of an agency’s NEPA review, which may have been expanded to reduce an agency’s reversal risk in court.

The decision indicates that going forward, environmental groups will face a higher bar in challenging FERC’s environmental documents. Unless they can show that FERC’s scoping decisions fall outside a “broad zone of reasonableness” or ignore impacts with a “reasonably close causal relationship” to the federal action, their claims may not overcome this reinforced deference standard. This could lead to fewer successful NEPA challenges in the D.C. Circuit, long considered a key venue for environmental litigation.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.