FERC Staff Questions Wind Farms on Calculation of PURPA’s One-Mile Rule

Jun 21, 2017

Reading Time : 5 min

By: Shawn Whites

One-Mile Rule

Under PURPA’s “mandatory purchase obligation,” a public utility is generally required to purchase all of the output of QFs with which it is interconnected at the utility’s avoided cost rate. A facility qualifies as a QF if its capacity is less than 80 MW, which includes the aggregated capacity of other small generation facilities that (i) use the same resource type, (ii) are owned by the same person or its affiliates, and (iii) are located at the same site.1In determining whether two or more facilities are located at the same site, FERC’s regulations specify that a facility “located within one mile of the facility for which [QF status] is sought”—as measured by the distance between the electric generating equipment of the facilities—is deemed to be “located at the same site.”2Since developers often pursue multiple projects within the same general vicinity, two 80 MW facilities owned by affiliates would not qualify as separate QFs if they are located within one mile of each other. 

Beaver Creek’s Weighted Geographic Center Methodology

On February 9, 2017, Beaver Creek applied for QF status for two approximately 80 MW wind projects in Montana made up of 32 wind turbines each. Beaver Creek notes that the projects are contiguous to two additional 80 MW wind projects, although the two Beaver Creek projects are not affiliated with each other or the other two projects.3Despite their stated non affiliation, Beaver Creek nonetheless acknowledges that “the [close] proximity of these four wind projects raises a question of how the calculation of the . . . one-mile rule would be applied [if] the Commission determined that the [projects] were affiliated” or if the Beaver Creek projects decide at a later date to form an affiliate relationship.4

While the distance between the projects’ electric generating equipment (i.e., wind turbines) serves as the relevant measurement for applying the one-mile rule, Beaver Creek argues that such an approach poses a “unique challenge” for wind projects. Unlike other renewable energy projects with less stringent siting requirements and fewer pieces of generating equipment, Beaver Creek notes that the siting of wind projects is “determined based on the specific topography of the region”5in order to maximize the wind resource, which requires the dispersal of multiple wind turbines across a large stretch of land. Beaver Creek instead proposes that the “appropriate application of the one-mile rule to wind facilities is to apply the distance calculation to the weighted geographic center of the turbine array,”6since each individual wind turbine forms a piece of the project as a whole, ultimately “converg[ing] to a central point for collection.”7Beaver Creek notes that, when measuring from this geographic center, each of the projects satisfies the one-mile rule.

NorthWestern Corporation, the utility required to purchase the output of the projects, protested the proposed methodology, arguing that the one-mile rule is “unambiguous”—the electric generating equipment is the wind turbines, and the distance between the two closest turbines is less than one mile.8

Beaver Creek’s Responses to FERC’s Deficiency Letters

FERC’s deficiency letters asked Beaver Creek to (1) explain how its weighted geographic center calculation of the one-mile rule complies with the Commission’s requirement that the “distances [between two facilities] shall be measured from the electrical generating equipment of a facility,” (2) provide the distance between the wind projects by measuring the distance between the two closest individual wind turbines and (3) submit a topographical map depicting the location of each individual wind turbine.9

In its June 9, 2017, response,  Beaver Creek repeats many of the same arguments made in its original application, stressing that “measur[ing] the distance between wind generation facilities” using individual wind turbines “is an impractical view on what constitutes the ‘facility’ or ‘electrical generating equipment’ for purposes of applying” the one-mile rule.10Beaver Creek then notes that, since the “Commission has provided little guidance on how to calculate the distance between wind generation facilities for purposes of calculating the one-mile rule,”11the weighted geographic center methodology serves as a reasonable proxy that is easily applicable to all wind projects. Crucial to Beaver Creek’s argument is the fact that, when taking into account the 2.5 MW capacity of each individual wind turbine, “there is no area within a one-mile radius of [each of the projects] with more than 80 MW of generation capacity.”12

Implications

Beaver Creek is essentially asking the Commission to re interpret the one-mile rule. In previous orders on QF applications, the Commission took the position that the one-mile rule is a “rule and not a rebuttable presumption” in response to protests that two projects technically greater than one-mile apart should nonetheless fail the test because they “gamed” PURPA.13Though that context differs from the instant case, which involves the standard of measurement for applying the rule, the Commission’s language appears to be clear—the one-mile rule is not open to interpretation. 

Concerns over PURPA’s one-mile rule were most recently discussed at a June 2016 FERC technical conference, where at least one participant, the American Wind Energy Association, urged the Commission to “publish information about how it measures one mile.”14Such information has yet to be published, though it could come through the issuance of an order on Beaver Creek’s applications once quorum is restored at FERC. The future Commission will thus need to determine whether the use of a weighted geographical center methodology is an acceptable approach for calculating the one-mile rule or whether the rule’s standard of measuring from the “electric generating equipment” is also a bright line. In any event, a clarification of the Commission’s policy regarding the one-mile rule will provide increased regulatory certainty for developers of projects hoping to achieve QF status.

 


 

118 C.F.R. § 292.204(a)(1) (2017).

2Id. § 292.204(a)(2).

3The additional projects are Beaver Creek Wind , LLC and Beaver Creek Wind IV, LLC, together with Beaver Creek Wind II, LLC and Beaver Creek Wind III, LLC.  

4Beaver Creek Wind II, LLC, Application for Certification, QF17-673-000, at 12 (filed Feb. 9, 2017).  While two applications were submitted in two separate dockets, both applications are substantively the same and are therefore referred to as one application in this post.

5Id. at 13.

6Id. at 12.

7Beaver Creek Wind II, LLC, Motion for Leave to Answer and Answer, Docket No. QF17-673-000, at 5 (filed Mar. 17, 2017).

8NorthWestern Corp., Motion to Intervene, Motion to Consolidate, and Protest, Docket No. QF17-673-000, at 6 (filed Mar. 2, 2017).

9FERC Staff, Deficiency Letter, Docket No. QF17-673-000, at 2 (May 10, 2017).

10Response of Beaver Creek Wind II, LLC to May 10, 2017 Deficiency Letter, Docket No. QF17-673-000, at 3 (filed June 9, 2017).

11Id.  

12Id. at 5.

13See, e.g., DeWind Novus, LLC, 139 FERC ¶ 61,201, at P 25 (2012).

14American Wind Energy Association, Post-Technical Conference Comments, AD16-16-000, at 6 (filed Nov. 15, 2016). 

 

Share This Insight

© 2024 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.