FERC Takes Its Next Step on “Price Formation” in Organized Markets

Dec 22, 2016

Reading Time : 4 min

The Problem

Each RTO/ISO currently handles fast-start resources somewhat differently, and the definitions of these resources also vary.  But, generally speaking, resources are considered “fast-start” if they can start in ten minutes or less (although some RTO/ISOs currently consider resources that can start in less than two hours to be “fast-start”).  Fast-start resources are generally dispatchable by the RTO/ISO, but often have a limited dispatch range (i.e., they are subject to economic operating limits or may be “block-loaded,” meaning that the resource can only be dispatched at a specific megawatt (MW) output).  Fast start resources also often have minimum or maximum run times that limit their operations.  Examples of resources that might qualify as fast-start include gas combustion turbines, batteries and automated demand response.

Because of these limits on dispatch, RTO/ISO market rules generally prevent such resources from setting the clearing price (i.e., the Locational Marginal Price (LMP).  FERC is concerned that, as a result, clearing prices may not accurately reflect the true marginal cost of energy.

Proposed Solutions  

To address this concern, FERC proposes require each RTO/ISO to adopt four changes to how prices for fast-start resources are calculated.  Each RTO/ISO would be required to apply such fast-start pricing to any resource, using any technology, that can start up in ten minutes or less, that has a minimum run time of one hour or less, and that submits economic energy offers. 

First, each RTO/ISO would be required to include the fast-start resource’s commitment costs (i.e., the costs it incurs to start up and be available to produce energy) in its energy and operating reserve prices.  FERC explains that because fast-start resources are often dispatched on short notice to respond to unforeseen real-time system needs, their commitment costs should be considered marginal costs.  The RTOs/ISOs currently do not consider such costs to be “marginal costs” that can be included in offers, however, which FERC preliminarily concludes will result in market clearing prices that do not reflect marginal costs.  Second, each RTO/ISO would be required to treat resources with minimum economic operating limits as dispatchable from “zero” to their maximum economic operating limit for the purpose of calculating prices.  LMPs are set based on the marginal cost of serving the next increment of demand, while many fast-start resources are subject to economic minimum operating limits (i.e., the lowest amount of output they can economically provide) or are block-loaded.  As FERC explains:

Because the system may need fewer megawatts (MW) than the fast-start resource’s economic minimum operating limit to meet load, other resources must be dispatched down. The resources that were dispatched down become the most economical option to serve the next increment of load. Therefore, despite the fact that a fast-start resource is essentially marginal, this restriction prevents a fast-start resource dispatched at its economic minimum operating limit from setting the LMP.1

FERC proposes to resolve this problem by requiring each RTO/ISO to program its pricing algorithm to “relax” the economic minimum operating limits and treat the resource as dispatchable to serve another increment of load for the purpose of determining LMP.  

Third, for those RTO/ISOs that chose to allow an offline fast-start resource to set the price, FERC proposes a requirement that such price-setting resources must be both “feasible and economical.”  The existing rules in some RTO/ISOs allow offline fast-start resources to set the price under certain system conditions (such as transmission constraint violations or reserve shortages).  FERC concludes that such a rule is reasonable, but only if it would be both feasible and economical for the offline fast-start resource to address the system condition. 

Fourth, FERC proposes a requirement that each RTO/ISO must incorporate fast-start pricing into both the day-ahead and real time markets.  However, FERC recognizes that much of the value of fast-start resources is realized in the real-time market, and specifically seeks further comment on this issue.

FERC preliminarily concludes that these market-rule reforms will more accurately reflect the marginal cost of serving load during times when fast-start resources are needed, and help avoid unnecessary uplift charges that result when fast-start resources are unable to factor their commitment costs into their offers.  In addition, FERC states that these market-rule changes will better reflect the need for fast-start resources and the value they provide to the system, providing price signals to encourage investment in such resources.

FERC’s proposal, if finalized, could allow market clearing prices to rise during periods when fast-start resources are required, providing additional revenue opportunities for all resources providing energy at those times.  It may also provide important new market opportunities to existing and new technologies that can quickly startup in response to electric grid needs.  How much effort the RTOs/ISOs would be required to expend to comply FERC’s proposals will vary; as FERC explains, most RTO/ISOs have some sort of fast-start pricing mechanism already.  The NOPR proposals would essentially require each RTO/ISO to adopt those mechanisms that FERC has determined are the best practices.

As noted above, the NOPR is the third in FERC’s series of rulemakings seeking to improve the process of price formation in the RTO/ISO markets.  FERC previously finalized two sets of regulations requiring the RTOs/ISOs to (1) reform settlement intervals and shortage pricing to more accurately compensate resources based on the value they provide the system, and (2) raise their existing caps on energy market offers and allow those higher-price offers to set market clearing prices.  While the leadership of FERC will change in 2017 following the transition to a new administration, the agency seems likely to continue these efforts.

Comments on the NOPR will be due 60 days after the NOPR is published in the Federal Register, which has not yet occurred.  Each RTO/ISO will be expected to submit a compliance filing within 90 days of the issuance of a Final Rule.


1 NOPR at p. 8.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.