5th Circuit Finds District Court Can Defer to FERC in PURPA Case . . . but not Indefinitely

Jan 13, 2016

Reading Time : 4 min

By: Jason Sison, law clerk (not admitted to practice)

PURPA Background

Section 210 of PURPA, which is currently the subject of much debate, seeks to encourage the development of cogeneration and small power production facilities (“qualifying facilities” or QFs) by, among other things, generally requiring utilities to offer to sell electricity to, and purchase electricity from, such facilities. Section 210 provides for a regulatory paradigm in which FERC promulgates rules to be implemented by state regulatory authorities and nonregulated utilities. Under Section 210(h), a qualifying facility that believes that a state regulatory authority or nonregulated utility is not properly implementing the Commission’s PURPA rules may petition the Commission to bring an enforcement action against the state regulatory authority or nonregulated utility in federal district court to enforce PURPA. If the Commission does not initiate such an enforcement action within 60 days of the petition, the petitioner can bring a district court enforcement action on its own.

FERC Proceedings and District Court Litigation

            The underlying dispute involves Entergy’s integration into the Midcontinent Independent System Operator (MISO) Regional Transmission Organization (RTO) and the effects that might have on Occidental Chemical Corp. and other QFs. Occidental claims that, in 2011, Entergy decided to join MISO to avoid its PURPA obligations to Occidental and other QFs, and that Entergy and MISO’s integration of QFs would strip the QFs of their PURPA rights. On January 17, 2013, Occidental filed a complaint against MISO at FERC regarding MISO’s plan to integrate QFs. That complaint remains pending at FERC. On January 9, 2014, the Louisiana Public Service Commission (LPSC) entered an order that Occidental argues effectively adopted Entergy’s plan for integrating QFs into MISO, stripping QFs of PURPA rights. Claiming that the LPSC’s order violated PURPA, on February 5, 2014, Occidental petitioned FERC under Section 210(h) of PURPA to initiate an enforcement action against the LPSC in federal district court. On April 4, 2014, FERC issued a notice of its intent not to act, which, under Section 210(h) of PURPA, authorized Occidental to file a district court enforcement action on its own. In its notice, FERC found that the petition raised largely the same issues as those raised by Occidental’s pending complaint at FERC against MISO.

On April 17, 2014, Occidental filed an action in federal district court against Entergy, the LPSC and the LPSC commissioners. Occidental’s complaint against the LPSC essentially repeated the arguments that it raised in its FERC complaint.

On June 4, 2015, Entergy and the LPSC defendants jointly moved the district court to stay the case pending an administrative determination in the pending complaint proceeding at FERC. In short, the defendants argued that the district court should exercise its discretion to stay the case pursuant to the primary jurisdiction doctrine, under which a court will defer to an agency for an initial decision on a matter, because FERC’s resolution of the administrative complaint would also resolve one of the issues before the district court—namely, whether MISO’s plan to integrate the QFs complies with PURPA and FERC’s rules. In opposition, Occidental argued that the district court was barred from invoking the primary jurisdiction doctrine because Section 210(h) of PURPA explicitly coordinates the work between FERC and the district court, displacing the primary jurisdiction doctrine. Occidental further argued that the costs of indefinitely delaying its PURPA suit would outweigh any benefits.

On January 20, 2015, the district court granted defendants’ request for a stay, concluding that the case should be stayed pending a decision by FERC on the issues relating to the MISO tariff and market rules underlying Occidental’s complaint. Occidental appealed the district court order to the 5th Circuit.

5th Circuit Finds Deference to FERC Okay, but Reverses Indefinite Stay

On appeal, the 5th Circuit considered whether Section 210(h) of PURPA precludes application of the primary jurisdiction doctrine. The primary jurisdiction doctrine is a doctrine of judicial abstention whereby a court can defer to an administrative agency for an initial decision on a question within the agency’s specific expertise. Occidental argued that the primary jurisdiction doctrine is not available for actions under Section 210 of PURPA because Congress explicitly coordinated the work between FERC and the district court by allowing a party to petition FERC to act and then, if FERC declines to do so, bring its own district court enforcement action.   

The 5th Circuit found that, while Section 210(h) does coordinate work between FERC and the federal courts, it does not expressly or impliedly preclude application of the primary jurisdiction doctrine. Thus, the 5th Circuit concluded that the district court acted within its discretion by staying the case under the primary jurisdiction doctrine and deferring to FERC. However, the 5th Circuit found that the term of the stay should be limited, allowing FERC a reasonable opportunity to act on the pending administrative complaint, but without the costs inherent in an indefinite stay. Accordingly, the 5th Circuit directed the district court to modify the stay to 180 days, subject to an extension if FERC can show good cause for failing to act in that time and if an additional delay would not prejudice Occidental.  

Share This Insight

Previous Entries

Speaking Energy

March 10, 2026

Federal energy regulators are assuming expanded roles as the administration prioritizes energy dominance and infrastructure development to meet unprecedented power demand. FERC Chairman Laura Swett has vowed to expedite data center interconnections while addressing jurisdictional challenges, warning that unmet electricity demand could drive data centers abroad and create national security risks. The agency is processing pipeline applications faster than in prior years and considering blanket authorizations for certain LNG and hydroelectric projects to streamline approvals. 

Pipeline projects previously stalled by Clean Water Act permits are being revitalized, particularly in northeastern states where historically high electricity prices have increased openness to natural gas infrastructure. The Department of Energy is expanding its emergency authority to require retention of generation resources and has granted major LNG export approvals, signaling commitment to expanding U.S. export capacity under a streamlined framework that deprioritizes climate considerations.  

The Administration is bullish on the opportunities for the U.S. energy industry in Venezuela and eager to support companies willing to navigate the political risk inherent in the operations at the moment. Early meetings with President Trump and industry leaders showed the path forward may be longer and more complex than anticipated by the President. 

As permitting reforms advance and the pendulum swings toward fossil fuel favorability, the regulatory and policy landscape is fundamentally reshaping energy infrastructure development timelines and investment opportunities. 

Oil & Gas in 2026: Energy Policy & Regulation 

Delve into the complete regulatory & policy outlook at our Oil & Gas in 2026 report.

...

Read More

Speaking Energy

March 3, 2026

Macroeconomic turbulence and volatile commodity markets significantly influenced oil & gas M&A activity throughout 2025, with deals showing renewed momentum only in the year's second half.  

...

Read More

Speaking Energy

February 24, 2026

On February 19, 2026, the Federal Energy Regulatory Commission (FERC) issued an order rescinding the soft price cap for bilateral spot market energy sales in the Western Electricity Coordinating Council (WECC) region.1 As previously covered, on July 15, 2025, FERC initiated a Federal Power Act Section 206 proceeding following the D.C. Circuit’s decision finding that FERC must apply the Mobile-Sierra public interest standard before ordering refunds for above-cap bilateral sales and vacating FERC’s orders requiring refunds for certain bilateral spot market transactions in the WECC region that exceeded the $1,000 MWh soft price cap.2 FERC’s Order follows through on the proposal it made last July to eliminate the WECCs soft price cap and marks a recognition that Western wholesale markets have evolved over the past two decades to become sufficiently competitive to render the soft price cap unnecessary.  

...

Read More

Speaking Energy

February 23, 2026

The oil & gas industry is experiencing a fundamental transformation in how companies access and deploy capital in 2026. Despite strong balance sheets and robust free cash flow generation, the sector is witnessing strategic shifts in funding sources and investment priorities that signal a new era of capital allocation.

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.