5th Circuit Finds District Court Can Defer to FERC in PURPA Case . . . but not Indefinitely

Jan 13, 2016

Reading Time : 4 min

By: Jason Sison, law clerk (not admitted to practice)

PURPA Background

Section 210 of PURPA, which is currently the subject of much debate, seeks to encourage the development of cogeneration and small power production facilities (“qualifying facilities” or QFs) by, among other things, generally requiring utilities to offer to sell electricity to, and purchase electricity from, such facilities. Section 210 provides for a regulatory paradigm in which FERC promulgates rules to be implemented by state regulatory authorities and nonregulated utilities. Under Section 210(h), a qualifying facility that believes that a state regulatory authority or nonregulated utility is not properly implementing the Commission’s PURPA rules may petition the Commission to bring an enforcement action against the state regulatory authority or nonregulated utility in federal district court to enforce PURPA. If the Commission does not initiate such an enforcement action within 60 days of the petition, the petitioner can bring a district court enforcement action on its own.

FERC Proceedings and District Court Litigation

            The underlying dispute involves Entergy’s integration into the Midcontinent Independent System Operator (MISO) Regional Transmission Organization (RTO) and the effects that might have on Occidental Chemical Corp. and other QFs. Occidental claims that, in 2011, Entergy decided to join MISO to avoid its PURPA obligations to Occidental and other QFs, and that Entergy and MISO’s integration of QFs would strip the QFs of their PURPA rights. On January 17, 2013, Occidental filed a complaint against MISO at FERC regarding MISO’s plan to integrate QFs. That complaint remains pending at FERC. On January 9, 2014, the Louisiana Public Service Commission (LPSC) entered an order that Occidental argues effectively adopted Entergy’s plan for integrating QFs into MISO, stripping QFs of PURPA rights. Claiming that the LPSC’s order violated PURPA, on February 5, 2014, Occidental petitioned FERC under Section 210(h) of PURPA to initiate an enforcement action against the LPSC in federal district court. On April 4, 2014, FERC issued a notice of its intent not to act, which, under Section 210(h) of PURPA, authorized Occidental to file a district court enforcement action on its own. In its notice, FERC found that the petition raised largely the same issues as those raised by Occidental’s pending complaint at FERC against MISO.

On April 17, 2014, Occidental filed an action in federal district court against Entergy, the LPSC and the LPSC commissioners. Occidental’s complaint against the LPSC essentially repeated the arguments that it raised in its FERC complaint.

On June 4, 2015, Entergy and the LPSC defendants jointly moved the district court to stay the case pending an administrative determination in the pending complaint proceeding at FERC. In short, the defendants argued that the district court should exercise its discretion to stay the case pursuant to the primary jurisdiction doctrine, under which a court will defer to an agency for an initial decision on a matter, because FERC’s resolution of the administrative complaint would also resolve one of the issues before the district court—namely, whether MISO’s plan to integrate the QFs complies with PURPA and FERC’s rules. In opposition, Occidental argued that the district court was barred from invoking the primary jurisdiction doctrine because Section 210(h) of PURPA explicitly coordinates the work between FERC and the district court, displacing the primary jurisdiction doctrine. Occidental further argued that the costs of indefinitely delaying its PURPA suit would outweigh any benefits.

On January 20, 2015, the district court granted defendants’ request for a stay, concluding that the case should be stayed pending a decision by FERC on the issues relating to the MISO tariff and market rules underlying Occidental’s complaint. Occidental appealed the district court order to the 5th Circuit.

5th Circuit Finds Deference to FERC Okay, but Reverses Indefinite Stay

On appeal, the 5th Circuit considered whether Section 210(h) of PURPA precludes application of the primary jurisdiction doctrine. The primary jurisdiction doctrine is a doctrine of judicial abstention whereby a court can defer to an administrative agency for an initial decision on a question within the agency’s specific expertise. Occidental argued that the primary jurisdiction doctrine is not available for actions under Section 210 of PURPA because Congress explicitly coordinated the work between FERC and the district court by allowing a party to petition FERC to act and then, if FERC declines to do so, bring its own district court enforcement action.   

The 5th Circuit found that, while Section 210(h) does coordinate work between FERC and the federal courts, it does not expressly or impliedly preclude application of the primary jurisdiction doctrine. Thus, the 5th Circuit concluded that the district court acted within its discretion by staying the case under the primary jurisdiction doctrine and deferring to FERC. However, the 5th Circuit found that the term of the stay should be limited, allowing FERC a reasonable opportunity to act on the pending administrative complaint, but without the costs inherent in an indefinite stay. Accordingly, the 5th Circuit directed the district court to modify the stay to 180 days, subject to an extension if FERC can show good cause for failing to act in that time and if an additional delay would not prejudice Occidental.  

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.