D.C. Circuit Concludes Again That FERC Has the Authority to Correct Its Own Errors

May 31, 2017

Reading Time : 3 min

Background

Chehalis Power Generating, L.P. (“Chehalis”) provided reactive power service to BPA free of charge until 2005. In 2005, Chehalis filed a rate schedule with FERC under Section 205 of the Federal Power Act (FPA) setting forth the rates that it would henceforth charge BPA for reactive power service. Chehalis’ submittal referred to the rate schedule as an “initial” rate, because Chehalis had not previously charged for reactive power service. However, FERC decided to treat Chehalis’ reactive power schedule as a “changed rate,” reasoning that an initial rate schedule must “involve a new customer and a new service.”2  The distinction between an “initial” and a “changed” rate is significant, because, under FPA Section 205, FERC can permit a rate change to go into effect while it considers whether the rate is just and reasonable. If FERC then determines that the rate is too high, it may order refunds of the difference between the rate charged and the just and reasonable rate. However, FERC interprets this refund authority under Section 205 to be limited to “changed” rates—initial rates are not subject to refund under FPA Section 205.

FERC found Chehalis’ proposed rate for reactive power service to be unjust and unreasonable, and thus directed it to refund the excess revenues it had collected. Chehalis appealed. The D.C. Circuit remanded the case to FERC, directing the Commission to explain why Chehalis’ proposed rate schedule for reactive power qualified as a “changed rate” when Chehalis had not previously filed a rate for reactive power.3  FERC eventually concluded that, although Chehalis’ rate schedule was a “changed rate,” because Chehalis should have filed a rate schedule when it started providing reactive power service—even if the rate was zero—its precedent on the issue was unclear. As such, FERC found that “it would be appropriate” for Chehalis to recover the refunds that it had paid to BPA.4  However, because BPA is anonjurisdictional utility, FERC concluded that it lacked the authority to order BPA to return the refunded amounts.5

TNA Merchant Projects, Inc. v. FERC          

It is well established that FERC lacks jurisdiction under the FPA to order a nonjurisdictional utility (e.g., a governmental entity, such as BPA, a municipal utility or a cooperative) to pay refunds to its customers.6  However, in the D.C. Circuit’s recent TNA decision, the court drew a distinction between refunds and recoupment, explaining that FERC’s lack of refund authority under FPA Section 205 does not prevent it from correcting its own mistakes by authorizing Chehalis to recoup the money it paid to BPA due to FERC’s error and ordering BPA to return the money. The court observed that FPA Section 309, which grants FERC broad remedial authority, “affords [FERC] broad authority to ‘remedy its errors’ and correct unjust situations.”7  The court cited its 2016 decision in Xcel Energy Servs. Inc. v. FERC, which likewise emphasized the Commission’s authority to correct its own errors.8

TNA is, in many ways, a companion case to Xcel. In Xcel, the court found that FERC’s inability to establish a retroactive refund date does not prohibit FERC from correcting its own mistakes, either by retroactively suspending rates under FPA Section 205 or by invoking its authority under FPA Section 309. In both cases, the court refused to accept FERC’s claim that it was statutorily prohibited from undoing the damage done by its own orders.

In addition to finding that FERC had the authority to order recoupment, the court did not disturb FERC’ s finding that Chehalis should have filed an initial rate schedule even when it was not charging for reactive power service. The court reasoned that, at this point in the proceedings, weighing in on that dispute would not affect the rights of the parties one way or the other.

The court remanded the case to FERC to determine the amount of recoupment to which Chehalis is entitled.


1TNA Merch. Projects, Inc. v. FERC, No. 13-1008 (D.C. Cir. May 19, 2017), https://www.ferc.gov/legal/court-cases/opinions/2017/13-1008opn.pdf.
2Chehalis Power Generating, L.P., 112 FERC ¶ 61,144, at P 23 (2005).
3TNA Merch. Projects, Inc. v. FERC, 616 F.3d 588, 593 (D.C. Cir. 2010).
4Chehalis Power Generating, L.P., 145 FERC ¶ 61,052, at P 14 (2013).
5Chehalis Power Generating, L.P., 153 FERC ¶ 61,194 (2015).
6Transmission Agency of N. Cal. v. FERC, 495 F.3d 663, 674 (D.C. Cir. 2007); Bonneville Power Admin. v. FERC, 422 F.3d 908, 926 (9th Cir. 2005).
7TNA Merch. Projects, Inc. v. FERC, No. 13-1008, at 9 (D.C. Cir. May 19, 2017).
8Xcel Energy Servs. Inc. v. FERC, 815 F.3d 947, 956 (D.C. Cir. 2016).




 

 

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.