D.C. Circuit Sides with FERC; Prevents Full Abandonment

Jan 18, 2019

Reading Time : 3 min

San Diego Gas & Electric Company (SDG&E) filed a petition for declaratory order with FERC in September 2015 to establish its eligibility for the abandonment incentive for the South Orange County Reliability Enhancement Project, an effort to rebuild and upgrade a substation and to replace and relocate certain transmission and distribution line segments. By the time of the application, the company had already spent roughly $31 million on the project. FERC issued a declaratory order in March 2016 finding that, should the project be abandoned for reasons beyond the company’s control, SDG&E could recover 100 percent of the prudently incurred project costs going forward, but that it would not be entitled to recover all of the
$31 million that hasalready been spent on the project.4 Instead, half of those costs could be recovered from ratepayers in accordance with FERC’s pre-Order No. 679 practice. SDG&E appealed that decision, arguing that it should be entitled to the abandonment incentive rate treatment for the full cost of the project.

The D.C. Circuit sided with FERC in a split decision.5 Writing for the majority, Judge Pillard emphasized that the purpose of FERC’s incentive program is to encourage investment in needed infrastructure projects. The majority therefore agreed with FERC that the portion of the project that was already financed and paid for before receiving approval for the incentive rate treatment “lacked the requisite nexus to the facilitation of new investment.”6 In other words, the incentive rate treatment cannot encourage an investment that has already occurred. The company itself had acknowledged that it had incurred the $31 million of costs “without assurance of cost recovery.”7

In a lengthy dissent, Judge Randolph took issue with, among other things, the majority’s characterization of when the “incentive” to invest begins. “The fallacy in [the majority’s] theory is its failure to recognize that FERC created the incentive when it promulgated the regulation in 2006,” Judge Randolph wrote, “well before San Diego began incurring costs for its transmission project.” Judge Randolph points out that FERC has rejected a “but for” test (i.e., the applicant does not need to show that the investment would not occur but for the incentive rate treatment), and that lack of “certain recovery” prior to a FERC application does not render the incentive treatment meaningless. Indeed, even if an applicant is approved for the rate treatment, the applicant still lacks “certain recovery,” since it will later have to make a prudency showing to recover the costs from ratepayers.

FERC has granted preorder abandonment incentives before, although not in a case where a party objected to such recovery, as here. As the first case to litigate the precise issue of when the abandonment incentive rate treatment may begin, this decision establishes a precedent that FERC is likely to follow in future cases. FERC has emphasized, however, that each application for transmission incentives will be evaluated on a case-by-case basis.


1 Energy Policy Act of 2005, Pub. L. No. 109-58, § 1241, 119 Stat. 961 (2005) (codified at 16 U.S.C.
§ 824s).

2 Promoting Transmission Investment Through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057 (2006), order on reh’g, Order No. 679-A, 117 FERC ¶ 61,345 (2006), order on reh’g, Order No. 679-B, 119 FERC ¶ 61,062 (2007); see also Promoting Transmission Investment Through Pricing Reform, 141 FERC ¶ 61,129 (2012) (“Policy Statement”).

3 Order No. 679 at P 155; see also Policy Statement, 141 FERC 61,129, at P 14.

4 San Diego Gas & Elec., 154 FERC ¶ 61,158, at PP 17-18 (2016).

5 San Diego Gas & Elec. v. FERC, No. 16-1433 (D.C. Cir. Jan. 15, 2019).

6 Id. at 15.

7 Id. at 19.

Share This Insight

Previous Entries

Speaking Energy

March 10, 2026

Federal energy regulators are assuming expanded roles as the administration prioritizes energy dominance and infrastructure development to meet unprecedented power demand. FERC Chairman Laura Swett has vowed to expedite data center interconnections while addressing jurisdictional challenges, warning that unmet electricity demand could drive data centers abroad and create national security risks. The agency is processing pipeline applications faster than in prior years and considering blanket authorizations for certain LNG and hydroelectric projects to streamline approvals. 

Pipeline projects previously stalled by Clean Water Act permits are being revitalized, particularly in northeastern states where historically high electricity prices have increased openness to natural gas infrastructure. The Department of Energy is expanding its emergency authority to require retention of generation resources and has granted major LNG export approvals, signaling commitment to expanding U.S. export capacity under a streamlined framework that deprioritizes climate considerations.  

The Administration is bullish on the opportunities for the U.S. energy industry in Venezuela and eager to support companies willing to navigate the political risk inherent in the operations at the moment. Early meetings with President Trump and industry leaders showed the path forward may be longer and more complex than anticipated by the President. 

As permitting reforms advance and the pendulum swings toward fossil fuel favorability, the regulatory and policy landscape is fundamentally reshaping energy infrastructure development timelines and investment opportunities. 

Oil & Gas in 2026: Energy Policy & Regulation 

Delve into the complete regulatory & policy outlook at our Oil & Gas in 2026 report.

...

Read More

Speaking Energy

March 3, 2026

Macroeconomic turbulence and volatile commodity markets significantly influenced oil & gas M&A activity throughout 2025, with deals showing renewed momentum only in the year's second half.  

...

Read More

Speaking Energy

February 24, 2026

On February 19, 2026, the Federal Energy Regulatory Commission (FERC) issued an order rescinding the soft price cap for bilateral spot market energy sales in the Western Electricity Coordinating Council (WECC) region.1 As previously covered, on July 15, 2025, FERC initiated a Federal Power Act Section 206 proceeding following the D.C. Circuit’s decision finding that FERC must apply the Mobile-Sierra public interest standard before ordering refunds for above-cap bilateral sales and vacating FERC’s orders requiring refunds for certain bilateral spot market transactions in the WECC region that exceeded the $1,000 MWh soft price cap.2 FERC’s Order follows through on the proposal it made last July to eliminate the WECCs soft price cap and marks a recognition that Western wholesale markets have evolved over the past two decades to become sufficiently competitive to render the soft price cap unnecessary.  

...

Read More

Speaking Energy

February 23, 2026

The oil & gas industry is experiencing a fundamental transformation in how companies access and deploy capital in 2026. Despite strong balance sheets and robust free cash flow generation, the sector is witnessing strategic shifts in funding sources and investment priorities that signal a new era of capital allocation.

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.