D.C. Circuit Sides with FERC; Prevents Full Abandonment

Jan 18, 2019

Reading Time : 3 min

San Diego Gas & Electric Company (SDG&E) filed a petition for declaratory order with FERC in September 2015 to establish its eligibility for the abandonment incentive for the South Orange County Reliability Enhancement Project, an effort to rebuild and upgrade a substation and to replace and relocate certain transmission and distribution line segments. By the time of the application, the company had already spent roughly $31 million on the project. FERC issued a declaratory order in March 2016 finding that, should the project be abandoned for reasons beyond the company’s control, SDG&E could recover 100 percent of the prudently incurred project costs going forward, but that it would not be entitled to recover all of the
$31 million that hasalready been spent on the project.4 Instead, half of those costs could be recovered from ratepayers in accordance with FERC’s pre-Order No. 679 practice. SDG&E appealed that decision, arguing that it should be entitled to the abandonment incentive rate treatment for the full cost of the project.

The D.C. Circuit sided with FERC in a split decision.5 Writing for the majority, Judge Pillard emphasized that the purpose of FERC’s incentive program is to encourage investment in needed infrastructure projects. The majority therefore agreed with FERC that the portion of the project that was already financed and paid for before receiving approval for the incentive rate treatment “lacked the requisite nexus to the facilitation of new investment.”6 In other words, the incentive rate treatment cannot encourage an investment that has already occurred. The company itself had acknowledged that it had incurred the $31 million of costs “without assurance of cost recovery.”7

In a lengthy dissent, Judge Randolph took issue with, among other things, the majority’s characterization of when the “incentive” to invest begins. “The fallacy in [the majority’s] theory is its failure to recognize that FERC created the incentive when it promulgated the regulation in 2006,” Judge Randolph wrote, “well before San Diego began incurring costs for its transmission project.” Judge Randolph points out that FERC has rejected a “but for” test (i.e., the applicant does not need to show that the investment would not occur but for the incentive rate treatment), and that lack of “certain recovery” prior to a FERC application does not render the incentive treatment meaningless. Indeed, even if an applicant is approved for the rate treatment, the applicant still lacks “certain recovery,” since it will later have to make a prudency showing to recover the costs from ratepayers.

FERC has granted preorder abandonment incentives before, although not in a case where a party objected to such recovery, as here. As the first case to litigate the precise issue of when the abandonment incentive rate treatment may begin, this decision establishes a precedent that FERC is likely to follow in future cases. FERC has emphasized, however, that each application for transmission incentives will be evaluated on a case-by-case basis.


1 Energy Policy Act of 2005, Pub. L. No. 109-58, § 1241, 119 Stat. 961 (2005) (codified at 16 U.S.C.
§ 824s).

2 Promoting Transmission Investment Through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057 (2006), order on reh’g, Order No. 679-A, 117 FERC ¶ 61,345 (2006), order on reh’g, Order No. 679-B, 119 FERC ¶ 61,062 (2007); see also Promoting Transmission Investment Through Pricing Reform, 141 FERC ¶ 61,129 (2012) (“Policy Statement”).

3 Order No. 679 at P 155; see also Policy Statement, 141 FERC 61,129, at P 14.

4 San Diego Gas & Elec., 154 FERC ¶ 61,158, at PP 17-18 (2016).

5 San Diego Gas & Elec. v. FERC, No. 16-1433 (D.C. Cir. Jan. 15, 2019).

6 Id. at 15.

7 Id. at 19.

Share This Insight

Previous Entries

Speaking Energy

February 10, 2026

The global energy sector enters 2026 amid major policy shifts, geopolitical tension and evolving market dynamics. The Trump administration’s reversal of Biden-era climate initiatives and renewed emphasis on domestic production have reshaped the policy landscape, offering a more favorable regulatory environment even as conflicts abroad, oil price volatility and shifting trade policies tempered deal activity through 2025.

...

Read More

Speaking Energy

January 22, 2026

On January 16, 2026, the National Energy Dominance Council (NDEC) and governors from each of the 13 states in PJM issued a Statement of Principles urging PJM Interconnection, L.L.C. (PJM) to hold an emergency backstop auction and take other measures to support the entry of new capacity to preserve the reliability of the PJM region. The Statement of Principles calls on PJM to expeditiously file with the Federal Energy Regulatory Commission (FERC or the Commission) tariff revisions that would overhaul aspects of PJM’s market rules to address rising electricity prices and growing reliability risks in the PJM region. The Statement of Principles comes at a time of growing concern that PJM will not have sufficient capacity in the coming years to meet demand due to the retirement of existing generation resources, the glacial pace of new entry and projected increased demand associated with data center development.

...

Read More

Speaking Energy

December 21, 2025

On December 19, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued its much-anticipated order on show cause proceeding concerning the co-location of generation and load within the PJM Interconnection, L.L.C. (PJM) market.[1] In the order, the Commission finds that PJM’s tariff is unjust and unreasonable because it does not provide sufficient clarity on the rates, terms, and conditions of service applicable to generators serving Co-Located Load and does not include transmission services appropriate for customers that are willing and able to limit their use of the transmission system in certain conditions. 

...

Read More

Speaking Energy

November 25, 2025

We are pleased to share the program materials and a recording of Akin’s recently presented webinar, “Navigating the Evolving Landscape of Corporate PPAs.”

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.