D.C. Circuit Sides with FERC; Prevents Full Abandonment

Jan 18, 2019

Reading Time : 3 min

San Diego Gas & Electric Company (SDG&E) filed a petition for declaratory order with FERC in September 2015 to establish its eligibility for the abandonment incentive for the South Orange County Reliability Enhancement Project, an effort to rebuild and upgrade a substation and to replace and relocate certain transmission and distribution line segments. By the time of the application, the company had already spent roughly $31 million on the project. FERC issued a declaratory order in March 2016 finding that, should the project be abandoned for reasons beyond the company’s control, SDG&E could recover 100 percent of the prudently incurred project costs going forward, but that it would not be entitled to recover all of the
$31 million that hasalready been spent on the project.4 Instead, half of those costs could be recovered from ratepayers in accordance with FERC’s pre-Order No. 679 practice. SDG&E appealed that decision, arguing that it should be entitled to the abandonment incentive rate treatment for the full cost of the project.

The D.C. Circuit sided with FERC in a split decision.5 Writing for the majority, Judge Pillard emphasized that the purpose of FERC’s incentive program is to encourage investment in needed infrastructure projects. The majority therefore agreed with FERC that the portion of the project that was already financed and paid for before receiving approval for the incentive rate treatment “lacked the requisite nexus to the facilitation of new investment.”6 In other words, the incentive rate treatment cannot encourage an investment that has already occurred. The company itself had acknowledged that it had incurred the $31 million of costs “without assurance of cost recovery.”7

In a lengthy dissent, Judge Randolph took issue with, among other things, the majority’s characterization of when the “incentive” to invest begins. “The fallacy in [the majority’s] theory is its failure to recognize that FERC created the incentive when it promulgated the regulation in 2006,” Judge Randolph wrote, “well before San Diego began incurring costs for its transmission project.” Judge Randolph points out that FERC has rejected a “but for” test (i.e., the applicant does not need to show that the investment would not occur but for the incentive rate treatment), and that lack of “certain recovery” prior to a FERC application does not render the incentive treatment meaningless. Indeed, even if an applicant is approved for the rate treatment, the applicant still lacks “certain recovery,” since it will later have to make a prudency showing to recover the costs from ratepayers.

FERC has granted preorder abandonment incentives before, although not in a case where a party objected to such recovery, as here. As the first case to litigate the precise issue of when the abandonment incentive rate treatment may begin, this decision establishes a precedent that FERC is likely to follow in future cases. FERC has emphasized, however, that each application for transmission incentives will be evaluated on a case-by-case basis.


1 Energy Policy Act of 2005, Pub. L. No. 109-58, § 1241, 119 Stat. 961 (2005) (codified at 16 U.S.C.
§ 824s).

2 Promoting Transmission Investment Through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057 (2006), order on reh’g, Order No. 679-A, 117 FERC ¶ 61,345 (2006), order on reh’g, Order No. 679-B, 119 FERC ¶ 61,062 (2007); see also Promoting Transmission Investment Through Pricing Reform, 141 FERC ¶ 61,129 (2012) (“Policy Statement”).

3 Order No. 679 at P 155; see also Policy Statement, 141 FERC 61,129, at P 14.

4 San Diego Gas & Elec., 154 FERC ¶ 61,158, at PP 17-18 (2016).

5 San Diego Gas & Elec. v. FERC, No. 16-1433 (D.C. Cir. Jan. 15, 2019).

6 Id. at 15.

7 Id. at 19.

Share This Insight

Previous Entries

Speaking Energy

July 8, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to ISO New England Inc. (ISO-NE) directing ISO-NE and ISO-NE participating transmission owners to show cause as to why ISO-NE’s tariff should not be found to be unjust and unreasonable (ISO New England Inc., 195 FERC ¶ 61,215 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

July 7, 2026

On June 29, 2026, the Supreme Court granted a petition for certiorari in Leonard Hoffmann v. WBI Energy Transmission, Inc. (Hoffmann), which presents the question whether section 7 of the Natural Gas Act (NGA) requires pipeline companies using federal eminent domain authority to pay landowners’ attorney’s fees in states where landowners can recover those fees under state law. In the decision giving rise to the Supreme Court’s review, the U.S. Court of Appeals for the Eighth Circuit held that a group of ranchers were not entitled to recover their $383,300 in attorney’s fees incurred while negotiating their compensation—creating a circuit split with four other courts of appeals. Hoffmann will be heard during the Court’s October 2026 Term, and marks the second time in five years that the Court has agreed to interpret NGA section 7.

...

Read More

Speaking Energy

July 6, 2026

On June 29, 2026, the United States Supreme Court issued Trump v. Slaughter, fundamentally reshaping presidential removal authority over independent regulatory agencies. The decision overruled a 90-year-old precedent established in Humphrey’s Executor v. United States, which had upheld the constitutionality of commissioner removal protections in the Federal Trade Commission Act (FTC Act). As written, the FTC Act permits a commissioner’s removal “only for inefficiency, neglect of duty, or malfeasance in office.” In Slaughter, the Court was asked to reevaluate this standard following the President’s removal of a Democratic-appointed FTC commissioner from office in 2025 without cause. Finding for the President, the Court held that removal was permissible because the FTC Act’s for-cause removal protections for commissioners violate the separation of powers, specifically, the President’s removal power under Article II. The Court explained that the FTC exercises executive power because it promulgates binding rules, investigates and enforces those rules through administrative adjudications, and brings civil enforcement actions in federal court. It found that because it exercises these executive powers, its commissioners “must therefore be controlled by the Chief Executive, in whom such power is vested.” While previous recent cases addressing the scope of the Removal Power, Seila Law LLC v. Consumer Financial Protection Bureau and Collins v. Yellen purported to preserve some kernel of Humphrey’s, the Court made clear that “[i]f anything more is left of Humphrey’s, we overrule it.”

...

Read More

Speaking Energy

June 25, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to the California Independent System Operator Corporation (CAISO) directing CAISO and CAISO transmission owners to show cause as to why CAISO’s tariff should not be found to be unjust and unreasonable (California Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (the Order)) because it fails to sufficiently:

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.