As we previously noted, and as described in FERC’s order, “[b]eginning in 1993, Columbia Gas offered available firm capacity through auctions in which the notices were posted on the public side of its EBB,” then known as Navigator, as required by its tariff. Later, in 2008, “Columbia Gas replaced Navigator with a new software program (Navigates) that required a login ID to access its password-protected side.”  Then, in 2009, “the notices of the auctions were removed from the public side of Navigates and placed on its password-protected side.”

In September 2014, FERC’s Division of Audits and Accounting (“Audits”) referred the matter to OE, noting that it “believed that it was onerous and confusing for many shippers and potential shippers to locate Columbia Gas’ capacity auctions on Navigates.”  Audits also believed that “there was little transparency and notice of when the auctions were to occur, because the notices were posted on only the password-protected side of Navigates, and some auctions were held on different days, and at different times, without notice of those changes to the schedule. OE ultimately determined that the pipeline’s failure to post those notices “posed a serious threat to transparency in the market, and may have compromised [FERC’s] open-access transportation requirements.”

The civil penalty agreed to by Columbia Gas in this case illustrates the seriousness of FERC’s approach to compliance, not only with the Federal Power Act, Natural Gas Act, and FERC’s regulations and orders, but also with regulated entities’ tariffs approved under those statutes and regulations. Although all shippers had access to the notices, anyone else could obtain access to them by request, and no bidders affiliated with the pipeline participated in the auctions during the investigation period that included capacity awarded at a discount, OE still found the harm to transparency severe enough to warrant a $350,000 penalty.

Share This Insight

Previous Entries

Speaking Energy

November 25, 2025

We are pleased to share the program materials and a recording of Akin’s recently presented webinar, “Navigating the Evolving Landscape of Corporate PPAs.”

...

Read More

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.