FERC Directs NERC to Propose Mandatory Reliability Standards Regarding Physical Security Risks to the Bulk-Power System

Mar 10, 2014

Reading Time : 4 min

Three-Step Approach

The FERC did not impose a “one size fits all” approach to protecting physical security, but directed NERC to include in the Reliability Standards a three-step approach to addressing physical security risks.

Step One:  Risk Assessment and Identification of “Critical Facilities”

First, the FERC directed that the Reliability Standards “should require owners or operators of the Bulk-Power System to perform a risk assessment” to identify their “critical facilities,” i.e., those which, “if rendered inoperable or damaged, could have a critical impact on the operation of the interconnection through instability, uncontrolled separation or cascading failures.”  The FERC did not require a specific type of risk assessment, but stated that the methodologies used to determine “critical facilities” should be “based on objective analysis, technical expertise, and experienced judgment.”  In addition, the Reliability Standards “should allow owners or operators to consider resilience of the grid in the risk assessment when identifying critical facilities, and the elements that make up those facilities, such as transformers that typically require significant time to repair or replace.”

Step Two:  Threat and Vulnerability Evaluation

Second, the FERC directed that the Reliability Standards should require owners or operators of “critical facilities” to evaluate potential threats and vulnerabilities to those facilities based on factors such as location, size, function, existing protections, and “attractiveness as a target.”  Thus, the FERC stated, the Reliability Standards should require owners or operators to tailor their threat and vulnerability evaluation “to the unique characteristics of the identified critical facilities and the type of attacks that can be realistically contemplated.”

Step Three:  Security Plans

Third, the FERC directed that the Reliability Standards should require owners or operators of critical facilities to develop, validate, and implement security plans “designed to protect against attacks to those . . . facilities based on the assessment of the potential threats and vulnerabilities to their physical security.”  The Reliability Standards “need not dictate specific steps an entity must take to protect against attacks,” but must require owners and operators of critical facilities to have plan that provides “an adequate level of protection against the potential physical threats and vulnerabilities they face.”

Confidentiality, Independent and Periodic Review, and Implementation

Because of the sensitive nature of the information related to all three steps, the FERC also required NERC to include in the proposed Reliability Standards a procedure to “ensure confidential treatment of sensitive or confidential information but still allow for the [FERC], NERC and the Regional Entities to review and inspect any information that is needed to ensure compliance with the Reliability Standards.”

In addition, the FERC noted that the risk assessments, threat and vulnerability evaluations, and security plans should be independently reviewed by an entity other than the owner or operator, such as the FERC, NERC, a Regional Entity, Reliability Coordinator, or other entity with appropriate expertise, and that the proposed Reliability Standards should require that all three “be periodically reevaluated and revised to ensure their continued effectiveness.”

The FERC did not impose an implementation timeline for the Reliability Standards, but required NERC to “develop an implementation plan that requires owners or operators of the Bulk-Power System to implement the Reliability Standards in a timely fashion, balancing the importance of protecting the Bulk-Power System from harm while giving the owners or operators adequate time to meaningfully implement the requirements.”

Commissioner Norris’s Concurrence and Concerns

In a separate statement, Commissioner Norris expressed support for the order, but noted several areas of concern.  First, Commissioner Norris noted that the procedural approach the FERC selected, which, due to the its ex parte rules, will limit communication and engagement between industry and the FERC, as well as the “uniquely expedited nature” of the standards development process, could weaken that process.  To mitigate these issues, Commissioner Norris encouraged broad participation in the NERC standards development process and the forthcoming FERC rulemaking proceeding.  Commissioner Norris also cautioned parties to “be mindful of the Commission’s expectation that the number of critical facilities identified will be relatively small compared to the number of facilities that comprise the Bulk-Power System and [to] strive for balance between the measures related to physical security and the costs for consumers.”

Second, Commissioner Norris expressed his concern regarding the sensitivity of information regarding the physical vulnerabilities of the power grid and urged Congress to expeditiously create a clearly-defined Freedom of Information Act exemption to facilitate the exchange of information important to the Reliability Standards development process among industry, the FERC, and NERC without fear of disclosure.

Third, Commissioner Norris expressed his concern that recent efforts to protect reliability have focused too narrowly on physical security.  Instead, Commissioner Norris argued, equal focus on and dedication of resources to other threats, including cyber-attacks, geomagnetic disturbances, electromagnetic pulses, and natural disasters, are necessary.

Finally, Commissioner Norris cautioned against overreaction to the widely-reported April 2013 attack on PG&E’s Metcalf Substation, which has received significant attention in recent months from legislators and regulators (as we discussed in prior posts available here, and here).  Specifically, Commissioner Norris noted that he remains concerned that “recent momentum will result in the electricity sector potentially spending billions of dollars erecting physical barriers to protect our grid infrastructure,” with “most if not all of those costs . . . passed through to ratepayers.”  Instead, Commissioner Norris believes that “the more prudent approach is to focus on building a smarter and more agile grid, incorporating better communication and coordination, to mitigate against the multiple forms of risks that we face,” as well as to “more readily integrate intermittent resources, increase demand-side management capabilities, enhance the competitiveness of the wholesale energy market and more.”

Potential Implications

Ultimately, the effect of the FERC’s order will depend on the outcomes of the NERC standards development process and FERC rulemaking proceeding.  For owners and operators of facilities that are part of the Bulk-Power System that already have assessed the risks to and vulnerabilities of their critical facilities and implemented protective measures, the Reliability Standards, as ultimately adopted, might not require significant further action or costs.  For other entities, the costs of compliance with the new Reliability Standards could be significant.  Either way, because of the expedited timeline for NERC to develop and propose the standards, NERC-registered entities should be sure to voice their concerns in the NERC and FERC proceedings.

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.