FERC Extends Order No. 2023 Interconnection Process Reform Compliance Deadlines

October 27, 2023

Reading Time : 1 min

By: Stephen J. Hug, Emily P. Mallen, Ben N. Reiter, Angelica Gonzalez (Paralegal)

On October 25, 2023, the Federal Energy Regulatory Commission (FERC) issued an order1 that extended the deadline for electric transmission providers to comply with its Order No. 2023, “Improvements to Generator Interconnection Procedures and Agreements” (the Final Rule2). The new compliance filing deadline is Wednesday, April 3, 2024, or 210 calendar days from the Final Rule’s publication in the Federal Register on September 6, 2023. The previous deadline had been December 5, 2023, or 90 days from the publication date. The revised deadline applies to “all transmission providers, except for those with wholesale distribution access tariffs,” whose compliance filings are now due “within 90 calendar days of the date on which their relevant regional transmission organization or independent systems operator submits its compliance filing.”3 FERC clarified that the Extension Order “does not change or modify any other determination or other deadlines established by Order No. 2023, including the deadline for eligibility for interconnection customers to opt to proceed with a transitional serial study (for those interconnection customers tendered a facilities study agreement) or transitional cluster study (for those interconnection customers assigned a queue position) or to withdraw their interconnection requests without penalty (i.e., 30 calendar days after the transmission provider submits its initial compliance filing).”4

Under the Final Rule, transmission providers must speed up the processing of requests in their interconnection queues, adopt a “first-ready, first-served” cluster study process and integrate technological advancements in generation and transmission into the interconnection process. More information about the Final Rule, which was released on July 28, 2023, can be found in a previous Akin Speaking Energy Blog post and in a webinar hosted by Akin on August 3, 2023.


1 Improvements to Generator Interconnection Procs. & Agreements, 185 FERC ¶ 61,063 (2023) (Extension Order).

2 Improvements to Generator Interconnection Procs. & Agreements, Order No. 2023, 184 FERC ¶ 61,054 (2023).

3 Extension Order at PP 3, 9-10.

4 Id. at P 11.

Share This Insight

Previous Entries

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Midcontinent Independent System Operator, Inc. (MISO) directing MISO and MISO transmission owners to show cause as to why MISO’s tariff should not be found to be unjust and unreasonable (Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to PJM Interconnection, L.L.C. directing PJM and PJM transmission owners to show cause as to why PJM’s tariff should not be found to be unjust and unreasonable (PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (the Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 22, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Southwest Power Pool, Inc. (SPP) directing SPP and SPP transmission owners to show cause as to why SPP’s tariff should not be unjust and unreasonable (Southwest Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 18, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued show cause orders under section 206 of the Federal Power Act to PJM Interconnection, L.L.C. (PJM), Midcontinent Independent System Operator, Inc. (MISO), Southwest Power Pool, Inc. (SPP), California Independent System Operator Corporation (CAISO), ISO New England Inc. (ISO-NE) and New York Independent System Operator, Inc. (NYISO), together with their transmission owners, directing each region to justify or reform the tariff provisions governing how data centers and other large loads connect to and receive service from the transmission grid. The orders are part of FERC’s broader response to rapidly increasing electricity demand, particularly from data centers and other large loads, and advance the objectives of the Secretary of Energy’s October 2025 Advance Notice of Proposed Rulemaking (ANOPR) by seeking to accelerate “speed to power” while preserving grid reliability, affordability and consumer protections. 

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.