On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

As described further here, the EO directs FERC and other agencies to establish conditional sunset dates for existing regulations governing “energy production.” The EO requires that each agency issue a final rule incorporating a one year sunset provision into applicable regulations. The EO further requires that each agency provide the public with the opportunity to comment on the costs and benefits of regulations subject to the sunset requirement and allows agencies to extend the sunset date for a regulation for a period not to exceed five years.

The EO was notable because it is one of the first instances in which an executive order has directed FERC, an independent agency, to take specific actions to amend its regulations. FERC historically has taken the position that its compliance with executive orders is voluntary. It also was unclear how the EO’s directive would apply to FERC’s regulations, an agency that has only limited jurisdiction over the production of energy.

Order No. 914 implements the EO by incorporating sunsetting provisions into 53 regulations that the Commission has concluded are outdated, redundant, or seldom-used regulations. Under the sunsetting provision, each regulation would cease to have any effect 365 days after the effective date of Order No. 914 unless the Commission determines that the deadline should be extended after providing the public an opportunity to provide input on the costs and benefits of the regulation. Order No. 914 further provides that the amendments will become effective 45 days after the date of publication in the Federal Register, unless adverse comments are received within 30 days of publication. FERC concurrently issued a Notice of Proposed Rulemaking (NOPR) in the same docket to provide for consideration of any significant adverse comments submitted in response to Order No. 914. If significant adverse comments are received in response to the NOPR, then Order No. 914 would be rescinded and the NOPR would be used to commence a proceeding to consider the elimination of the regulations that FERC has proposed to sunset.

Below is a chart identifying the regulations and FERC’s justification for adding a sunsetting provision:

Regulation to be sunset

Reason for sunsetting

18 C.F.R. § 2.15: Specified reasonable rate of return for computing amortization reserves for hydroelectric project licenses.

Outdated and no longer used; imposes duplicative requirements.

18 C.F.R. § 2.18: Phased electric rate increase filings.

FERC no longer received phased rate increase filings.

18 C.F.R. § 2.21: Regional Transmission Groups.

Outdated because Regional Transmission Groups have been replaced by Regional Transmission Organizations and Independent System Operators.

18 C.F.R. § 2.25: Ratemaking treatment of the cost of emissions allowances in coordination transaction.

Not needed after the transition to market-based rates for most generation facilities.

18 C.F.R. § 2.26: Policies concerning review of applications under section 203.

Duplicative of Part 33.

18 C.F.R. § 2.27: Availability of North American Energy Standards Board (NAESB) Smart Grid Standards as non-mandatory guidance.

Not needed as the standards are not mandatory.

18 C.F.R. § 2.78: Utilization and conservation of natural resources – natural gas.

Not needed now that natural gas pipelines are functionally unbundled.

18 C.F.R. § 2.103: Statement of policy respecting take or pay provisions in gas purchase contracts.

Not needed now that natural gas pipelines are functionally unbundled. Covered by 18 C.F.R. § 284.7(e).

18 C.F.R. § 2.105 Gas supply charges.

Not needed now that natural gas pipelines are functionally unbundled.

18 C.F.R. § 5.31 Transition provision.

Obsolete as it was only effective between 2003 and 2005.

18 C.F.R. § 131.50: Reports of proposals received.

Not needed as this regulation is typically waived for applicants.

18 C.F.R. § 131.52: Certificate of Concurrence.

Not needed as the sample form is informational and not a requirement. FERC will post the sample on its Website.

18 C.F.R. § 156.5(a)(9): Exhibit H-Total Gas Supply Data.

Not needed now that natural gas pipelines are functionally unbundled.

18 C.F.R. § 157.14(a)(11): Exhibit H-Total Gas Supply Data.

Not needed now that natural gas pipelines are functionally unbundled.

18 C.F.R. § 157.202(b)(9): Right-of-way Grantor Defines “right of way grantor”

Not needed as the term is not used in the Commission’s regulations outside of one instance and has a commonly understood meaning.

18 C.F.R. § 157.218: Changes in Customer Name. Requires a certificate holder to submit any customer names changes each year in its annual report.

Redundant, as information is already required under 18 C.F.R. § 154.111 (Index of customer).

18 C.F.R. § 287.101: Rules Generally Applicable to Powerplant and Industrial Fuel Use

Issued under repealed statute.

18 C.F.R. § 375.104, 375.105 Transfer of proceedings from other agencies to the Commission, Filings.

Transitional regulations after creation of the Commission and the Department of Energy; no longer needed.

18 C.F.R. § 385.101(b)(3): Rule 101 Exceptions.

Refers to 49 C.F.R. X, which the Commission no longer relies upon.

18 C.F.R. § 385.504(b)(19): Duties and powers of presiding officers (Rule 504), Powers- Rule on motions of reconsideration of an initial decision as provided in Rule 717.

Not needed as Rule 717 has been removed.

18 C.F.R. § 385.602(c)(1)(ii): Submission of settlement offers (Rule 602), Contents of Offer.

Explanatory statement requirement is not needed as they are largely duplicative of the settlement agreement itself.

18 C.F.R. § 385.902(b)-(c): Interim remedial order for immediate compliance, Order of disallowance.

Not needed as they reference orders issued pursuant to repealed regulations.

18 C.F.R. § 385.904(b): Commencement of proceeding (Rule 904).

Not needed as interim remedial orders are no longer issued.

18 C.F.R. § 385.915: Off-the-record communications.

Not needed as the broader Rule 2201 applies to all off-record communications.

18 C.F.R. § 385.1012: Off-the-record Communications (Rule 1012).

Not needed as the broader Rule 2201 applies to all off-record communications.

18 C.F.R. § 36.1(b)(1): Notice provisions applicable to applications for transmissions services under section 211 of the Federal Power Act.

Form of notice no longer needed.

18 C.F.R. § 153.20(c): Where to file paper copies of export/import applications.

Form of notice no longer needed.

18 C.F.R. § 157.6(a)(2): Requires providing a paper copy of maps and diagrams.

Form of notice no longer needed.

18 C.F.R. § 157.6(b)(7): Requires applicants to provide a form of notice for the Federal Register.

Form of notice no longer needed.

18 C.F.R. § 157.205(b)(5): A form of notice of the application suitable for publication in the Federal Register in accordance with the specifications in § 385.203(d).

Form of notice no longer needed.

18 C.F.R. § 300.10(a)(1): Application for confirmation and approval of the Rates of Federal Power Marketing Administrations.

Form of notice no longer needed.

18 C.F.R. § 366.4(b)(1), (b)(3), (c)(1), and (c)(2): FERC-65A, exemption notification, and FERC-65-B waiver notification

Notice requirements no longer needed.

18 C.F.R. § 366.7(a) and (7)(b): Procedures for obtaining exempt wholesale generator and foreign utility company status.

Forms of notice no longer needed.

18 C.F.R. § 385.203(d): Contents of pleadings and tariff or rate filings (Rule 203), Form of notice.

Form of notice no longer required.

18 C.F.R. § 385.206(b)(10): Complaints (Rule 206), Form of notice.

Form of notice no longer required.

18 C.F.R. §§ 1101-1117: Subpart K – Petitions for Adjustments Under the Natural Gas Policy Act

These 17 rules related to the adjustment provisions of the Natural Gas Policy Act that have been repealed, and thus these regulations are obsolete.

 

Share This Insight

Previous Entries

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.