FERC Overrules Northern Natural and Finds It Does Not Need to Identify Whether a Natural Gas Project’s Greenhouse Gas Emissions are ‘Significant’

December 5, 2024

Reading Time : 3 min

On November 27, 2024, in Venture Global, CP2 LNG, LLC,1 the Federal Energy Regulatory Commission’s (FERC or Commission) explicitly overruled precedent set in Northern Natural Gas Co.,2 a 2021 decision in which FERC made an affirmative finding that an interstate natural gas pipeline project it was certificating under section 7 of the Natural Gas Act (NGA) would not make a “significant” contribution to global climate change. Northern Natural is the only FERC decision in which a so-called significance determination was made with respect to greenhouse gas emissions (GHG) arising from a FERC-regulated natural gas infrastructure project. In Venture Global, FERC rejected arguments that it needed to follow Northern Natural and assess the significance of GHG emissions in all NGA certificate proceedings to comply with the National Environmental Policy Act (NEPA). NEPA requires federal agencies, including FERC, that perform “major federal actions,” which include issuing NGA section 7 certificates, to prepare an environmental impact statement (EIS) if the action will “significantly affect[] the quality of the human environment.”3 FERC has been under pressure to fully explain why it has chosen not to apply Northern Natural’s significance analysis in subsequent cases, and that issue is currently before FERC on remand from the U.S. Court of Appeals for the District of Columbia (D.C. Circuit) in Healthy Gulf et al. v. FERC, which reviewed FERC’s approval of a liquefied natural gas (LNG) terminal under NGA section 3.

In Venture Global, FERC rejected arguments that it needed to make a binary significance or insignificance determination to comply with NEPA or regulations implementing NEPA, particularly if the agency prepares an EIS that discusses the significance of emissions. FERC also explains that Northern Natural does not represent an agency policy or practice necessitating a binary result. FERC held that Northern Natural’s determination was “sui generis” as it merely compared the project’s reasonably foreseeable GHG emissions to the total of GHG emissions in the United States as well as to state inventories, but did not explain the basis upon which it determined significance, nor identified any tool or method for making a significance determination. FERC also explained that it could not:

characterize any project’s GHG emissions as significant or insignificant because we are unable to identify any accepted tool or method, including use of the social cost of GHGs, that would allow us to determine what level of GHG emissions’ contribution to adverse climate change impacts is significant under NEPA. We note that to date, no other Federal agency, including the U.S. Environmental Protection Agency (EPA) and [Council on Environmental Quality], has established either an accepted tool or method or a threshold for determining significance that the Commission could adopt.

FERC also rejected arguments that that it needed to use the “social cost of GHGs,” a tool that allows policy-makers to estimate the dollar value associated with emitted a metric ton of GHGs, to make a significance determination. FERC, however, committed to continue to calculate and publish the social cost of GHGs for a project’s reasonably foreseeable GHG emissions to fulfill its obligations under NEPA of public disclosure.

Venture Global represents the clearest explanation to date regarding FERC’s position on its role to evaluate reasonably foreseeable GHG emissions arising from projects it regulates. The clarity likely may be a biproduct of the new Commissioners. While Commissioner Chang did not participate in the decision, Venture Global is a bipartisan decision with no dissents. It leaves some things unknown, however. FERC states that it will continue to consider GHG impacts on a case-by-case basis. It also leaves open the possibility that natural gas infrastructure projects will always require an EIS to address GHGs when an explicit significance determination cannot be made. And, while the natural gas industry will appreciate Venture Global’s holdings on significance for GHGs, other aspects of the decision are unfavorable, including FERC’s decision to pause construction of an LNG terminal and related pipeline project while it completes a supplemental EIS process. This is the topic of a different Akin Speaking Energy post, which can be found here.


1 189 FERC ¶ 61,148 (2024).

2 174 FERC ¶ 61,189 (2021).

3 42 U.S.C. 4332(2)(C).

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.