FERC Revises Gas Nomination Regulations, Leaves Gas Day Unchanged

May 5, 2015

Reading Time : 2 min

The NOPR called on the North American Energy Standards Board (NAESB) to work with the gas and electric industries to develop standards in response to the proposals in the NOPR.  Working with industry participants, NAESB modified its Wholesale Gas Quadrant (WGQ) business practice standards to move the start of the Timely Nomination Cycle from 11:30 a.m. CCT to 1 p.m. CCT and to establish three intraday nomination cycles.  However, NAESB was unable to reach a consensus regarding the start of the Gas Day.

In Order No. 809, FERC adopted NAESB’s modified business practice standards.  Examining the record with regard to a change in the Gas Day, it concluded that a change in the start of the Gas Day might not “provide sufficient benefits to outweigh the operational and safety impacts and costs” of the change, particularly the increased need for nighttime work from pipeline and local distribution company employees.  FERC observed that it had requested information about gas generator derates from the Regional Transmission Organizations (RTO) and Independent System Operators (ISO), and that the resulting data provided only limited evidence that the timing of the Gas Day was a primary contributor even to those derates that were connected to fuel issues.  Therefore, FERC concluded that the evidence did not warrant ordering a nationwide change in the Gas Day.

In addition to changes in the timing of nominations, FERC also decided that it would require pipelines to offer multiparty firm transportation contracts, as proposed in the NOPR, but that the requirement would become effective only if shippers requested this option.  FERC declined to order a blanket waiver of the Shipper-Must-Have-Title rule for the purposes of multiparty contracts, but stated that it would consider such waivers on a case-by-case basis if granting the waiver would be in the public interest.  FERC specifically noted that assisting gas-fired generators in gaining access to firm natural gas transportation service might be such a case.

FERC’s decision to leave the Gas Day untouched further suggests that it believes that resolving the coordination issue is a problem for both industries.  On the same day that it issued the NOPR, FERC also instituted proceedings under Section 206 of the Federal Power Act to ensure that the RTOs and ISOs institute scheduling practices that mesh with the revised gas nomination schedules.  FERC also initiated a proceeding under Section 5 of the Natural Gas Act to determine whether natural gas pipelines were giving proper notice of offers to purchase released capacity.  FERC also observed that RTOs and ISOs that have been most affected by gas derates, PJM and ISO-NE, have undertaken independent steps to address generator performance.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.