FERC Revises Its Regulations Regarding Computation of Time

Feb 11, 2019

Reading Time : 2 min

The Final Rule modifies Rule 2007 to address days when FERC “is closed due to adverse conditions—including inclement weather—even though some official duties may be performed by telework-ready employees.” FERC explains that the change will prevent “unintended Commission action by operation of law,” such as where a pipeline or public utility rate filing would become effective automatically absent a FERC order at the end of a statutory period, and “provides clarity as to filing deadlines and deadlines for action by the Commission.”

Previously, Rule 2007 provided that the last day of any period is included in that period, “unless it is a Saturday, Sunday, day on which the Commission closes due to adverse conditions and does not reopen prior to its official close of business, part-day holiday that affects the Commission, or legal public holiday . . . , in which case the period does not end until the close of the Commission business of the next day which is not” such a day.

FERC explains that Office of Personnel Management regulations promulgated in April 2018 to implement the weather and safety leave provisions of the Administrative Leave Act of 2016 require “employees that are telework-ready continue to perform official duties, even though Federal offices are closed due to severe weather or another emergency situation.” Thus, to avoid confusion when FERC closes due to adverse conditions but some FERC employees continue to perform official duties, FERC revised Rule 2007 to make clear that such a day will not be counted as the last day of the relevant period. FERC explains that, “[i]n such circumstances, employee and public access to the Commission’s physical facilities may be restricted, not all employees may be telework-ready, and not all telework-ready employees may be able to telework due to the adverse conditions.” Accordingly, when FERC is closed due to adverse conditions, its “ability to accept filings and issue orders . . . may be affected,” and “the public’s ability to submit a filing on the last day on which a filing is due may also be restricted”; accordingly, such a day should not be counted as the last day of any relevant period.

Importantly, the changes to Rule 2007 address only the “last day of any time period” (i.e., closures do not otherwise extend any relevant period) and days when FERC closes and does not reopen before 5:00 p.m. ET on that day.

Share This Insight

Previous Entries

Speaking Energy

February 10, 2026

The global energy sector enters 2026 amid major policy shifts, geopolitical tension and evolving market dynamics. The Trump administration’s reversal of Biden-era climate initiatives and renewed emphasis on domestic production have reshaped the policy landscape, offering a more favorable regulatory environment even as conflicts abroad, oil price volatility and shifting trade policies tempered deal activity through 2025.

...

Read More

Speaking Energy

January 22, 2026

On January 16, 2026, the National Energy Dominance Council (NDEC) and governors from each of the 13 states in PJM issued a Statement of Principles urging PJM Interconnection, L.L.C. (PJM) to hold an emergency backstop auction and take other measures to support the entry of new capacity to preserve the reliability of the PJM region. The Statement of Principles calls on PJM to expeditiously file with the Federal Energy Regulatory Commission (FERC or the Commission) tariff revisions that would overhaul aspects of PJM’s market rules to address rising electricity prices and growing reliability risks in the PJM region. The Statement of Principles comes at a time of growing concern that PJM will not have sufficient capacity in the coming years to meet demand due to the retirement of existing generation resources, the glacial pace of new entry and projected increased demand associated with data center development.

...

Read More

Speaking Energy

December 21, 2025

On December 19, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued its much-anticipated order on show cause proceeding concerning the co-location of generation and load within the PJM Interconnection, L.L.C. (PJM) market.[1] In the order, the Commission finds that PJM’s tariff is unjust and unreasonable because it does not provide sufficient clarity on the rates, terms, and conditions of service applicable to generators serving Co-Located Load and does not include transmission services appropriate for customers that are willing and able to limit their use of the transmission system in certain conditions. 

...

Read More

Speaking Energy

November 25, 2025

We are pleased to share the program materials and a recording of Akin’s recently presented webinar, “Navigating the Evolving Landscape of Corporate PPAs.”

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.