FERC Wins Statute of Limitations Fight in Market Manipulation Enforcement Case, But Uncertainty Remains

Jan 8, 2019

Reading Time : 5 min

Brief Background on the Case

The Day-Ahead Load Response Program (DALRP) was a demand response program run by ISO New England until June 2012. In July 2012, FERC initiated Order to Show Cause (OSC) proceedings against four entities, including Respondents, alleged to have committed fraud in connection with the DALRP by altering “baseline” energy consumption during a test period for the purpose of misrepresenting the amount of demand response they would actually provide once the program started. All subjects elected the Federal Power Act’s (FPA) “de novo review” procedural option, where FERC assesses penalties without an agency hearing and then files an action in federal district court to enforce the penalty, which the court reviews de novo. In August 2013, following the OSC proceedings, FERC assessed civil penalties against CES, Silkman, and one of the other subjects (the fourth settled with FERC during the OSC proceeding). In December 2013, after the subjects did not pay the assessed penalties, FERC filed enforcement actions in the District of Massachusetts. In April 2016, the court denied the subjects’ motion to dismiss (including on statute of limitations grounds), but transferred to the case to the District of Maine.1 The third subject subsequently settled with FERC, but Respondents continued to litigate. In February 2018, Respondents and FERC filed cross-motions for partial summary judgment on Respondents’ statute of limitations defense, which claimed that FERC’s December 2013 enforcement action was untimely since it was filed more than five years after the alleged manipulation occurred (which began in 2007).

The January 4 Order

The court found that FERC’s enforcement action against Respondents was timely even though it was filed in court more than five years after the conduct occurred. The court found the issue was governed by the First Circuit’s decision in U.S. v. Meyer,2 which held that where an agency proceeding (there, a Department of Commerce (DOC) administrative enforcement proceeding) is a statutory prerequisite to a civil enforcement action, the civil enforcement claim does not “accrue” until the penalty has been assessed administratively. The result, under Meyer, is that there are two limitations periods—one five-year period to initiate administrative proceedings to assess the penalty, and another five-year period to enforce the penalty in court once it has been assessed. Thus, although FERC did not file its district court enforcement action against Respondents until December 2013 (well more than five years after the conduct began), the court found FERC’s action was timely.

The court rejected Respondents’ argument that Meyer was no longer good law following the Supreme Court’s decisions in Gabelli v. SEC (which held that the “discovery rule” in fraud actions does not extend to Securities and Exchange Commission (SEC) enforcement actions) and Kokesh v. SEC (which held that disgorgement in SEC enforcement actions constitutes a penalty subject to the statute of limitations).3 The court found that neither of these cases addressed the specific statute of limitations questions presented in Meyer and Silkman: when the limitations period for an enforcement action begins to run when an administrative proceeding is a statutory prerequisite to bringing a case. The court also rejected Respondents’ argument that Meyer did not apply because FERC’s penalty assessment proceeding (the OSC process) is merely a “decision to prosecute” rather than a true administrative proceeding with procedures and due process comparable to the DOC proceeding in Meyer (which was a more traditional agency adjudication involving a hearing before an administrative law judge). The court found that the FERC OSC proceeding, despite not providing for discovery or a live hearing, was more than merely a prosecutorial determination such that the Meyer framework of two statute of limitations periods should apply.

Implications

FERC is still likely to move cases more quickly. This marks FERC’s second consecutive win on statute of limitations challenges to enforcement actions—with the last case being the September 2018 decision in FERC v. Powhatan Energy Fund in the Eastern District of Virginia (discussed here).4 While one might think FERC would be emboldened by these wins, we continue to expect that FERC will try to bring cases more quickly to mitigate statute of limitations litigation risk. Courts within the First Circuit have found Meyer to provide a helpful (and binding) framework for considering FERC enforcement cases. However, courts elsewhere have (understandably) found statute of limitations questions confounding given the FPA’s unique procedural framework. This was reflected in the Powhatan decision, where the court (reluctantly) agreed with FERC that its claim technically did not accrue until FERC had assessed the penalty administratively rather than at the time of the conduct, but took the unusual step of allowing defendants to seek an interlocutory appeal before the Fourth Circuit (and inviting Congress to provide clarity). Further, the Powhatan court, despite ruling in FERC’s favor, found that Meyer should not govern FPA “de novo review” cases because of the differences between FERC’s penalty assessment process and a traditional agency adjudication. The bottom line, in our view, is that the agency will continue to face real statute of limitations risk by not filing a federal complaint within five years of the conduct—particularly in jurisdictions that do not follow Meyer.

All eyes on the Fourth Circuit. As noted above, in the Powhatan case, the court ruled in FERC’s favor on the statute of limitations question but allowed the defendants to seek an interlocutory appeal. The Fourth Circuit has agreed to hear the case, and briefing will begin later this month. This will be the first appellate decision on this issue.

Disgorgement likely a “penalty” for statute of limitations purposes. As we wrote about here, the Kokesh case—which held that disgorgement of unjust profits in SEC enforcement cases is subject to the five-year statute of limitations—should apply equally to FERC. In Powhatan, the court concluded that Kokesh would apply to disgorgement in FERC enforcement cases provided the disgorgement is punitive in nature rather than purely remedial. But the court found this question was fact-specific and could not be resolved at the motion to dismiss stage. The Silkman court, however, found the question more straightforward as a matter of law, holding that, under Kokesh, disgorgement in FERC enforcement cases constitutes a penalty and is subject to the five-year statute of limitations.


1 FERC v. Silkman, 177 F. Supp. 3d 683 (D. Mass. 2016) (Order on Mot. to Dismiss).  FERC v. Silkman, No. 13-13054-DPW, 2016 U.S. Dist. LEXIS 48409 (D. Mass. April 11, 2016) (Order on Mot. to Transfer).

2 808 F.2d 912 (1st Cir. 1987).

3 See Gabelli v. SEC, 568 U.S. 442 (2013); Kokesh v. SEC, 137 S. Ct. 1635 (2017).

4 Order on Motions for Summary Judgment, FERC v. Silkman, No. 1:16-cv-00205-JAW (D. Me. Jan. 4, 2019).

Share This Insight

Previous Entries

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.