FERC Wins Statute of Limitations Fight in Market Manipulation Enforcement Case, But Uncertainty Remains

Jan 8, 2019

Reading Time : 5 min

Brief Background on the Case

The Day-Ahead Load Response Program (DALRP) was a demand response program run by ISO New England until June 2012. In July 2012, FERC initiated Order to Show Cause (OSC) proceedings against four entities, including Respondents, alleged to have committed fraud in connection with the DALRP by altering “baseline” energy consumption during a test period for the purpose of misrepresenting the amount of demand response they would actually provide once the program started. All subjects elected the Federal Power Act’s (FPA) “de novo review” procedural option, where FERC assesses penalties without an agency hearing and then files an action in federal district court to enforce the penalty, which the court reviews de novo. In August 2013, following the OSC proceedings, FERC assessed civil penalties against CES, Silkman, and one of the other subjects (the fourth settled with FERC during the OSC proceeding). In December 2013, after the subjects did not pay the assessed penalties, FERC filed enforcement actions in the District of Massachusetts. In April 2016, the court denied the subjects’ motion to dismiss (including on statute of limitations grounds), but transferred to the case to the District of Maine.1 The third subject subsequently settled with FERC, but Respondents continued to litigate. In February 2018, Respondents and FERC filed cross-motions for partial summary judgment on Respondents’ statute of limitations defense, which claimed that FERC’s December 2013 enforcement action was untimely since it was filed more than five years after the alleged manipulation occurred (which began in 2007).

The January 4 Order

The court found that FERC’s enforcement action against Respondents was timely even though it was filed in court more than five years after the conduct occurred. The court found the issue was governed by the First Circuit’s decision in U.S. v. Meyer,2 which held that where an agency proceeding (there, a Department of Commerce (DOC) administrative enforcement proceeding) is a statutory prerequisite to a civil enforcement action, the civil enforcement claim does not “accrue” until the penalty has been assessed administratively. The result, under Meyer, is that there are two limitations periods—one five-year period to initiate administrative proceedings to assess the penalty, and another five-year period to enforce the penalty in court once it has been assessed. Thus, although FERC did not file its district court enforcement action against Respondents until December 2013 (well more than five years after the conduct began), the court found FERC’s action was timely.

The court rejected Respondents’ argument that Meyer was no longer good law following the Supreme Court’s decisions in Gabelli v. SEC (which held that the “discovery rule” in fraud actions does not extend to Securities and Exchange Commission (SEC) enforcement actions) and Kokesh v. SEC (which held that disgorgement in SEC enforcement actions constitutes a penalty subject to the statute of limitations).3 The court found that neither of these cases addressed the specific statute of limitations questions presented in Meyer and Silkman: when the limitations period for an enforcement action begins to run when an administrative proceeding is a statutory prerequisite to bringing a case. The court also rejected Respondents’ argument that Meyer did not apply because FERC’s penalty assessment proceeding (the OSC process) is merely a “decision to prosecute” rather than a true administrative proceeding with procedures and due process comparable to the DOC proceeding in Meyer (which was a more traditional agency adjudication involving a hearing before an administrative law judge). The court found that the FERC OSC proceeding, despite not providing for discovery or a live hearing, was more than merely a prosecutorial determination such that the Meyer framework of two statute of limitations periods should apply.

Implications

FERC is still likely to move cases more quickly. This marks FERC’s second consecutive win on statute of limitations challenges to enforcement actions—with the last case being the September 2018 decision in FERC v. Powhatan Energy Fund in the Eastern District of Virginia (discussed here).4 While one might think FERC would be emboldened by these wins, we continue to expect that FERC will try to bring cases more quickly to mitigate statute of limitations litigation risk. Courts within the First Circuit have found Meyer to provide a helpful (and binding) framework for considering FERC enforcement cases. However, courts elsewhere have (understandably) found statute of limitations questions confounding given the FPA’s unique procedural framework. This was reflected in the Powhatan decision, where the court (reluctantly) agreed with FERC that its claim technically did not accrue until FERC had assessed the penalty administratively rather than at the time of the conduct, but took the unusual step of allowing defendants to seek an interlocutory appeal before the Fourth Circuit (and inviting Congress to provide clarity). Further, the Powhatan court, despite ruling in FERC’s favor, found that Meyer should not govern FPA “de novo review” cases because of the differences between FERC’s penalty assessment process and a traditional agency adjudication. The bottom line, in our view, is that the agency will continue to face real statute of limitations risk by not filing a federal complaint within five years of the conduct—particularly in jurisdictions that do not follow Meyer.

All eyes on the Fourth Circuit. As noted above, in the Powhatan case, the court ruled in FERC’s favor on the statute of limitations question but allowed the defendants to seek an interlocutory appeal. The Fourth Circuit has agreed to hear the case, and briefing will begin later this month. This will be the first appellate decision on this issue.

Disgorgement likely a “penalty” for statute of limitations purposes. As we wrote about here, the Kokesh case—which held that disgorgement of unjust profits in SEC enforcement cases is subject to the five-year statute of limitations—should apply equally to FERC. In Powhatan, the court concluded that Kokesh would apply to disgorgement in FERC enforcement cases provided the disgorgement is punitive in nature rather than purely remedial. But the court found this question was fact-specific and could not be resolved at the motion to dismiss stage. The Silkman court, however, found the question more straightforward as a matter of law, holding that, under Kokesh, disgorgement in FERC enforcement cases constitutes a penalty and is subject to the five-year statute of limitations.


1 FERC v. Silkman, 177 F. Supp. 3d 683 (D. Mass. 2016) (Order on Mot. to Dismiss).  FERC v. Silkman, No. 13-13054-DPW, 2016 U.S. Dist. LEXIS 48409 (D. Mass. April 11, 2016) (Order on Mot. to Transfer).

2 808 F.2d 912 (1st Cir. 1987).

3 See Gabelli v. SEC, 568 U.S. 442 (2013); Kokesh v. SEC, 137 S. Ct. 1635 (2017).

4 Order on Motions for Summary Judgment, FERC v. Silkman, No. 1:16-cv-00205-JAW (D. Me. Jan. 4, 2019).

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.