FERC Wins Statute of Limitations Fight in Market Manipulation Enforcement Case, But Uncertainty Remains

Jan 8, 2019

Reading Time : 5 min

Brief Background on the Case

The Day-Ahead Load Response Program (DALRP) was a demand response program run by ISO New England until June 2012. In July 2012, FERC initiated Order to Show Cause (OSC) proceedings against four entities, including Respondents, alleged to have committed fraud in connection with the DALRP by altering “baseline” energy consumption during a test period for the purpose of misrepresenting the amount of demand response they would actually provide once the program started. All subjects elected the Federal Power Act’s (FPA) “de novo review” procedural option, where FERC assesses penalties without an agency hearing and then files an action in federal district court to enforce the penalty, which the court reviews de novo. In August 2013, following the OSC proceedings, FERC assessed civil penalties against CES, Silkman, and one of the other subjects (the fourth settled with FERC during the OSC proceeding). In December 2013, after the subjects did not pay the assessed penalties, FERC filed enforcement actions in the District of Massachusetts. In April 2016, the court denied the subjects’ motion to dismiss (including on statute of limitations grounds), but transferred to the case to the District of Maine.1 The third subject subsequently settled with FERC, but Respondents continued to litigate. In February 2018, Respondents and FERC filed cross-motions for partial summary judgment on Respondents’ statute of limitations defense, which claimed that FERC’s December 2013 enforcement action was untimely since it was filed more than five years after the alleged manipulation occurred (which began in 2007).

The January 4 Order

The court found that FERC’s enforcement action against Respondents was timely even though it was filed in court more than five years after the conduct occurred. The court found the issue was governed by the First Circuit’s decision in U.S. v. Meyer,2 which held that where an agency proceeding (there, a Department of Commerce (DOC) administrative enforcement proceeding) is a statutory prerequisite to a civil enforcement action, the civil enforcement claim does not “accrue” until the penalty has been assessed administratively. The result, under Meyer, is that there are two limitations periods—one five-year period to initiate administrative proceedings to assess the penalty, and another five-year period to enforce the penalty in court once it has been assessed. Thus, although FERC did not file its district court enforcement action against Respondents until December 2013 (well more than five years after the conduct began), the court found FERC’s action was timely.

The court rejected Respondents’ argument that Meyer was no longer good law following the Supreme Court’s decisions in Gabelli v. SEC (which held that the “discovery rule” in fraud actions does not extend to Securities and Exchange Commission (SEC) enforcement actions) and Kokesh v. SEC (which held that disgorgement in SEC enforcement actions constitutes a penalty subject to the statute of limitations).3 The court found that neither of these cases addressed the specific statute of limitations questions presented in Meyer and Silkman: when the limitations period for an enforcement action begins to run when an administrative proceeding is a statutory prerequisite to bringing a case. The court also rejected Respondents’ argument that Meyer did not apply because FERC’s penalty assessment proceeding (the OSC process) is merely a “decision to prosecute” rather than a true administrative proceeding with procedures and due process comparable to the DOC proceeding in Meyer (which was a more traditional agency adjudication involving a hearing before an administrative law judge). The court found that the FERC OSC proceeding, despite not providing for discovery or a live hearing, was more than merely a prosecutorial determination such that the Meyer framework of two statute of limitations periods should apply.

Implications

FERC is still likely to move cases more quickly. This marks FERC’s second consecutive win on statute of limitations challenges to enforcement actions—with the last case being the September 2018 decision in FERC v. Powhatan Energy Fund in the Eastern District of Virginia (discussed here).4 While one might think FERC would be emboldened by these wins, we continue to expect that FERC will try to bring cases more quickly to mitigate statute of limitations litigation risk. Courts within the First Circuit have found Meyer to provide a helpful (and binding) framework for considering FERC enforcement cases. However, courts elsewhere have (understandably) found statute of limitations questions confounding given the FPA’s unique procedural framework. This was reflected in the Powhatan decision, where the court (reluctantly) agreed with FERC that its claim technically did not accrue until FERC had assessed the penalty administratively rather than at the time of the conduct, but took the unusual step of allowing defendants to seek an interlocutory appeal before the Fourth Circuit (and inviting Congress to provide clarity). Further, the Powhatan court, despite ruling in FERC’s favor, found that Meyer should not govern FPA “de novo review” cases because of the differences between FERC’s penalty assessment process and a traditional agency adjudication. The bottom line, in our view, is that the agency will continue to face real statute of limitations risk by not filing a federal complaint within five years of the conduct—particularly in jurisdictions that do not follow Meyer.

All eyes on the Fourth Circuit. As noted above, in the Powhatan case, the court ruled in FERC’s favor on the statute of limitations question but allowed the defendants to seek an interlocutory appeal. The Fourth Circuit has agreed to hear the case, and briefing will begin later this month. This will be the first appellate decision on this issue.

Disgorgement likely a “penalty” for statute of limitations purposes. As we wrote about here, the Kokesh case—which held that disgorgement of unjust profits in SEC enforcement cases is subject to the five-year statute of limitations—should apply equally to FERC. In Powhatan, the court concluded that Kokesh would apply to disgorgement in FERC enforcement cases provided the disgorgement is punitive in nature rather than purely remedial. But the court found this question was fact-specific and could not be resolved at the motion to dismiss stage. The Silkman court, however, found the question more straightforward as a matter of law, holding that, under Kokesh, disgorgement in FERC enforcement cases constitutes a penalty and is subject to the five-year statute of limitations.


1 FERC v. Silkman, 177 F. Supp. 3d 683 (D. Mass. 2016) (Order on Mot. to Dismiss).  FERC v. Silkman, No. 13-13054-DPW, 2016 U.S. Dist. LEXIS 48409 (D. Mass. April 11, 2016) (Order on Mot. to Transfer).

2 808 F.2d 912 (1st Cir. 1987).

3 See Gabelli v. SEC, 568 U.S. 442 (2013); Kokesh v. SEC, 137 S. Ct. 1635 (2017).

4 Order on Motions for Summary Judgment, FERC v. Silkman, No. 1:16-cv-00205-JAW (D. Me. Jan. 4, 2019).

Share This Insight

Previous Entries

Speaking Energy

March 10, 2026

Federal energy regulators are assuming expanded roles as the administration prioritizes energy dominance and infrastructure development to meet unprecedented power demand. FERC Chairman Laura Swett has vowed to expedite data center interconnections while addressing jurisdictional challenges, warning that unmet electricity demand could drive data centers abroad and create national security risks. The agency is processing pipeline applications faster than in prior years and considering blanket authorizations for certain LNG and hydroelectric projects to streamline approvals. 

Pipeline projects previously stalled by Clean Water Act permits are being revitalized, particularly in northeastern states where historically high electricity prices have increased openness to natural gas infrastructure. The Department of Energy is expanding its emergency authority to require retention of generation resources and has granted major LNG export approvals, signaling commitment to expanding U.S. export capacity under a streamlined framework that deprioritizes climate considerations.  

The Administration is bullish on the opportunities for the U.S. energy industry in Venezuela and eager to support companies willing to navigate the political risk inherent in the operations at the moment. Early meetings with President Trump and industry leaders showed the path forward may be longer and more complex than anticipated by the President. 

As permitting reforms advance and the pendulum swings toward fossil fuel favorability, the regulatory and policy landscape is fundamentally reshaping energy infrastructure development timelines and investment opportunities. 

Oil & Gas in 2026: Energy Policy & Regulation 

Delve into the complete regulatory & policy outlook at our Oil & Gas in 2026 report.

...

Read More

Speaking Energy

March 3, 2026

Macroeconomic turbulence and volatile commodity markets significantly influenced oil & gas M&A activity throughout 2025, with deals showing renewed momentum only in the year's second half.  

...

Read More

Speaking Energy

February 24, 2026

On February 19, 2026, the Federal Energy Regulatory Commission (FERC) issued an order rescinding the soft price cap for bilateral spot market energy sales in the Western Electricity Coordinating Council (WECC) region.1 As previously covered, on July 15, 2025, FERC initiated a Federal Power Act Section 206 proceeding following the D.C. Circuit’s decision finding that FERC must apply the Mobile-Sierra public interest standard before ordering refunds for above-cap bilateral sales and vacating FERC’s orders requiring refunds for certain bilateral spot market transactions in the WECC region that exceeded the $1,000 MWh soft price cap.2 FERC’s Order follows through on the proposal it made last July to eliminate the WECCs soft price cap and marks a recognition that Western wholesale markets have evolved over the past two decades to become sufficiently competitive to render the soft price cap unnecessary.  

...

Read More

Speaking Energy

February 23, 2026

The oil & gas industry is experiencing a fundamental transformation in how companies access and deploy capital in 2026. Despite strong balance sheets and robust free cash flow generation, the sector is witnessing strategic shifts in funding sources and investment priorities that signal a new era of capital allocation.

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.