Iowa Modifies its Renewable Energy Tax Credit Regime

Jul 31, 2015

Reading Time : 3 min

Three Favorable Changes

First, the Act increases the maximum cumulative value of solar energy system tax credits (Iowa Code Section 422.11L) that the Iowa Department of Revenue may issue annually to all applicants (who must apply for the credits with the Department of Revenue) from $4.5 million to $5 million.5This change applies retroactively to January 1, 2015 (for tax years beginning on or after that date).6 

Second, the Act expands the definition of “eligible renewable energy facility” with respect to renewable energy tax credits (Iowa Code Section 476C.1).7 Now included within the scope of such facilities is certain municipally owned city utilities and regulated public utilities.8 This revision is also retroactively effective as of January 1, 2015.9 Note that Iowa’s renewable energy tax credits can be calculated in one of four ways, each based on the amount of renewable energy purchased from an eligible renewable energy facility or used on-site by a producer:

  • as $0.015 per kilowatt-hour of electricity
  • as $4.50 per million British thermal units (Btus) of heat for a commercial purpose
  • as $4.50 per million Btus of methane gas or other biogas used to generate electricity or
  • as $1.40 per 1,000 standard cubic feet of hydrogen fuel.10

Third, the maximum allowable production capacity with respect to tax credits requested for “all other facilities” that Iowa’s review board might find eligible for the renewable energy tax credits has been increased.11 The increase takes the maximum from 53 megawatts of nameplate-generating capacity and 167 billion Btus of heat for commercial purposes to 63 megawatts of nameplate-generating capacity and, annually, 167 billion British units of heat for commercial purposes.12 This change applies retroactively to January 1, 2014, a year earlier than the effective dates for the first two changes mentioned above.


1 H.F. 645 (June 26, 2015).

2 “A taxpayer who is eligible to claim a credit under . . . section [422.11L] shall not be eligible to claim a renewable energy tax credit under chapter 476C.”  Iowa Code § 422.11L (2015).

3 H.F. 645 (June 26, 2015).

4 Iowa Code § 422.11L (2015).

5 H.F. 645 (June 26, 2015). 

6 Id.

7 Id. Note that Iowa includes the following sources of energies as within the scope of “renewable energy” for purposes of claiming this credit: biogas, biomass, methane gas, refuse, solar and wind. Iowa Code § 476C.1(6) (2015).   

8 H.F. 645 (June 26, 2015).

9 Id.

10 Iowa Code § 476C.2(1) (2015).

11 H.F. 645 (June 26, 2015).

12 Id.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.