Jordan Cove LNG Setback

Mar 17, 2016

Reading Time : 5 min

Jordan Cove was one of a number of West Coast LNG projects in line for development and considered a leading contender among the West Coast LNG projects. Jordan Cove, however, had yet to secure any firm commitments from LNG buyers, although it purportedly had nonbinding Heads of Agreements with various Asian companies for liquefaction and transportation capacity for about three times the volume of the Terminal’s capacity. At an expected project cost of $7.5 billion, Jordan Cove and Pacific Connector had designed the Terminal and the Pipeline to enable the production of up to 6.8 million metric tons per annum of LNG (using a feed of approximately 1.04 Bcf/d of natural gas) for export.

Pacific Connector

Pacific Connector stated in its FERC application that it would not build the Pipeline if the Terminal was not contracted by LNG buyers. Consistent with that position, Pacific Connector did not submit any precedent agreements or contracts with (or subsequent to) its application, and it has yet to hold an open season. Rather, Pacific Connector stated that it would “keep [FERC] apprised of its plans to conduct an open season and enter into precedent agreements for the [P]ipeline’s capacity”2 and that negotiations between Jordan Cove, Pacific Connector and prospective customers were “active and ongoing.”3  FERC staff sent Pacific Connector a series of data requests between May 2014 and October 2015 asking it to provide updates on its proposed plans and negotiations. In one of its data requests, FERC staff explained that FERC’s Certificate Policy Statement4 would require Pacific Connector to show that the public benefits of the Pipeline would outweigh its adverse impacts. In response, Pacific Connector argued that, because the Pipeline was an “integral component” of the Terminal, and the U.S. Department of Energy (DOE) had already authorized the Terminal’s export of LNG to free trade agreement (FTA) nations and non-FTA nations as consistent with the public interest, the Pipeline’s public benefits must encompass all the public benefits of the Terminal.5  In response to another data request, Pacific Connector indicated that it had obtained easements for “5 percent and 3 percent, respectively, of its necessary permanent and construction right of way.”6

In the Order, FERC explained that its Certificate Policy Statement provided guidance for evaluating proposals to certificate new construction, and that, under its policy, applicants must satisfy a multipronged test that balances the public benefits against the potential adverse consequences. FERC found that the Pipeline failed to satisfy this test.

FERC found that, since Pacific Connector was a new natural gas company with no existing customers, there was no issue of subsidization, nor would the Pipeline adversely impact existing pipelines in the market or their captive customers. FERC also acknowledged that Pacific Connector had made efforts to minimize the adverse effect on landowners and communities by proposing to locate 41 percent of the Pipeline adjacent to existing power lines, roads and other pipelines. However, the remaining 59 percent of the route would be constructed within newly created rights of way through forests, farms and rangeland. It was this portion of the proposed Pipeline route that troubled FERC, with FERC finding that such route would (i) affect approximately 630 landowners; (ii) have negative economic impacts on these landowners; and (iii) require, at least in part, the exercise of eminent domain.7  In addition, FERC found that Pacific Connector had presented “little or no evidence of need for the . . . Pipeline” and it had “neither entered into any precedent agreements for its project, nor conducted an open season, which might (or might not) have resulted in ‘expressions of interest’ the company could have claimed as indicia of demand.”8

The Order noted that Pacific Connector had argued that (i) the Pipeline would “benefit the public by delivering gas supply from the Rocky Mountains and Canada to the . . . Terminal and by providing an additional source of gas supply to communities in southern Oregon”; (ii) construction of the Pipeline and Terminal would create temporary and full-time jobs and provide millions of dollars in taxes to state and local governments; and (iii) FERC had previously found that “the benefits provided by pipelines that deliver feed gas to export terminals outweigh the minimal adverse impacts and such projects are required by the public convenience and necessity.”9  FERC rejected these arguments and explained that it had not previously found “a proposed pipeline to be required by the public convenience and necessity under NGA Section 7 on the basis of a DOE finding under NGA Section 3 that the importation or exportation of the commodity natural gas by an entity proposing to use the services of an associated LNG facility is consistent with the public interest.”10  FERC explained also that it had not “relied solely on the fact that a company is not likely to proceed with construction of facilities in the absence of a market for a project’s services — particularly in the face of significant opposition from directly impacted landowners.”11  Because FERC found that the record did not support a finding that the public benefits of the Pipeline would outweigh the adverse effects on landowners, FERC denied the Pipeline’s request for certificate authorization.

Terminal

After denying Pacific Connector’s request for certificate authority to construct and operate the Pipeline, FERC found that, “without a pipeline connecting it to a source of gas to be liquefied and exported, the proposed . . . Terminal can provide no benefit to the public to counterbalance any of the impacts which would be associated with its construction.”12  Accordingly, it similarly denied Jordan Cove’s request for authorization to site, construct and operate the Terminal.13

Impact of the Order

Whether this Order will impact continued funding for other LNG projects under development and in line for FERC approval remains to be seen. But one thing is now clear: DOE export authorization, by itself, is insufficient to support construction and operation of a U.S. LNG terminal and associated pipelines. LNG terminal developers and the proposed feeder pipelines critical to the viability of those projects would be well-advised to coordinate and expedite their marketing efforts in order to avoid Jordan Cove’s fate and be prepared, in a world where more than 100 MTPA of LNG liquefaction capacity is expected to enter the market in the next five years, to present FERC with persuasive evidence of market demand for their capacity.


1 See Jordan Cove Energy Project, L.P., 154 FERC ¶ 61,190 (2016).

2 See id. at 13-14.

3 See id. at 18.

4 Certification of New Interstate Natural Gas Pipeline Facilities, 88 FERC ¶ 61,227 (1999), order on clarification, 90 FERC ¶ 61,128, order on clarification, 92 FERC ¶ 61,094 (2000) (“Certificate Policy Statement”).

5 Order at 17.

6 Id. at 18.

7 Id. at 38.

8 Id. at 39.

9 Id.

10 Id. at 40.

11 Id.

12 Id. at P 44.

13 Id. at P 46.

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.