Mexico's Energy Industry: Midstream Regulations

Aug 3, 2015

Reading Time : 5 min

These Midstream Regulations’ main goals are (i) to provide open, nondiscriminatory access to existing transportation and storage infrastructure and (ii) to establish a legal framework that will promote the development of the midstream market. They will apply equally to all new or existing pipeline and storage operators, regardless whether they are State-Owned or private companies, foreign or Mexican. Overall, the Regulations provide the CRE vast authority to regulate the Mexican midstream sector to complete the transition from a state-owned and operated monopoly to a competitive and vibrant market-driven industry. Moreover, Petroleos Mexicanos is required to carry out a complete inventory of all its midstream assets and present market-driven Terms and Conditions for all its Transportation Systems and Storage Facilities within 90-days from the final publication of the Midstream Regulations.

The following summary presents some of the more relevant aspects of the Midstream Regulations including a clear distinction between transportation and storage, different midstream service modalities, cap on Carriers’ Reserved Capacity, open seasons, interconnectivity, expansion/extension, quality banks, guidelines for Carriers to prepare their Terms and Conditions, and their Rates/Tariffs schemes.

Services

Transportation
Scope: Includes (i) reception of petroleum and petrochemicals (P&P) at a designated entry point; (ii) their shipment through the pipelines; (iii) measurement and analysis of the quantity and quality of P&P; and (iv) delivery at a designated exit point.

 

Components: Transportation Systems may include “buffer facilities” like temporary storage or processing tanks as long as these buffer facilities are directly and exclusively necessary for the transportation of P&P. Buffer facilities cannot be used only for storage purposes and their capacity must reflect the “temporary” requirement.

Carriers:

  • Must obtain a Transportation Permit from the CRE. The Permit shall include the Terms and Conditions (“TCPS”) for the Transportation System (similar to the Rules Tariff in the U.S.).
  • Must limit their “corporate purpose” to the transportation of hydrocarbons.
  • Must provide (i) Firm Commitment Services and (ii) Open Access Services.
  • May only transport a limited quantity of their own P&P thorough their Transportation System.
  • Must certify the Transportation System’s Capacity, Firm Commitment Capacity, Available Capacity and Open Access Capacity (if any).

Storage:
Scope: Includes (i) reception of P&P at a designated point for storage or depository purposes; (ii) measurement and analysis of the quantity and quality of P&P; (iii) any processing and mixing necessary to meet necessary quality standards; and (iv) delivery at a designated point.

Storage Providers:

  • Must obtain a Storage Permit from the CRE. The Permit shall include TCPS for the Storage Facilities (similar to the Rules Tariff in the U.S.).
  • Must limit their “corporate purpose” to the storage of hydrocarbons.
  • Must provide (i) Firm Commitment Services and (ii) Open Access Services.
  • May only store a limited quantity of their own P&P in their Storage Facilities.
  • Must certify the Storage Facility’s Capacity, Firm Commitment Capacity, Available Capacity and Open Access Capacity (if any).

Service Formats

Firm Commitment
As a general rule, transportation and storage services of P&P will be offered under a Firm Commitment scheme, whereby Shippers enter into medium to long term fixed volume and frequency agreements with Carriers and Storage Providers (Midstream Companies). The Firm Commitment scheme has priority over the Open Access or Common Use schemes because it allows Shipper to guaranty capacity and access to the Transportation System and Storage Facilities.

 

Open Access
Midstream Companies must include in their TCPS the necessary conditions to guaranty open access to all the services they provide. Shippers interested in hiring P&P transportation and storage services must send an application to the corresponding Mistream Company, who must provide a formal response within 30 days. Midstream Companies may only deny requested services when there is no Available Capacity or it is determined that the service request is not technically feasible. If the Shipper believes Midstream Companies are not providing open, non-discriminatory access to their Systems/Facilities, they may file a complaint with the CRE.

 

Common Use
Midstream Companies may offer P&P transportation and storage services based on the Common Use scheme together with the Firm Commitment and Open Access schemes. Midstream Companies may allot a percentage of their Available Capacity to provide services on a pro-rata basis which must include the following considerations: (i) Shipper’s historic volume profile; (ii) regularity or frequency of services provided to Shipper; (iii) Shipper’s nomination requirements; and (iv) minimum work commitments, among others. Midstream Companies may offer Unconfirmed Capacity under the Firm Commitment scheme to Common Use Shippers.

Main Characteristics

Rates/Tariffs
The CRE will determine, based on the existing market conditions for a particular Transportation System or Storage Facility, whether it will establish a maximum rate/tariff. If market conditions indicate there will be a competitive environment, no maximum rates/tariffs will be established. Otherwise, the CRE will impose maximum rate/tariff schemes to protect Shippers and mitigate any anticompetitive practices. The CRE will evaluate the Midstream Companies’ rates/tariffs based on the following: operating, sunk and recoverable costs; likely Shippers’ characteristics; current market conditions; operating efficiency; reasonable risk allocation between Shippers and Midstream Companies; and adequate profitability, among others.

Batching
Midstream Companies may offer Batching services based on P&P’s quality and specifications. Any additional requirements, quality ranges and costs involved in Batching must be included in the Permit Terms and Conditions.

Open Season
Midstream Companies must hold Open Seasons every time they have Permanent Available Capacity, get a new Transportation/Storage Permit, decide to build new or expand existing pipelines and storage facilities, or are asked by Shippers to build or expand existing pipelines and storage facilities. Open Seasons will help identify interested parties, scope of services required and the characteristics of the TCPS.

Quality Banks
Midstream Companies may establish quality banks to identify and compensate for any discrepancies in the quality of the P&P introduced vs. received. Any quality bank provisions must be included in the TCPS.

Interconnection
Carriers must facilitate Shipper’s interconnection to their Transportation System by providing technical support and paying for such interconnection. All interconnection-related costs can be incorporated into the transportation rates. Interconnection is limited to a maximum distance of 100 meters from the existing Transportation System; otherwise it would be considered an expansion/extension.

Expansion and Extension
Midstream Companies may enter into investment/development agreements with Shippers to expand or extend existing Systems/Facilities to cover Shippers’ needs. Midstream Companies should establish terms and conditions under which they will agree to such agreements. Otherwise, Shippers may undertake the expansion or extension, apply independently for a Permit and request interconnection with the existing Transportation System.

Electronic Bulletin
Midstream Companies must create Electronic Bulletins for all Systems/Facilities. They will have to post the following information: System/Facility Capacity, Firm Commitment Capacity, Available Capacity, Open Access Capacity, TCPS, Open Seasons, existing Transportation and Storage Agreements, among other relevant matters.

Capacity Assignment/Transfer
Shippers may assign or transfer the Firm Commitment capacity they have acquired. If any Firm Commitment capacity goes unused for a long period of time, Shipper will be forced to forgo or sell it.

Title
Shippers must certify to the Midstream Companies that the P&P they are putting in the System/Facility is free of liens or encumbrances, and that they are the rightful owners. The P&P may not be sold, assigned or transferred while in transit.

Share This Insight

Previous Entries

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.