NERC Proposes New Physical Reliability Standard

May 29, 2014

Reading Time : 5 min

Proposed Reliability Standard CIP-014-1 – Physical Security

Proposed Reliability Standard CIP-014-1 would require transmission owners and operators to protect critical transmission stations and substations and their associated primary control centers that if rendered inoperable or damaged as a result of a physical attack could result in widespread instability, uncontrolled separation, or cascading within an interconnection.  Specifically:

  • Requirement R1 requires applicable transmission owners1 to perform risk assessments on a periodic basis to identify their transmission stations and substations that if rendered inoperable or damaged could result in widespread instability, uncontrolled separation, or cascading within an interconnection.  The transmission owner must then identify  the  primary  control  center  that  operationally  controls  each  of the  identified transmission stations or substations.  Subsequent risk assessments must be performed:
    • At least once every 30  calendar months for a transmission owner that has identified in its previous risk assessment one or more transmission stations or substations that if rendered inoperable or damaged could result in widespread instability, uncontrolled separation, or cascading within an interconnection; or
    • At least once every 60 calendar months for a transmission owner that has not identified in its previous risk assessment any transmission stations or substations that if rendered inoperable or damaged could result in widespread instability, uncontrolled separation, or cascading within an interconnection.
  • Requirement  R2  provides  that  each  applicable  transmission  owner  shall  have  an unaffiliated third party with appropriate experience verify the risk assessment performed under Requirement R1.  The transmission owner must either modify its identification of facilities consistent with the verifier’s recommendation or document the technical basis for not doing so.
  • Requirement R3 requires the transmission owner to notify a transmission operator that operationally controls a primary control center identified under Requirement R1 of such identification. This requirement helps ensure that such a transmission operator has notice of the identification so that it may timely fulfill its resulting obligations  under Requirements R4 and R5 to protect that primary control center.
  • Requirement R4 requires each applicable transmission owner and transmission operator to conduct an evaluation of the potential threats and vulnerabilities of a physical attack to each of its respective transmission station(s), substation(s), and primary control center(s) identified in Requirement R1, as verified under Requirement R2.  The evaluation shall consider the following:
    • Unique characteristics of the transmission station(s), substation(s), and primary control center(s);
    • Prior history of attack on similar facilities taking into account the frequency, geographic proximity, and severity of past physical security related events; and
    • Intelligence or threat warnings received from sources such as law enforcement, the Electric Reliability Organization, the Electricity Sector Information Sharing and Analysis Center, U.S. federal and/or Canadian governmental agencies, or their successors.
  • Requirement R5 requires each transmission owner and transmission operator to develop and implement a documented physical security plan that covers each of its respective transmission stations, substations, and primary control centers identified in Requirement R1, as verified under Requirement R2.  The physical security plan(s) shall include the following attributes:
    • Resiliency or security measures designed collectively to deter, detect, delay, assess, communicate, and respond to potential physical threats and vulnerabilities identified during the evaluation conducted in Requirement R4.  These measures could include, for example: (i) modifications to system topology, (ii) the construction of a new transmission station or substation that would lessen the criticality of the facility, (iii) providing for access to spare or replacement equipment.
    • Law enforcement contact and coordination information.
    • A timeline for executing the physical security enhancements and modifications specified in the physical security plan.
    • Provisions to evaluate evolving physical threats, and their corresponding security measures, to the transmission station(s), substation(s), or primary control center(s).  An entity's physical security plan should include processes and responsibilities for obtaining and handling alerts, intelligence, and threat warnings from various sources
  • Requirement  R6  provides  that  each  transmission  owner  and  transmission  operator subject to Requirements R4 and R5 have an unaffiliated third party with  appropriate experience review its Requirement R4 evaluation and Requirement R5 security plan. The transmission owner and transmission operator must either modify its evaluation and security plan consistent with the recommendation of the reviewer or document its reasons for not doing so.

The proposed new standard also creates an affirmative obligation on each transmission owner and transmission operator to implement procedures for protecting sensitive or confidential information made available to the unaffiliated third party reviewer and to protect sensitive or confidential information from public disclosure.  Procedures for protecting confidential information may include, among other things: (1) the control and retention of information at the applicable entity’s facility for third party verifiers/reviewers; (2) restricting information to only those employees that need to know such information for purposes of carrying out their job functions; (3) marking all relevant documents as confidential; (4) securely storing and destroying information, both physical and electronically; and (5) requiring senior manager sign-off prior to releasing any sensitive or confidential information to an outside entity.

Proposed Implementation Plan

The proposed implementation plan would require transmission owners to complete their initial risk assessments on or before the effective date of the proposed new standard.  NERC has requested that FERC approve the proposed new standard to become effective on the first day of the first calendar quarter that is six months after Commission approval.

Potential Implications

If approved by FERC, the proposed new standard would hold transmission owners and operators potentially accountable if physical security measures later viewed as inadequate were to contribute to widespread instability, uncontrolled separation, or cascading within an interconnection.  Transmission owners and operators will want to carefully document compliance with the standard and prudent evaluation of the full range of options available to reduce physical threats, including the construction of new assets that would lessen the criticality of any one facility.  Entities with stated transmission rates (rather than formula rates) also may want to consider regulatory strategies to ensure full recovery of prudent costs incurred to comply with the new standard, including the costs of third party verifiers.


1 The proposed standard applies only to those transmission owners that own a transmission station or substation that meets the description of “Medium Impact” Transmission Facilities listed in Attachment 1 of Reliability Standard CIP-002-5.1.  NERC expects that a number of transmission owners required to perform risk assessments under Requirement R1 will not identify any transmission stations or substations that, if damaged or rendered inoperable as a result of physical attack, pose a risk of widespread instability, uncontrolled separation, or cascading within an interconnection. Nevertheless, NERC and the standard drafting team concluded that using the “Medium Impact” criteria was a prudent approach to balancing the need for a reliability standard that is broad enough to capture all critical transmission stations and substations while narrowing the scope of the reliability standard so as not to unnecessarily include entities that do not own or operate such critical facilities.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.