NERC Proposes New Physical Reliability Standard

May 29, 2014

Reading Time : 5 min

Proposed Reliability Standard CIP-014-1 – Physical Security

Proposed Reliability Standard CIP-014-1 would require transmission owners and operators to protect critical transmission stations and substations and their associated primary control centers that if rendered inoperable or damaged as a result of a physical attack could result in widespread instability, uncontrolled separation, or cascading within an interconnection.  Specifically:

  • Requirement R1 requires applicable transmission owners1 to perform risk assessments on a periodic basis to identify their transmission stations and substations that if rendered inoperable or damaged could result in widespread instability, uncontrolled separation, or cascading within an interconnection.  The transmission owner must then identify  the  primary  control  center  that  operationally  controls  each  of the  identified transmission stations or substations.  Subsequent risk assessments must be performed:
    • At least once every 30  calendar months for a transmission owner that has identified in its previous risk assessment one or more transmission stations or substations that if rendered inoperable or damaged could result in widespread instability, uncontrolled separation, or cascading within an interconnection; or
    • At least once every 60 calendar months for a transmission owner that has not identified in its previous risk assessment any transmission stations or substations that if rendered inoperable or damaged could result in widespread instability, uncontrolled separation, or cascading within an interconnection.
  • Requirement  R2  provides  that  each  applicable  transmission  owner  shall  have  an unaffiliated third party with appropriate experience verify the risk assessment performed under Requirement R1.  The transmission owner must either modify its identification of facilities consistent with the verifier’s recommendation or document the technical basis for not doing so.
  • Requirement R3 requires the transmission owner to notify a transmission operator that operationally controls a primary control center identified under Requirement R1 of such identification. This requirement helps ensure that such a transmission operator has notice of the identification so that it may timely fulfill its resulting obligations  under Requirements R4 and R5 to protect that primary control center.
  • Requirement R4 requires each applicable transmission owner and transmission operator to conduct an evaluation of the potential threats and vulnerabilities of a physical attack to each of its respective transmission station(s), substation(s), and primary control center(s) identified in Requirement R1, as verified under Requirement R2.  The evaluation shall consider the following:
    • Unique characteristics of the transmission station(s), substation(s), and primary control center(s);
    • Prior history of attack on similar facilities taking into account the frequency, geographic proximity, and severity of past physical security related events; and
    • Intelligence or threat warnings received from sources such as law enforcement, the Electric Reliability Organization, the Electricity Sector Information Sharing and Analysis Center, U.S. federal and/or Canadian governmental agencies, or their successors.
  • Requirement R5 requires each transmission owner and transmission operator to develop and implement a documented physical security plan that covers each of its respective transmission stations, substations, and primary control centers identified in Requirement R1, as verified under Requirement R2.  The physical security plan(s) shall include the following attributes:
    • Resiliency or security measures designed collectively to deter, detect, delay, assess, communicate, and respond to potential physical threats and vulnerabilities identified during the evaluation conducted in Requirement R4.  These measures could include, for example: (i) modifications to system topology, (ii) the construction of a new transmission station or substation that would lessen the criticality of the facility, (iii) providing for access to spare or replacement equipment.
    • Law enforcement contact and coordination information.
    • A timeline for executing the physical security enhancements and modifications specified in the physical security plan.
    • Provisions to evaluate evolving physical threats, and their corresponding security measures, to the transmission station(s), substation(s), or primary control center(s).  An entity's physical security plan should include processes and responsibilities for obtaining and handling alerts, intelligence, and threat warnings from various sources
  • Requirement  R6  provides  that  each  transmission  owner  and  transmission  operator subject to Requirements R4 and R5 have an unaffiliated third party with  appropriate experience review its Requirement R4 evaluation and Requirement R5 security plan. The transmission owner and transmission operator must either modify its evaluation and security plan consistent with the recommendation of the reviewer or document its reasons for not doing so.

The proposed new standard also creates an affirmative obligation on each transmission owner and transmission operator to implement procedures for protecting sensitive or confidential information made available to the unaffiliated third party reviewer and to protect sensitive or confidential information from public disclosure.  Procedures for protecting confidential information may include, among other things: (1) the control and retention of information at the applicable entity’s facility for third party verifiers/reviewers; (2) restricting information to only those employees that need to know such information for purposes of carrying out their job functions; (3) marking all relevant documents as confidential; (4) securely storing and destroying information, both physical and electronically; and (5) requiring senior manager sign-off prior to releasing any sensitive or confidential information to an outside entity.

Proposed Implementation Plan

The proposed implementation plan would require transmission owners to complete their initial risk assessments on or before the effective date of the proposed new standard.  NERC has requested that FERC approve the proposed new standard to become effective on the first day of the first calendar quarter that is six months after Commission approval.

Potential Implications

If approved by FERC, the proposed new standard would hold transmission owners and operators potentially accountable if physical security measures later viewed as inadequate were to contribute to widespread instability, uncontrolled separation, or cascading within an interconnection.  Transmission owners and operators will want to carefully document compliance with the standard and prudent evaluation of the full range of options available to reduce physical threats, including the construction of new assets that would lessen the criticality of any one facility.  Entities with stated transmission rates (rather than formula rates) also may want to consider regulatory strategies to ensure full recovery of prudent costs incurred to comply with the new standard, including the costs of third party verifiers.


1 The proposed standard applies only to those transmission owners that own a transmission station or substation that meets the description of “Medium Impact” Transmission Facilities listed in Attachment 1 of Reliability Standard CIP-002-5.1.  NERC expects that a number of transmission owners required to perform risk assessments under Requirement R1 will not identify any transmission stations or substations that, if damaged or rendered inoperable as a result of physical attack, pose a risk of widespread instability, uncontrolled separation, or cascading within an interconnection. Nevertheless, NERC and the standard drafting team concluded that using the “Medium Impact” criteria was a prudent approach to balancing the need for a reliability standard that is broad enough to capture all critical transmission stations and substations while narrowing the scope of the reliability standard so as not to unnecessarily include entities that do not own or operate such critical facilities.

Share This Insight

Previous Entries

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.