In a recent case, the High Court in London addressed this question and confirmed the prevailing academic view: namely, that a petroleum license is a contract R (Benjamin Dean) v the Secretary of State for Business, Energy and Industrial Strategy [2017] EWCH 1998 (Admin) (Holgate J).

Facts

A petroleum license had been granted for the exploration for and production of coalbed methane. Subsequently, it was realized that greater potential laid in the exploitation of shale gas. The claimant sought to use arguments relating to the legal characteristics of a petroleum license in order to prevent fracking.

The claimant argued that by entering into a deed of variation to alter the length of the Initial Term, the Secretary of State had acted ultra vires. It was submitted that the 1998 Act is a complete statutory code governing licenses and contains no powers to vary an executed license. In response, the Secretary of State submitted that the license was contractual in nature and, therefore, capable of being varied by further agreement between the parties.

Decision

The Court emphasized that it was not concerned with the merits of the fracking proposal, but that its focus was solely with the legal issues. It held:

  • Petroleum licenses need the English law requirements of a contract: namely, an offer (by the Secretary of State as grantor), an acceptance (by the licensee), good consideration and the intention to create legal relations. The license therefore is a contract, and capable of being varied. Variation must be by mutual agreement.
  • Petroleum licenses lack certain traditional public law features. For example, there is no right of appeal regarding their terms. Compare this to a planning license: once granted, the only recourse if the licensee is dissatisfied is an administrative or court appeal. Planning license amendments do not need to be by agreement, but can be made unilaterally.
  • A petroleum license gives the licensee a right to own production, and then sell it to third parties. These are private law rights and, accordingly, should be governed by private law.

The judge determined these rights to be a property transaction (similar to a mining license). The use of a deed (rather than a simple contract) reflects the formalities needed when creating an interest in land.

Going Forward

The conclusions of the court should be a comfort to licensees for two reasons. A mechanism exists to vary Work Programmes and/or the duration of the Initial or Second Terms of a petroleum license. Furthermore, third parties cannot use public or administrative law arguments to disrupt or challenge the license and petroleum operations.

Share This Insight

Previous Entries

Speaking Energy

December 21, 2025

On December 19, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued its much-anticipated order on show cause proceeding concerning the co-location of generation and load within the PJM Interconnection, L.L.C. (PJM) market.[1] In the order, the Commission finds that PJM’s tariff is unjust and unreasonable because it does not provide sufficient clarity on the rates, terms, and conditions of service applicable to generators serving Co-Located Load and does not include transmission services appropriate for customers that are willing and able to limit their use of the transmission system in certain conditions. 

...

Read More

Speaking Energy

November 25, 2025

We are pleased to share the program materials and a recording of Akin’s recently presented webinar, “Navigating the Evolving Landscape of Corporate PPAs.”

...

Read More

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.