The Rise in Arbitration Claims Filed by Renewable Energy Investors Under the Energy Charter Treaty

Nov 3, 2015

Reading Time : 2 min

Arbitrating Under the ECT

The ECT allows for disputes to be settled in one of three ways: (a) in the “Courts or administrative tribunals of the Contracting Party”; (b) “in accordance with any applicable previously agreed dispute settlement procedure”; or (c) through International Arbitration. Article 26(3)(a) of the treaty provides any disputes under the treaty to be resolved by arbitration given the signatory state’s “unconditional consent to the submission of a dispute to international arbitration.” Investors have the choice under Article 26(4) to submit the dispute to International Centre for Settlement of Investment Disputes (ICSID) arbitration (provided that both parties are signatories to the Washington Convention); to ICSID Additional Facility arbitration (if one party is a signatory to the Washington Convention, but the other party is not); to ad hoc UNCITRAL arbitration; or to arbitration administered by the Stockholm Chamber of Commerce. The vast majority of the cases have been submitted to ICSID arbitration.

Causes of Action

Though most of the information surrounding the current disputes being filed by renewable energy investors is confidential and therefore not publicly available, the Energy Charter Secretariat lists the subject matter of the disputes as “legal reforms affecting the renewable energy sector.” In particular, most of the disputes are thought to be based upon the erosion of “feed-in tariffs,” related to renewable energy and a large amount of investments in solar technology.

Feed-in tariffs provide a premium price to renewable energy producers for the production of their green energy. Feed-in tariffs typically have three elements in common: guaranteed (premium) sales prices, guaranteed grid access and long-term contracts. Moreover, depending on the regime, utility grid companies may be under an obligation to purchase all of the electricity produced by the renewable energy company, thereby ensuring the energy investors a return on their investment into the country and the technology.

Spain and Italy have both publicly decided to reduce the amount of the feed-in tariffs for renewable energy in attempts to lower individual utility bills and minimize other governmental expenditures associated with renewable energy. These decisions, however, have exposed the host states to a significant number of ECT claims seeking damages for the change in regulatory regime from the one that induced investment. Spain, with a previously booming solar energy industry, has also borne the brunt of investor claims seeking compensation for their losses.

The sheer number of claims recently filed under the ECT surrounding the changes to the regulatory environment have brought renewed attention to the ECT. Many will also recall that the ECT is also the instrument under which the largest international arbitration award was issued in July 2014. (Hulley Enterprises Ltd., Yukos Universal Ltd. and Veteran Petroleum Ltd. v. Russian Federation) The adverse award against Russia amounted to approximately US$50 billion to be paid by Russia to the shareholders of “Yukos” and is currently in the midst of annulment proceedings in the Netherlands.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.