In 2011, a coalition of generators filed a complaint with the Commission arguing that the then-existing MOPR was inadequate. Shortly thereafter, PJM filed a related proposal to revise certain aspects of the MOPR. Both the complaint and PJM’s tariff proposal were motivated in large part, if not entirely, by state-sponsored proposals to subsidize new generation units in New Jersey and Maryland. The coalition of generators, PJM, and others argued to the Commission that the New Jersey and Maryland initiatives would destroy the ability of RPM to produce competitive prices for capacity. In a series of orders, the Commission ultimately made several changes to the MOPR, including eliminating a then-existing exemption from the MOPR for state-mandated resources. The Commission also clarified that resources designated as new “self-supply,” i.e. new resources offered into the market by a load serving entity to serve its own load, would be subject to the MOPR. Both the New Jersey and Maryland state initiatives were recently invalidated by federal district courts for violating the Supremacy Clause because they sought to regulate wholesale prices for energy in interstate commerce, a field that is occupied exclusively by the Commission. 

Maryland and New Jersey challenged several of the Commission’s findings before the Third Circuit. They argued, among other things, that the Commission exceeded its statutory authority under the Federal Power Act when it eliminated the exemption for state-mandated resources and that the Commission’s decision to eliminate this exemption was arbitrary and capricious.  Various entities also challenged the Commission’s decision to apply the MOPR to new self-supply resources. Petitioners, including the coalition of generators, made several other challenges to the Commission’s orders as well. 

The Third Circuit denied all petitions challenging the 2011 Commission orders. On the issue of whether the Commission exceeded its jurisdiction in eliminating the exemption for state-mandated resources, the court held that the Commission’s rationale for eliminating the state-mandated exemption related directly to its duty of ensuring just and reasonable wholesale rates—which is exclusively the jurisdiction of the Commission. In response to state arguments that the Commission interfered with state efforts to sponsor new capacity, the court held that “[W]hat FERC has actually done here is permit states to develop whatever capacity resources they wish, and to use those resources to any extent that they wish, while approving rules that prevent the state’s choices from adversely affecting wholesale capacity rates.”   

While expressing some concern about the manner in which the Commission required PJM to subject new self-supply to the MOPR, the Third Circuit dismissed challenges on this matter as moot. In a subsequent MOPR proceeding, the Commission accepted further revisions to the MOPR that now allowed for an exemption for new self-supply so long as the resources fit within certain established “net-short” and “net-long” thresholds. 1

Despite denying all petitions challenging the 2011 Commission orders, the Third Circuit was highly critical of the Commission for failing to consider the economic harm that could result from the state-mandated exemption when it first approved the MOPR in 2006. The Third Circuit stated:

It is more than mildly disturbing that, by endorsing a state-mandated exemption with perfectly predictable incentives, FERC would allow sovereign states and private parties to be drawn into making complex and costly investments, only to later pull the rug out from under those were persuaded that the exemption was somehow real.  That FERC has done so based on little more than an “ah ha” moment when foreseeable outcomes approached fruition only makes matters worse.  Our power to rein in bureaucratic behavior like this is, however, constrained. 

As mentioned above, the PJM MOPR has gone through further, substantial changes since the 2011 order, and these changes have rendered some of the challenges to the 2011 orders moot.  Nevertheless, the Third Circuit’s decision establishes important precedent on various issues, including the often difficult jurisdictional balance between state authority over local generation and resource adequacy and the Commission’s statutory duty to ensure just and reasonable rates in the wholesale markets.  

Please click here to review the Third Circuit decision.



1 PJM Interconnection, L.L.C., 143 FERC ¶ 61,090 (2013).

Share This Insight

Previous Entries

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.