Lack of Quorum Costs East Kentucky Power Cooperative in PURPA Dispute

Sep 15, 2017

Reading Time : 3 min

By: Shawn Whites (paralegal)

The Public Utility Regulatory Policies Act of 1978 (PURPA), a 1970s law that sought to foster the development of independent power producers and renewable generation, requires electric utilities to buy power at “avoided cost” from QFs.1 Pursuant to FERC’s Order No. 688, however, utilities may seek authorization from FERC to terminate this purchase requirement prospectively for QFs that have nondiscriminatory access to a wholesale electricity and capacity market. Importantly, any such termination does not apply to “legally enforceable obligations” between a QF and the utility that exist prior to the filing of the utility’s application seeking termination of the purchase requirement.

On November 4, 2016, EKPC submitted its initial application seeking to terminate the purchase requirement in its service territory for QFs of more than 20 MW.  PURPA and FERC’s regulations require the Commission to make a final determination within 90 days of the application’s filing date. Due to the lack of quorum at the Commission, however, the Commission was unable to act on the filing within 90 days.  FERC issued a notice in March 2017 noting as much and deemed the application denied. EKPC resubmitted the application in March, but FERC, still lacking a quorum, deemed the application denied once again in June when the 90-day period expired. EKPC filed a third and final application in June 2017, which FERC approved in the September 2017 Order.

While FERC grantedEKPC’s June 2017 application, it held that termination of the purchase requirement was effective June 9, 2017—the date of the third and final application—and not the date ofEKPC’s initial application, November 4, 2016, asEKPC requested. Bluebird Solar LLC and Blue Jay Solar LLC, two QFs inEKPC’s territory, informedEKPC of their intention to sell their output toEKPC pursuant to PURPA prior to June 9. FERC therefore concluded thatEKPC’s application “does not foreclose Bluebird or Blue Jay from having established a legally enforceable obligation under PURPA.”1  Barring any state law restrictions, FERC concluded that Bluebird and Blue Jay “would be grandfathered such that Commission approval of [the] Application would not include Bluebird or Blue Jay QFs.”2  Had the Commission approved the original (and nearly identical) EKPC application from November 2016, the two QFs would not have received grandfathered status because the original application preceded the QFs’ legally enforceable obligations.

The 90-day requirement in the PURPA statute states that FERC “shall make a determination” on any such application within 90 days, but it does not state—in contrast to certain provisions in the Federal Power Act—that inaction within that period automatically results in denial (or approval).  EKPC sought rehearing of FERC’s notice deeming the application denied, but the Commission dismissed the request because, according to FERC, the notice does not constitute a final Commission order subject to rehearing. 

In other PURPA news, FERC issued an order granting QF certification last week to the Beaver Creek Wind II, LLC and Beaver Creek Wind III, LLC facilities located in Stillwater County, Montana. The utility required to purchase the output of the QFs, NorthWestern Corp., had protested the application, arguing that the facilities are each within one mile of other affiliated Beaver Creek Wind projects and that, based on the Commission’s “one-mile rule,” the facilities exceed the 80 MW limit for QF status.4 While this proceeding appeared to provide FERC with an opportunity to clarify its methodology for applying the one-mile rule, FERC ultimately declined to provide clarification because it found that Beaver Creek II and Beaver Creek III are neither affiliates of each other nor the other Beaver Creek projects located in close proximity.

 


1 QFs are small, renewable generation facilities and cogeneration facilities.

2 September 2017 Order at P 21.

3 Id.

4 To determine whether two or more facilities are located at the same site, FERC’s regulations specify that a facility located within one mile of the facility for which QF status is sought—as measured by the distance between the electric generating equipment of the facilities—is deemed to be located at the same site.  18 C.F.R. § 292.204(a)(2).  Thus, two 80 MW facilities owned by affiliates would not qualify as separate QFs if they are located within one mile of each other.

Share This Insight

Previous Entries

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.