Electric Utility Securitizations—Plant Closings

Feb 19, 2016

Reading Time : 2 min

The following represent two recent utility securitizations related to plant closings:

  • Consumers Energy Company (Michigan) Coal-Fired and Gas-Fueled Units (2014)—This Michigan utility was authorized to recover through a utility securitization the remaining or unrecovered book value (determined to be a regulatory asset and qualified cost for purposes of the Michigan utility securitization statute) of seven coal-fired and three gas-fueled electric generating units designated for early retirement due to changes in environmental regulations. The financing order approved the issuance of approximately $390 million of bonds.
  • Duke Energy Florida (Florida) Nuclear Plant (securitization expected to close in 2016)—This Florida utility was authorized to recover through a utility securitization costs related to the premature closing of the Crystal River nuclear plant. In light of damage to the nuclear plant in 2009, and the considerable costs that would be required to repair the plant, the plant was permanently shut down in 2013. The financing order approved the issuance of approximately $1,313 million of bonds.

An important requirement of utility securitizations that the applicant demonstrate that the securitization has a significant likelihood of resulting in lower overall costs or would avoid, or significantly mitigate, rate impacts compared to the traditional method of cost recovery. The Michigan Public Service Commission financing order found that the net present value of the revenues to be collected under the financing order would be less than the amount that would be recovered over the remaining life of the qualified costs using conventional financing methods (with Consumers Energy’s assertion of an approximate $135 million difference reduced by $35 million pursuant to the financing order). The Florida Public Service Commission financing order found that the traditional method of recovering the costs (i.e., implementation of a base rate increase) would result in a total revenue requirement over the 20-year recovery period of approximately $2,531 million, while, with the issuance of bonds, the estimated cumulative revenue requirement over the total period outstanding would be $1,823 million, which is $708 million lower than the estimated cumulative revenue requirement under the traditional recovery method. Two additional important factors support these findings: utility securitizations provide for the spreading of costs over the term of the bonds and, due to the AAA rating of the bonds issued in these securitizations, a significant reduction to a utility’s cost of capital.

Share This Insight

Categories

Previous Entries

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Midcontinent Independent System Operator, Inc. (MISO) directing MISO and MISO transmission owners to show cause as to why MISO’s tariff should not be found to be unjust and unreasonable (Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to PJM Interconnection, L.L.C. directing PJM and PJM transmission owners to show cause as to why PJM’s tariff should not be found to be unjust and unreasonable (PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (the Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 22, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Southwest Power Pool, Inc. (SPP) directing SPP and SPP transmission owners to show cause as to why SPP’s tariff should not be unjust and unreasonable (Southwest Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 18, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued show cause orders under section 206 of the Federal Power Act to PJM Interconnection, L.L.C. (PJM), Midcontinent Independent System Operator, Inc. (MISO), Southwest Power Pool, Inc. (SPP), California Independent System Operator Corporation (CAISO), ISO New England Inc. (ISO-NE) and New York Independent System Operator, Inc. (NYISO), together with their transmission owners, directing each region to justify or reform the tariff provisions governing how data centers and other large loads connect to and receive service from the transmission grid. The orders are part of FERC’s broader response to rapidly increasing electricity demand, particularly from data centers and other large loads, and advance the objectives of the Secretary of Energy’s October 2025 Advance Notice of Proposed Rulemaking (ANOPR) by seeking to accelerate “speed to power” while preserving grid reliability, affordability and consumer protections. 

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.