Northeast Supply Enhancement Project Receives Key Environmental Permits

November 12, 2025

Reading Time : 2 min

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

NESE initially received a certificate of public convenience and necessity from FERC for the project in 2019 under the Natural Gas Act (NGA), but its project sponsor ultimately canceled the project without initiating construction due to an inability to secure CWA and flood hazard permits from New York and New Jersey that were required by FERC. In 2025, following the President’s declaration of an Energy Emergency in Executive Order No. 14156 (E.O. 14156), Transco applied to reinstate the 2019 certificate, relying on FERC’s prior environmental analysis. FERC granted the requested relief on August 28, 2025, and reauthorized the project under NGA section 7.

The states’ changed position on the permits after rejecting prior applications made by Transco in 2018, 2019 and 2020, may portend a broader energy and environmental policy shift for several converging reasons. These include a surging demand for energy in the Northeast, forecasted grid reliability concerns in New York and historically high electricity prices in New Jersey. New York’s governor, Kathy Hochul, stated that the NYSDEC’s decision is consistent with her administration’s “all of the above approach” to addressing grid reliability and affordability. State officials also may be concerned about future actions by the federal government to force infrastructure development in the Northeast region in line with statements made in E.O. 14156, and seek to take greater control to maintain a level of state autonomy for federally permitted projects. Additional Northeast pipeline projects are anticipated to materialize. However, project opponents may try to challenge state-issued permits required for FERC-approved natural gas infrastructure, akin to a recent challenge to a Louisiana-issued Coastal Use Permit received by a liquefied natural gas terminal developer with FERC NGA section 3 authorization.

The Akin team will continue to monitor these regulatory developments. More information on Executive Orders impacting energy development can be found here.

Share This Insight

Previous Entries

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Midcontinent Independent System Operator, Inc. (MISO) directing MISO and MISO transmission owners to show cause as to why MISO’s tariff should not be found to be unjust and unreasonable (Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to PJM Interconnection, L.L.C. directing PJM and PJM transmission owners to show cause as to why PJM’s tariff should not be found to be unjust and unreasonable (PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (the Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 22, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Southwest Power Pool, Inc. (SPP) directing SPP and SPP transmission owners to show cause as to why SPP’s tariff should not be unjust and unreasonable (Southwest Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 18, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued show cause orders under section 206 of the Federal Power Act to PJM Interconnection, L.L.C. (PJM), Midcontinent Independent System Operator, Inc. (MISO), Southwest Power Pool, Inc. (SPP), California Independent System Operator Corporation (CAISO), ISO New England Inc. (ISO-NE) and New York Independent System Operator, Inc. (NYISO), together with their transmission owners, directing each region to justify or reform the tariff provisions governing how data centers and other large loads connect to and receive service from the transmission grid. The orders are part of FERC’s broader response to rapidly increasing electricity demand, particularly from data centers and other large loads, and advance the objectives of the Secretary of Energy’s October 2025 Advance Notice of Proposed Rulemaking (ANOPR) by seeking to accelerate “speed to power” while preserving grid reliability, affordability and consumer protections. 

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.