7th Circuit Affirms FERC Finding That Wind Generators Are Responsible for Corrected Costs

Aug 31, 2015

Reading Time : 3 min

By: Shawn Whites (paralegal)

As part of the interconnection process, MISO conducted several interconnection studies to analyze the reliability impacts of the Generators’ 150 MW wind projects and provide them with potential interconnection costs. MISO’s studies initially indicated that the Generators’ projects would require roughly $6 million in additional network upgrades, and the Generators proceeded with the execution of interconnection agreements (IAs) on that basis. The dispute arose soon thereafter when MISO notified the Generators that its studies contained a significant error—MISO overlooked a higher-queued project that would need upgrades as a result of the Generators’ interconnection. As a result, the correct cost of interconnection network upgrades required an additional $11.5 million, for a total of $17.5 million. At this point, MISO informed the Generators that they could either agree to fewer MWs (120 as opposed to 150) or pay the corrected costs in order to interconnect. The Generators rejected both options and instead looked to FERC for guidance, which ultimately ruled that the Generators were responsible for the corrected costs.

In their petitions for review, the Generators argued that their original decision to interconnect was based on a faulty contract—the IA—and thus a new agreement was needed. The court ruled, however, that FERC properly viewed the dispute from a regulatory framework, since the Generators were not “free to contract as they wish[ed]” and had to, at all times, “structure their [IAs with MISO] within [FERC’s] elaborate regulatory regime.”2 The court stated that, even if it “focus[ed] on the contract-like aspects” of the dispute, the Generators “had the option of connecting to the grid at [120 MW], paying, or walking away” after “they learned of the additional upgrades that were necessary to avoid overloading the system.”3 Instead, the Generators deferred to FERC on the matter, which relied on “substantial evidence and was not arbitrary.”4

The court further rejected the Generators’ argument that FERC’s decision violated the filed-rate doctrine. The filed rate, the Generators claimed, was the initial interconnection costs of roughly $6 million, which were “memorialized” in the original IAs. The Generators argued that the original costs included the “expectation, based on the filed rate, that all actual network upgrades and the circumstances that could lead to other potential network upgrades [had] been identified”—such as the higher-queued project later recognized by MISO.5 The court instead found that the “filed rate doctrine protects parties not from misquoted rates, but from discriminatory or fraudulent” rates and, as such, does not apply to the Generators’ case.

The Generators also sought review of FERC’s decision to implement a specific pricing option under MISO’s open access transmission tariff with respect to the payment of the additional interconnection network upgrades. Under the initially executed IAs, the Generators had agreed to a pricing option (Option 1) that was later eliminated in a separate FERC proceeding brought by MISO. A new pricing option (Option 2) was thus implemented for any future IAs between MISO and the Generators (e.g., the amended IAs that included the additional upgrades that the Generators refused to sign), although FERC chose to grandfather Option 1 pricing for the original network upgrades under the initial IAs and applied Option 2 pricing to only the additional upgrades later identified by MISO. The Generators preferred Option 2 pricing across the board, claiming that FERC’s finding was contrary to its prior decisions. The court agreed with FERC’s decision to grandfather Option 1 pricing to the original costs, since it “provided regulatory certainty” and served the Federal Power Act’s “purpose of preserving the expectations of [the] parties.”6

Though the court ultimately ruled in FERC’s favor, it touched on a number of hypotheticals in the decision, noting that the outcome of the FERC proceedings—and the court’s decision—might have been different had “the record before FERC demonstrated that the difference in the interconnection costs turned a profitable enterprise into a losing one for [the Generators].”


1 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, FERC Stats. & Regs. ¶ 31,146 (2003), order on reh’-g, Order No. 2003-A, FERC Stats. & Regs. ¶ 31,160, order on reh’g, Order No. 2003-B, FERC Stats. & Regs. ¶ 31,171 (2004), order on reh’g, Order No. 2003-C, FERC Stats. & Regs. 31,190 (2005), aff’d sub nom. Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007), cert. denied, 552 U.S. 1230 (2008). 

2 Pioneer Trail Wind Farm, LLC v. FERC, No. 13-2326, slip op. at 9 (7th Cir. Aug. 19, 2015).

3 Id. at 10.

4 Id. at 11.

5 Brief for Petitioners at 19, Pioneer Trail Wind Farm, LLC v. FERC, No. 13-2326 (7th Cir. Dec. 19, 2014).

6 Decision at 16.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.