7th Circuit Affirms FERC Finding That Wind Generators Are Responsible for Corrected Costs

Aug 31, 2015

Reading Time : 3 min

By: Shawn Whites (paralegal)

As part of the interconnection process, MISO conducted several interconnection studies to analyze the reliability impacts of the Generators’ 150 MW wind projects and provide them with potential interconnection costs. MISO’s studies initially indicated that the Generators’ projects would require roughly $6 million in additional network upgrades, and the Generators proceeded with the execution of interconnection agreements (IAs) on that basis. The dispute arose soon thereafter when MISO notified the Generators that its studies contained a significant error—MISO overlooked a higher-queued project that would need upgrades as a result of the Generators’ interconnection. As a result, the correct cost of interconnection network upgrades required an additional $11.5 million, for a total of $17.5 million. At this point, MISO informed the Generators that they could either agree to fewer MWs (120 as opposed to 150) or pay the corrected costs in order to interconnect. The Generators rejected both options and instead looked to FERC for guidance, which ultimately ruled that the Generators were responsible for the corrected costs.

In their petitions for review, the Generators argued that their original decision to interconnect was based on a faulty contract—the IA—and thus a new agreement was needed. The court ruled, however, that FERC properly viewed the dispute from a regulatory framework, since the Generators were not “free to contract as they wish[ed]” and had to, at all times, “structure their [IAs with MISO] within [FERC’s] elaborate regulatory regime.”2 The court stated that, even if it “focus[ed] on the contract-like aspects” of the dispute, the Generators “had the option of connecting to the grid at [120 MW], paying, or walking away” after “they learned of the additional upgrades that were necessary to avoid overloading the system.”3 Instead, the Generators deferred to FERC on the matter, which relied on “substantial evidence and was not arbitrary.”4

The court further rejected the Generators’ argument that FERC’s decision violated the filed-rate doctrine. The filed rate, the Generators claimed, was the initial interconnection costs of roughly $6 million, which were “memorialized” in the original IAs. The Generators argued that the original costs included the “expectation, based on the filed rate, that all actual network upgrades and the circumstances that could lead to other potential network upgrades [had] been identified”—such as the higher-queued project later recognized by MISO.5 The court instead found that the “filed rate doctrine protects parties not from misquoted rates, but from discriminatory or fraudulent” rates and, as such, does not apply to the Generators’ case.

The Generators also sought review of FERC’s decision to implement a specific pricing option under MISO’s open access transmission tariff with respect to the payment of the additional interconnection network upgrades. Under the initially executed IAs, the Generators had agreed to a pricing option (Option 1) that was later eliminated in a separate FERC proceeding brought by MISO. A new pricing option (Option 2) was thus implemented for any future IAs between MISO and the Generators (e.g., the amended IAs that included the additional upgrades that the Generators refused to sign), although FERC chose to grandfather Option 1 pricing for the original network upgrades under the initial IAs and applied Option 2 pricing to only the additional upgrades later identified by MISO. The Generators preferred Option 2 pricing across the board, claiming that FERC’s finding was contrary to its prior decisions. The court agreed with FERC’s decision to grandfather Option 1 pricing to the original costs, since it “provided regulatory certainty” and served the Federal Power Act’s “purpose of preserving the expectations of [the] parties.”6

Though the court ultimately ruled in FERC’s favor, it touched on a number of hypotheticals in the decision, noting that the outcome of the FERC proceedings—and the court’s decision—might have been different had “the record before FERC demonstrated that the difference in the interconnection costs turned a profitable enterprise into a losing one for [the Generators].”


1 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, FERC Stats. & Regs. ¶ 31,146 (2003), order on reh’-g, Order No. 2003-A, FERC Stats. & Regs. ¶ 31,160, order on reh’g, Order No. 2003-B, FERC Stats. & Regs. ¶ 31,171 (2004), order on reh’g, Order No. 2003-C, FERC Stats. & Regs. 31,190 (2005), aff’d sub nom. Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007), cert. denied, 552 U.S. 1230 (2008). 

2 Pioneer Trail Wind Farm, LLC v. FERC, No. 13-2326, slip op. at 9 (7th Cir. Aug. 19, 2015).

3 Id. at 10.

4 Id. at 11.

5 Brief for Petitioners at 19, Pioneer Trail Wind Farm, LLC v. FERC, No. 13-2326 (7th Cir. Dec. 19, 2014).

6 Decision at 16.

Share This Insight

Previous Entries

Speaking Energy

April 15, 2025

On April 9, 2025, President Trump issued an executive order (EO)1 directing several federal agencies and subagencies that regulate energy, environmental, and conservation matters,2 including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), to establish conditional sunset dates for “regulations governing energy production.” The stated objective of the EO is to require agencies to periodically reexamine their regulations to ensure that they continue to serve the public good. For FERC, the order covers regulations promulgated under the Federal Power Act (FPA), the Natural Gas Act (NGA) and the Powerplant and Industrial Fuel Use Act (FUA)3, as amended, while DOE must consider regulations promulgated under the Atomic Energy Act (AEA), the National Appliance Energy Conservation Act, the Energy Policy Act of 1992 (EPAct 1992), the Energy Policy Act of 2005 (EPAct 2005) and the Energy Independence and Security Act of 2007 (EISA), as amended (collectively the Covered Regulations).4 To the extent the DOE has been directed to promulgate regulations under various sections of the NGA, FPA and FUA, and FERC has been directed to promulgate regulations specific to the statutes attributed to the DOE in the EO, the EO is silent. The EO expressly does not apply to those “regulatory permitting regimes authorized by statute.”5

...

Read More

Speaking Energy

April 10, 2025

On April 8, 2025, President Trump issued an Executive Order (EO) directing the Department of Energy (DOE) to take steps to expand the use of its emergency authority under Federal Power Act (FPA) Section 202(c) to require the retention of generation resources deemed necessary to maintain resource adequacy within at risk-regions of the bulk power system regulated by the Federal Energy Regulatory Commission (FERC).1 The EO appears to envision a more active role for DOE in overseeing and supporting the resource adequacy of the grid that deviates from the historic use of Section 202(c) and touches on issues at the intersection of state and federal authority over resource planning.

...

Read More

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.