7th Circuit Affirms FERC Finding That Wind Generators Are Responsible for Corrected Costs

Aug 31, 2015

Reading Time : 3 min

By: Shawn Whites (paralegal)

As part of the interconnection process, MISO conducted several interconnection studies to analyze the reliability impacts of the Generators’ 150 MW wind projects and provide them with potential interconnection costs. MISO’s studies initially indicated that the Generators’ projects would require roughly $6 million in additional network upgrades, and the Generators proceeded with the execution of interconnection agreements (IAs) on that basis. The dispute arose soon thereafter when MISO notified the Generators that its studies contained a significant error—MISO overlooked a higher-queued project that would need upgrades as a result of the Generators’ interconnection. As a result, the correct cost of interconnection network upgrades required an additional $11.5 million, for a total of $17.5 million. At this point, MISO informed the Generators that they could either agree to fewer MWs (120 as opposed to 150) or pay the corrected costs in order to interconnect. The Generators rejected both options and instead looked to FERC for guidance, which ultimately ruled that the Generators were responsible for the corrected costs.

In their petitions for review, the Generators argued that their original decision to interconnect was based on a faulty contract—the IA—and thus a new agreement was needed. The court ruled, however, that FERC properly viewed the dispute from a regulatory framework, since the Generators were not “free to contract as they wish[ed]” and had to, at all times, “structure their [IAs with MISO] within [FERC’s] elaborate regulatory regime.”2 The court stated that, even if it “focus[ed] on the contract-like aspects” of the dispute, the Generators “had the option of connecting to the grid at [120 MW], paying, or walking away” after “they learned of the additional upgrades that were necessary to avoid overloading the system.”3 Instead, the Generators deferred to FERC on the matter, which relied on “substantial evidence and was not arbitrary.”4

The court further rejected the Generators’ argument that FERC’s decision violated the filed-rate doctrine. The filed rate, the Generators claimed, was the initial interconnection costs of roughly $6 million, which were “memorialized” in the original IAs. The Generators argued that the original costs included the “expectation, based on the filed rate, that all actual network upgrades and the circumstances that could lead to other potential network upgrades [had] been identified”—such as the higher-queued project later recognized by MISO.5 The court instead found that the “filed rate doctrine protects parties not from misquoted rates, but from discriminatory or fraudulent” rates and, as such, does not apply to the Generators’ case.

The Generators also sought review of FERC’s decision to implement a specific pricing option under MISO’s open access transmission tariff with respect to the payment of the additional interconnection network upgrades. Under the initially executed IAs, the Generators had agreed to a pricing option (Option 1) that was later eliminated in a separate FERC proceeding brought by MISO. A new pricing option (Option 2) was thus implemented for any future IAs between MISO and the Generators (e.g., the amended IAs that included the additional upgrades that the Generators refused to sign), although FERC chose to grandfather Option 1 pricing for the original network upgrades under the initial IAs and applied Option 2 pricing to only the additional upgrades later identified by MISO. The Generators preferred Option 2 pricing across the board, claiming that FERC’s finding was contrary to its prior decisions. The court agreed with FERC’s decision to grandfather Option 1 pricing to the original costs, since it “provided regulatory certainty” and served the Federal Power Act’s “purpose of preserving the expectations of [the] parties.”6

Though the court ultimately ruled in FERC’s favor, it touched on a number of hypotheticals in the decision, noting that the outcome of the FERC proceedings—and the court’s decision—might have been different had “the record before FERC demonstrated that the difference in the interconnection costs turned a profitable enterprise into a losing one for [the Generators].”


1 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, FERC Stats. & Regs. ¶ 31,146 (2003), order on reh’-g, Order No. 2003-A, FERC Stats. & Regs. ¶ 31,160, order on reh’g, Order No. 2003-B, FERC Stats. & Regs. ¶ 31,171 (2004), order on reh’g, Order No. 2003-C, FERC Stats. & Regs. 31,190 (2005), aff’d sub nom. Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007), cert. denied, 552 U.S. 1230 (2008). 

2 Pioneer Trail Wind Farm, LLC v. FERC, No. 13-2326, slip op. at 9 (7th Cir. Aug. 19, 2015).

3 Id. at 10.

4 Id. at 11.

5 Brief for Petitioners at 19, Pioneer Trail Wind Farm, LLC v. FERC, No. 13-2326 (7th Cir. Dec. 19, 2014).

6 Decision at 16.

Share This Insight

Previous Entries

Speaking Energy

July 8, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to ISO New England Inc. (ISO-NE) directing ISO-NE and ISO-NE participating transmission owners to show cause as to why ISO-NE’s tariff should not be found to be unjust and unreasonable (ISO New England Inc., 195 FERC ¶ 61,215 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

July 7, 2026

On June 29, 2026, the Supreme Court granted a petition for certiorari in Leonard Hoffmann v. WBI Energy Transmission, Inc. (Hoffmann), which presents the question whether section 7 of the Natural Gas Act (NGA) requires pipeline companies using federal eminent domain authority to pay landowners’ attorney’s fees in states where landowners can recover those fees under state law. In the decision giving rise to the Supreme Court’s review, the U.S. Court of Appeals for the Eighth Circuit held that a group of ranchers were not entitled to recover their $383,300 in attorney’s fees incurred while negotiating their compensation—creating a circuit split with four other courts of appeals. Hoffmann will be heard during the Court’s October 2026 Term, and marks the second time in five years that the Court has agreed to interpret NGA section 7.

...

Read More

Speaking Energy

July 6, 2026

On June 29, 2026, the United States Supreme Court issued Trump v. Slaughter, fundamentally reshaping presidential removal authority over independent regulatory agencies. The decision overruled a 90-year-old precedent established in Humphrey’s Executor v. United States, which had upheld the constitutionality of commissioner removal protections in the Federal Trade Commission Act (FTC Act). As written, the FTC Act permits a commissioner’s removal “only for inefficiency, neglect of duty, or malfeasance in office.” In Slaughter, the Court was asked to reevaluate this standard following the President’s removal of a Democratic-appointed FTC commissioner from office in 2025 without cause. Finding for the President, the Court held that removal was permissible because the FTC Act’s for-cause removal protections for commissioners violate the separation of powers, specifically, the President’s removal power under Article II. The Court explained that the FTC exercises executive power because it promulgates binding rules, investigates and enforces those rules through administrative adjudications, and brings civil enforcement actions in federal court. It found that because it exercises these executive powers, its commissioners “must therefore be controlled by the Chief Executive, in whom such power is vested.” While previous recent cases addressing the scope of the Removal Power, Seila Law LLC v. Consumer Financial Protection Bureau and Collins v. Yellen purported to preserve some kernel of Humphrey’s, the Court made clear that “[i]f anything more is left of Humphrey’s, we overrule it.”

...

Read More

Speaking Energy

June 25, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to the California Independent System Operator Corporation (CAISO) directing CAISO and CAISO transmission owners to show cause as to why CAISO’s tariff should not be found to be unjust and unreasonable (California Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (the Order)) because it fails to sufficiently:

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.