Arizona Increased Tax Credit for Renewable Energy Facilities Used for Self-Consumption by Five Times per Facility

Oct 1, 2015

Reading Time : 3 min

Favorable Revisions

First, taxpayers may now claim a total of $25 million of tax credits per renewable energy facility instead of $5 million.  Previously, a taxpayer could receive a $1 million credit annually for each of the first five years a given renewable energy facility was operational.  The $1 million annual limit has been lifted to $5 million.  The five-year limit remains.

Second, the credit had previously been applicable only for taxpayers using their renewable energy production in furtherance of supporting the taxpayer’s manufacturing facility, but it is now also applicable for taxpayers using such energy for the purpose of supporting the taxpayer’s “International Operations Center.”  An International Operations Center is defined as a facility “that self-consumes renewable energy from a qualified [Arizona renewable energy] facility” and invests $1.25 billion in new capital assets (including costs of land, buildings and equipment) within 10 years, with a minimum of $100 million being spent annually (investments greater than $100 million in any year can be carried forward to make up for any shortfalls in future years).  A certification must be obtained from the Arizona Commerce Authority to validate that an investment is on track for these thresholds and that the property thus qualifies as an International Operations Center.

Third, with respect to International Operations Centers, self-consumption is very broadly defined to include power transferred to a utility “if the utility is the same utility that provides power to the owner’s International Operations Center in [Arizona].”  Therefore, for an International Operations Center, net metering is permitted, and the center does not actually have to use any of the electricity generated at its site.  With respect to manufacturing facilities, “self-consumption” continues to include power transferred to a utility if at least 90 percent of the power is “transferred back for self-consumption in [Arizona].”  

Key Considerations

Key considerations that taxpayers should keep in mind when planning to claim these credits include the following three concepts.

First, timing is critical.  Arizona will issue only $10 million of these credits per year, on a first-come, first-served basis.  This cap has not been increased, even though an individual facility may now qualify for $5 million of credits annually.  Taxpayers interested in claiming these credits should apply for them immediately, because two taxpayers each claiming the maximum would exhaust the available mandate. 

Furthermore, with respect to timing, if an International Operations Center is used, by December 31, 2018, a taxpayer must invest at least $100 million in a renewable energy facility in Arizona.  This $100 million is in addition to the above-mentioned capital spending requirements on the International Operations Center—meaning that a total outlay of at least $1.35 billion will be required to avoid having the credits clawed back.  For manufacturing operations, the rule continues to be that $300 million must be spent on Arizona renewable energy facilities by December 31, 2017, for a taxpayer to be eligible for the credits.    

Second, the credits can be clawed back if it turns out that the capital expenditure requirements are ultimately not met.  For example, if $1.25 billion is not spent on an International Operations Center within 10 years after its certification, the taxpayer will need to reimburse all credits used (potentially $25 million) to the state of Arizona.  Exemption from reimbursement may be granted only under circumstances of extraordinary hardship outside of a taxpayer’s control.

Third, the taxpayer is explicitly permitted to lease an International Operations Center to another party and still be eligible to claim the credits, and it may also be able to lease the associated renewable energy facility as well (with respect to the renewable energy facility, the applicable statutes appear to stipulate only that the taxpayer must “invest” in the facility, without prohibiting the leasing of such a facility).  This creates a significant tax credit opportunity for a financial institution with Arizona tax liability that is interested in making a passive investment in an International Operations Center and an associated renewable energy facility.

*This blog post was originally on Tax Equity Telegraph.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.