Arizona Increased Tax Credit for Renewable Energy Facilities Used for Self-Consumption by Five Times per Facility

Oct 1, 2015

Reading Time : 3 min

Favorable Revisions

First, taxpayers may now claim a total of $25 million of tax credits per renewable energy facility instead of $5 million.  Previously, a taxpayer could receive a $1 million credit annually for each of the first five years a given renewable energy facility was operational.  The $1 million annual limit has been lifted to $5 million.  The five-year limit remains.

Second, the credit had previously been applicable only for taxpayers using their renewable energy production in furtherance of supporting the taxpayer’s manufacturing facility, but it is now also applicable for taxpayers using such energy for the purpose of supporting the taxpayer’s “International Operations Center.”  An International Operations Center is defined as a facility “that self-consumes renewable energy from a qualified [Arizona renewable energy] facility” and invests $1.25 billion in new capital assets (including costs of land, buildings and equipment) within 10 years, with a minimum of $100 million being spent annually (investments greater than $100 million in any year can be carried forward to make up for any shortfalls in future years).  A certification must be obtained from the Arizona Commerce Authority to validate that an investment is on track for these thresholds and that the property thus qualifies as an International Operations Center.

Third, with respect to International Operations Centers, self-consumption is very broadly defined to include power transferred to a utility “if the utility is the same utility that provides power to the owner’s International Operations Center in [Arizona].”  Therefore, for an International Operations Center, net metering is permitted, and the center does not actually have to use any of the electricity generated at its site.  With respect to manufacturing facilities, “self-consumption” continues to include power transferred to a utility if at least 90 percent of the power is “transferred back for self-consumption in [Arizona].”  

Key Considerations

Key considerations that taxpayers should keep in mind when planning to claim these credits include the following three concepts.

First, timing is critical.  Arizona will issue only $10 million of these credits per year, on a first-come, first-served basis.  This cap has not been increased, even though an individual facility may now qualify for $5 million of credits annually.  Taxpayers interested in claiming these credits should apply for them immediately, because two taxpayers each claiming the maximum would exhaust the available mandate. 

Furthermore, with respect to timing, if an International Operations Center is used, by December 31, 2018, a taxpayer must invest at least $100 million in a renewable energy facility in Arizona.  This $100 million is in addition to the above-mentioned capital spending requirements on the International Operations Center—meaning that a total outlay of at least $1.35 billion will be required to avoid having the credits clawed back.  For manufacturing operations, the rule continues to be that $300 million must be spent on Arizona renewable energy facilities by December 31, 2017, for a taxpayer to be eligible for the credits.    

Second, the credits can be clawed back if it turns out that the capital expenditure requirements are ultimately not met.  For example, if $1.25 billion is not spent on an International Operations Center within 10 years after its certification, the taxpayer will need to reimburse all credits used (potentially $25 million) to the state of Arizona.  Exemption from reimbursement may be granted only under circumstances of extraordinary hardship outside of a taxpayer’s control.

Third, the taxpayer is explicitly permitted to lease an International Operations Center to another party and still be eligible to claim the credits, and it may also be able to lease the associated renewable energy facility as well (with respect to the renewable energy facility, the applicable statutes appear to stipulate only that the taxpayer must “invest” in the facility, without prohibiting the leasing of such a facility).  This creates a significant tax credit opportunity for a financial institution with Arizona tax liability that is interested in making a passive investment in an International Operations Center and an associated renewable energy facility.

*This blog post was originally on Tax Equity Telegraph.

Share This Insight

Previous Entries

Speaking Energy

April 15, 2025

On April 9, 2025, President Trump issued an executive order (EO)1 directing several federal agencies and subagencies that regulate energy, environmental, and conservation matters,2 including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), to establish conditional sunset dates for “regulations governing energy production.” The stated objective of the EO is to require agencies to periodically reexamine their regulations to ensure that they continue to serve the public good. For FERC, the order covers regulations promulgated under the Federal Power Act (FPA), the Natural Gas Act (NGA) and the Powerplant and Industrial Fuel Use Act (FUA)3, as amended, while DOE must consider regulations promulgated under the Atomic Energy Act (AEA), the National Appliance Energy Conservation Act, the Energy Policy Act of 1992 (EPAct 1992), the Energy Policy Act of 2005 (EPAct 2005) and the Energy Independence and Security Act of 2007 (EISA), as amended (collectively the Covered Regulations).4 To the extent the DOE has been directed to promulgate regulations under various sections of the NGA, FPA and FUA, and FERC has been directed to promulgate regulations specific to the statutes attributed to the DOE in the EO, the EO is silent. The EO expressly does not apply to those “regulatory permitting regimes authorized by statute.”5

...

Read More

Speaking Energy

April 10, 2025

On April 8, 2025, President Trump issued an Executive Order (EO) directing the Department of Energy (DOE) to take steps to expand the use of its emergency authority under Federal Power Act (FPA) Section 202(c) to require the retention of generation resources deemed necessary to maintain resource adequacy within at risk-regions of the bulk power system regulated by the Federal Energy Regulatory Commission (FERC).1 The EO appears to envision a more active role for DOE in overseeing and supporting the resource adequacy of the grid that deviates from the historic use of Section 202(c) and touches on issues at the intersection of state and federal authority over resource planning.

...

Read More

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.