Arizona Increased Tax Credit for Renewable Energy Facilities Used for Self-Consumption by Five Times per Facility

Oct 1, 2015

Reading Time : 3 min

Favorable Revisions

First, taxpayers may now claim a total of $25 million of tax credits per renewable energy facility instead of $5 million.  Previously, a taxpayer could receive a $1 million credit annually for each of the first five years a given renewable energy facility was operational.  The $1 million annual limit has been lifted to $5 million.  The five-year limit remains.

Second, the credit had previously been applicable only for taxpayers using their renewable energy production in furtherance of supporting the taxpayer’s manufacturing facility, but it is now also applicable for taxpayers using such energy for the purpose of supporting the taxpayer’s “International Operations Center.”  An International Operations Center is defined as a facility “that self-consumes renewable energy from a qualified [Arizona renewable energy] facility” and invests $1.25 billion in new capital assets (including costs of land, buildings and equipment) within 10 years, with a minimum of $100 million being spent annually (investments greater than $100 million in any year can be carried forward to make up for any shortfalls in future years).  A certification must be obtained from the Arizona Commerce Authority to validate that an investment is on track for these thresholds and that the property thus qualifies as an International Operations Center.

Third, with respect to International Operations Centers, self-consumption is very broadly defined to include power transferred to a utility “if the utility is the same utility that provides power to the owner’s International Operations Center in [Arizona].”  Therefore, for an International Operations Center, net metering is permitted, and the center does not actually have to use any of the electricity generated at its site.  With respect to manufacturing facilities, “self-consumption” continues to include power transferred to a utility if at least 90 percent of the power is “transferred back for self-consumption in [Arizona].”  

Key Considerations

Key considerations that taxpayers should keep in mind when planning to claim these credits include the following three concepts.

First, timing is critical.  Arizona will issue only $10 million of these credits per year, on a first-come, first-served basis.  This cap has not been increased, even though an individual facility may now qualify for $5 million of credits annually.  Taxpayers interested in claiming these credits should apply for them immediately, because two taxpayers each claiming the maximum would exhaust the available mandate. 

Furthermore, with respect to timing, if an International Operations Center is used, by December 31, 2018, a taxpayer must invest at least $100 million in a renewable energy facility in Arizona.  This $100 million is in addition to the above-mentioned capital spending requirements on the International Operations Center—meaning that a total outlay of at least $1.35 billion will be required to avoid having the credits clawed back.  For manufacturing operations, the rule continues to be that $300 million must be spent on Arizona renewable energy facilities by December 31, 2017, for a taxpayer to be eligible for the credits.    

Second, the credits can be clawed back if it turns out that the capital expenditure requirements are ultimately not met.  For example, if $1.25 billion is not spent on an International Operations Center within 10 years after its certification, the taxpayer will need to reimburse all credits used (potentially $25 million) to the state of Arizona.  Exemption from reimbursement may be granted only under circumstances of extraordinary hardship outside of a taxpayer’s control.

Third, the taxpayer is explicitly permitted to lease an International Operations Center to another party and still be eligible to claim the credits, and it may also be able to lease the associated renewable energy facility as well (with respect to the renewable energy facility, the applicable statutes appear to stipulate only that the taxpayer must “invest” in the facility, without prohibiting the leasing of such a facility).  This creates a significant tax credit opportunity for a financial institution with Arizona tax liability that is interested in making a passive investment in an International Operations Center and an associated renewable energy facility.

*This blog post was originally on Tax Equity Telegraph.

Share This Insight

Previous Entries

Speaking Energy

March 10, 2026

Federal energy regulators are assuming expanded roles as the administration prioritizes energy dominance and infrastructure development to meet unprecedented power demand. FERC Chairman Laura Swett has vowed to expedite data center interconnections while addressing jurisdictional challenges, warning that unmet electricity demand could drive data centers abroad and create national security risks. The agency is processing pipeline applications faster than in prior years and considering blanket authorizations for certain LNG and hydroelectric projects to streamline approvals. 

Pipeline projects previously stalled by Clean Water Act permits are being revitalized, particularly in northeastern states where historically high electricity prices have increased openness to natural gas infrastructure. The Department of Energy is expanding its emergency authority to require retention of generation resources and has granted major LNG export approvals, signaling commitment to expanding U.S. export capacity under a streamlined framework that deprioritizes climate considerations.  

The Administration is bullish on the opportunities for the U.S. energy industry in Venezuela and eager to support companies willing to navigate the political risk inherent in the operations at the moment. Early meetings with President Trump and industry leaders showed the path forward may be longer and more complex than anticipated by the President. 

As permitting reforms advance and the pendulum swings toward fossil fuel favorability, the regulatory and policy landscape is fundamentally reshaping energy infrastructure development timelines and investment opportunities. 

Oil & Gas in 2026: Energy Policy & Regulation 

Delve into the complete regulatory & policy outlook at our Oil & Gas in 2026 report.

...

Read More

Speaking Energy

March 3, 2026

Macroeconomic turbulence and volatile commodity markets significantly influenced oil & gas M&A activity throughout 2025, with deals showing renewed momentum only in the year's second half.  

...

Read More

Speaking Energy

February 24, 2026

On February 19, 2026, the Federal Energy Regulatory Commission (FERC) issued an order rescinding the soft price cap for bilateral spot market energy sales in the Western Electricity Coordinating Council (WECC) region.1 As previously covered, on July 15, 2025, FERC initiated a Federal Power Act Section 206 proceeding following the D.C. Circuit’s decision finding that FERC must apply the Mobile-Sierra public interest standard before ordering refunds for above-cap bilateral sales and vacating FERC’s orders requiring refunds for certain bilateral spot market transactions in the WECC region that exceeded the $1,000 MWh soft price cap.2 FERC’s Order follows through on the proposal it made last July to eliminate the WECCs soft price cap and marks a recognition that Western wholesale markets have evolved over the past two decades to become sufficiently competitive to render the soft price cap unnecessary.  

...

Read More

Speaking Energy

February 23, 2026

The oil & gas industry is experiencing a fundamental transformation in how companies access and deploy capital in 2026. Despite strong balance sheets and robust free cash flow generation, the sector is witnessing strategic shifts in funding sources and investment priorities that signal a new era of capital allocation.

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.