DOE Directs FERC To Initiate Large Load Interconnection Rulemaking

October 27, 2025

Reading Time : 10+ min

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

Citing “unprecedented and extraordinary” electricity demand driven by the rapid proliferation of data centers, onshoring of manufacturing, and trends in electrification, the Directive would have FERC address the lack of standardized rules governing how large loads—which it preliminarily defines as greater than 20 MW2 —are interconnected at the transmission level. The Directive issued shortly after the Senate confirmation of two new Republican FERC commissioners, Chair Laura V. Swett and Commissioner David LaCerte. Swett and LaCerte are the first appointments of the second Trump Administration to the agency and provide Republicans with a majority for the first time since August 2021.3 The new makeup of the agency along the Directive’s ambitious timeline suggest that FERC is likely to move quickly to address the issue of large load interconnection. Commissioner David Rosner, the agency’s prior Acting Chairman, has already expressed eagerness to work on the Secretary’s proposal.4

The ANOPR provides FERC with a critical opportunity to clarify FERC policy on large load interconnections. Although FERC has held a technical conference on the co-location of large loads5 and instituted a Federal Power Act (FPA) Section 206 proceeding regarding co-locating large loads in PJM Interconnection, L.L.C.,6 FERC has not provided comprehensive guidance on the process, cost allocation requirements, or timeline that transmission providers must follow when addressing large load requests. Additionally, the limited orders that FERC issued under the leadership of former Chairman Mark Christie appeared skeptical of the ability of the grid to accommodate loads without impairing service to other customers, including certain well-publicized orders thwarting efforts to co-locate large loads with existing generation in PJM.7 The ANOPR provides FERC with an opportunity to articulate a coherent policy framework that creates a path for the interconnection of large loads that recognizes the strategic and economic importance of large loads while maintaining reliability and resource adequacy.

Section 403 Authority

The Directive is issued pursuant to Section 403 of the Department of Energy Organization Act, which allows the Secretary of Energy to “propose rules, regulations, and statements of policy of general applicability with respect to any function within the jurisdiction of the [FERC].”8 The legal impact of the Directive is, however, somewhat limited. FERC is not required to adopt any DOE proposal. It must only “consider” such proposal and take final action on the proposal in an “expeditious manner” and “in accordance with such reasonable time limits as may be set by the Secretary…”9

The directive marks the second time10 that the current Secretary has invoked his Section 403 authority following his August 29, 2025 directive for FERC to terminate its long-running proceeding addressing proposed updates to its policy statement on the certification of new interstate natural gas facilities.11 FERC followed the August 2025 Directive by issuing an order terminating its interstate natural gas facilities certificate proceeding just 14 days later.12 Prior to the August 2025 Directive, the DOE Secretary had not issued a Section 403 directive to FERC since former Secretary Rick Perry directed FERC to consider action to require transmission providers to compensate generation resources with on-site fuel supplies.13 Following extensive and widespread opposition to the Secretary Perry’s directive, FERC declined to adopt his proposed rule and terminated the proceeding.14

Jurisdiction Over Transmission-Level Interconnections

Parties are likely to contest whether FERC has jurisdiction over the interconnection of large loads to the transmission system. Historically, FERC has declined to assert jurisdiction over load interconnections in deference to the states’ authority over retail sales. In anticipation of these arguments, the Secretary’s Directive asserts that the interconnection of large loads to the transmission system falls “squarely within the [FERC’s] jurisdiction.”15 The ANOPR draws upon the U.S. Supreme Court’s decision in New York v. FERC, in which the Court upheld FERC’s decision to exercise jurisdiction over unbundled retail sales but declined jurisdiction over bundled retail sales.16 The Court explained that “[t]he unbundled retail transmissions targeted by FERC are indeed transmissions of ‘electric energy in interstate commerce,’” subject to FERC jurisdiction and “[t]here is no language in the [FPA] limiting FERC’s transmission jurisdiction to the wholesale market…”17 It found that FERC had “discretion to decline to assert such jurisdiction [over bundled retail transactions] … in part because of the complicated nature of the jurisdictional issues.”18 The ANOPR questions FERC’s decision not to exercise jurisdiction over bundled retail sales, by citing to Justice Clarence Thomas’s dissent in which he disagreed with the Court’s conclusion that FERC could decline such jurisdiction since “FERC has jurisdiction over all interstate transmission, regardless of the type of transaction with which it is associated…”19

The ANOPR also finds support for the Secretary’s jurisdictional assertion in FERC’s generator interconnection framework. The ANOPR explains that in Order No. 2003 FERC found that generator interconnection is a “critical component of open access transmission service” over which it has jurisdiction to establish a standardized set of non-discriminatory procedures that transmission providers are required to adopt.20 Although the ANOPR does not directly compare the pre-Order No. 2003 generator interconnection process in which generators faced an “inefficient,” “case-by-case approach” to interconnect that “frequently result in complex, time consuming technical dispute about interconnection feasibility, cost, and cost responsibility,”21 the parallels between such process and current load interconnection processes are not difficult to draw.

From this background, the ANOPR identifies four legal justifications for FERC to assert jurisdiction over large load interconnections:

  1. Load interconnection are, like generator interconnections, a “critical component of open access transmission service” over which FERC has jurisdiction.22 FERC’s exclusive jurisdiction over interstate transmission service would appear, based upon the discussion of New York and FERC’s generator interconnection framework, to be the primary basis that DOE believes FERC has jurisdiction over large load interconnections.
  2. Load interconnections directly affect FERC-jurisdictional wholesale electricity rates, for which courts have found FERC has jurisdiction.23 Although the ANOPR does not elaborate on how FERC’s “affecting” jurisdiction extends to large load interconnections, courts have approved FERC’s assertion of jurisdiction over other entities that were engaged in activities that touched on state jurisdiction. For example, courts have found FERC has jurisdiction to establish rates for demand response participating in wholesale markets and to require states to allow energy storage resources to participate in wholesale markets, including by interconnecting at the distribution level.24
  3. FERC’s assertion of jurisdiction over large load interconnections will not infringe on states’ authority over retail electricity sales or the siting of generating facilities.25 The ANOPR explains that while states have authority over retail sales and the siting, expansion, and modification of generating facilities, FERC’s adoption of processes governing large load interconnections will not impinge on this authority since the ANOPR does not address retail sales or the siting, expansion, and modification of generation facilities.
  4. Finally, “[a]ny contrary view of the proposed reforms conflicts with the FPA’s core purposes.”26 The ANOPR’s point appears to be that that a core purpose of the FPA is that FERC shall be vested with exclusive jurisdiction to oversee the rates, terms, and conditions of transmission service and large loads interconnecting to the transmission system intend to obtain such service and its associated benefits. The interconnection of large loads thus falls within FERC’s jurisdiction.

Principles for Large Load Interconnection Processes

The ANOPR sets forth 14 broad principles that “should inform [FERC’s] rulemaking procedures.”27 Some of these principles may be relatively uncontroversial (e.g., utilities serving large loads must meet all applicable North American Electric Reliability Corporation (NERC) reliability standards and transmission provider tariff requirements).28 But many other principles are likely to generate significant comment from utilities, large loads, generators, and consumers.

The 14 principles that the ANOPR instructs should inform FERC’s rulemaking are as follows:29

  1. Limit FERC’s jurisdiction to interconnections directly to transmission facilities, consistent with FERC’s seven-factor test, to avoid infringing on state regulation of distribution facilities.30 FERC historically has applied the seven-factor test to evaluate whether facilities constitute transmission facilities subject to FERC’s jurisdiction or local distribution facilities subject to the exclusive authority of the states.
  2. Apply the load interconnection process to new loads greater than 20 MW (and hybrid facilities with greater than 20 MW load).
  3. Study large loads jointly with generation to promote efficient siting and minimize costly network upgrades.
  4. Adopt standardized deposits, readiness criteria, and withdrawal penalties to deter speculative large loads and improve queue management.
  5. Study hybrid facilities (i.e., facilities consisting of both load and generation) based on their net injection/withdrawal rights to encourage co-location and efficient grid use.
  6. Require system-protection equipment for hybrid projects to prevent unauthorized injections or withdrawals, with potential penalties for violations.
  7. Expedite studies (potentially as fast as 60-days) for large loads that agree to be curtailable.
  8. Assign full responsibility for network-upgrade costs to interconnecting loads, with potential crediting or recovery mechanisms.
  9. Provide large loads the option-to-build interconnection facilities and certain network upgrades, consistent with the generator option-to-build.
  10. Require SSR/RMR-type studies when generators partially suspend operations to serve new load, ensuring reliability before suspension.
  11. Charge for transmission service based on withdrawal rights to reflect the capacity and energy transmitted to serve such load.
  12. Utilities serving large loads should be responsible for ancillary services based on peak demand without any consideration of co-located generation; however, any co-located generation should be fully compensated for the provision of ancillary services.
  13. Establish transition plans for pending large load interconnections under study.
  14. Require compliance with NERC standards, including possible new registration categories or modified standards to protect the bulk-power system.

The 14 principles set forth in the ANOPR appear designed to push FERC in the direction of resolving certain issues related to the interconnection and integration of large loads that already are being hotly contested before the FERC. For instance, the principle that facilities be studied and charged for transmission based on a net basis appears to put DOE’s weight behind parties that have argued that large loads should be permitted to serve a portion of their demand behind the meter without being subjected to transmission charges. At the same time, the ANOPR appears to make a concession to those parties that have argued that certain charges—such as ancillary services—should be allocated based on the gross capacity of a large load even if a portion may be served by onsite generation, although the ANOPR also confirms that onsite generation should have the opportunity to supply and be compensated for these services.

The ANOPR seeks comment on many of the 14 principles, including how to define large loads,31 what financial commitments or withdrawal penalties should apply to large load interconnections processes,32 and whether expedited study processes should be available for curtailable large loads.33 If FERC moves forward with a large load interconnection rulemaking, interested parties will have the opportunity to comment on other principles and present alternatives for FERC’s consideration.

It will now be on FERC to take up the ANOPR. While FERC has discretion regarding the substance of any orders that it issues in response to DOE’s directive, FERC will need to move quickly if it is to meet the DOE’s deadline of taking “final action” on the proposal by April 2026. Given that DOE’s proposal is cast as an ANOPR—which typically precedes the issuance of a notice of proposed rulemaking and final rule—it seems likely that any actions that are taken by FERC by April 2026 may represent the first steps in a longer rulemaking process. Nevertheless, an order by the FERC articulating its view on the principles included in the ANOPR would represent a milestone in the FERC’s articulation of a policy respecting the interconnection of large loads.


1 Secretary of Energy’s Direction that the Federal Energy Regulatory Commission Initiate Rulemaking Procedures and Proposal Regarding the Interconnection of Large Loads Pursuant to the Secretary’s Authority Under Section 403 of the Department of Energy Organization Act (Oct. 23, 2025), https://www.energy.gov/articles/secretary-wright-acts-unleash-american-industry-and-innovation-newly-proposed-rules (“Directive”).

2 ANOPR at ¶ 1, n.1.

3 Maya Weber and Ellie Potter, Chatterjee set to depart FERC on Aug. 30, leaving 2-2 voting split, S&P Global (Aug. 20, 2021), https://www.spglobal.com/commodity-insights/en/news-research/latest-news/electric-power/082021-chatterjee-set-to-depart-ferc-on-aug-30-leaving-2-2-voting-split.

4 David Rosner, October 24, 2025 LinkedIn Post (Oct. 24, 2025), available at: https://www.linkedin.com/feed/update/urn:li:activity:7387508898917715968/ (stating that “I am excited to work with my colleagues on U.S. Department of Energy (DOE) Secretary Wright’s large load proposal. Getting large load interconnection right is a generational opportunity that’s key to winning the AI race, reshoring American manufacturing, and keeping electricity reliable and affordable for everyone. There is broad bipartisan support for the Federal Energy Regulatory Commission taking action soon on these issues, and I appreciate the Secretary turning to FERC to do so.”).

5 Large Loads Co-Located at Generating Facilities, Docket No. AD24-11-000, Third Supplemental Notice of Commissioner-Led Technical Conference (Oct. 10, 2024).

6 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025).

7 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024).

8 42 U.S.C. § 7173.

9 Id.

10 A third Section 403 directive was issued on the same day.

11 Certification of New Interstate natural Gas Facilities, Docket Nos. PL18-1-000, et al., Secretary of Energy’s Direction that the Federal Energy Regulatory Commission Initiate Rulemaking Procedures and Proposal to Rescind the Draft Updated Certificate Policy Statement Pursuant to the Secretary’s Authority Under Section 403 of the Department of Energy Organization Act (Aug. 29, 2025) (“August 2025 Directive”).

12 Certification of New Interstate Natural Gas Facilities, 192 FERC ¶ 61,216 (2025).

13 Grid Reliability and Resilience Pricing, Docket No. RM18-1-000, Secretary of Energy’s Direction that the Federal Energy Regulatory Commission Issue Grid Resiliency Rules Pursuant to the Secretary’s Authority Under Section 403 of the Department of Energy Organization Act at 7 (Sept. 28, 2017).

14 Grid Reliability and Resilience Pricing, 162 FERC ¶ 61,012 (2018).

15 Directive at 1.

16 ANOPR at ¶ 4.

17 New York v. FERC, 535 U.S. 1, 17 (2002).

18 ANOPR at ¶ 4 (quoting New York v. FERC, 535 U.S. 1, 28 (2002)).

19 ANOPR at ¶ 5 (quoting New York v. FERC, 535 U.S. 1 (2002) (Thomas, J. dissenting at 29)). The ANOPR also cites FERC’s recent transmission planning and cost allocation rule Order No. 1920, but aside from noting that Order No. 1920 built upon prior orders addressing FERC’s open access transmission policy, it did not further elaborate on the jurisdictional support Order No. 1920 may lend to the Directive.

20 ANOPR at ¶ 7 (quoting Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103, at P 9 (2003) (“Order No. 2003”), order on reh’g, Order No. 2003‐A, 106 FERC ¶ 61,220 (2004), order on reh’g, Order No. 2003‐B, 109 FERC ¶ 61,287 (2005), order on reh’g, Order No. 2003‐C, 111 FERC ¶ 61,401 (2005), aff’d sub nom., National Ass’n of Regulatory Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007)).

21 ANOPR at ¶¶ 7, 8 (quoting Order No. 2003 at ¶¶ 10, 11).

22 ANOPR at ¶ 13.

23 ANOPR at ¶ 14 (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260 (2016)).

24 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260 (2016); Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 964 F.3d 1177 (D.C. Cir. 2020).

25 ANOPR at ¶ 15.

26 ANOPR at ¶ 16.

27 ANOPR at ¶ 17.

28 ANOPR at ¶ 30.

29 ANOPR at ¶¶ 18-31.

30 The ANOPR asserts that this limiting principle will ensure that states’ jurisdiction over generation or distribution facilities is not “even arguably” affected. ANOPR at ¶ 18.

31 ANOPR at ¶ 19.

32 ANOPR at ¶ 21.

33 ANOPR at ¶ 24.

Share This Insight

Previous Entries

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.