D.C. Circuit Upholds Order No. 1000, FERC’s Landmark Transmission Planning and Cost Allocation Rulemaking Order

Aug 18, 2014

Reading Time : 3 min

FERC determined in Order No. 1000 that “the narrow focus of [the pre-Order No. 1000] planning requirements and shortcomings of [the pre-Order No. 1000] cost allocation practices create an environment that fails to promote the more efficient and cost-effective development of new transmission facilities, and that addressing these issues is necessary to ensure just and reasonable rates.”3 The D.C. Circuit agreed, concluding that there was “substantive evidence of a theoretical threat” to justify FERC’s adoption of the Order No. 1000 pursuant to an FPA Section 206 rulemaking proceeding.

In Order No. 1000, FERC mandated that a regional transmission planning process consider and evaluate transmission projects proposed by “non-incumbent” developers.  FERC therefore required that public utility transmission providers remove certain rights of first refusal (ROFR) from their federal tariffs and contracts, thereby eliminating the public utilities’ automatic right to construct transmission facilities within their service territories, including proposals submitted by third parties.4 In the wake of Order No. 1000, regional transmission planning groups across the country have adopted a variety of competitive processes for selecting transmission proposals and assigning construction rights.  The court held that FERC has the authority under FPA Section 206 to require removal of the federal ROFR and rejected Petitioners’ argument that the relationship between the federal ROFR and FERC-jurisdictional rates is too attenuated to trigger FERC’s Section 206 authority. 

The court also rejected Petitioners’ argument that the removal of the federal ROFR violated the so-called Mobile-Sierra doctrine,5 “which presumes that freely-negotiated wholesale-energy contracts are just and reasonable unless found to seriously harm the public interest.”  The court found that Petitioners’ Mobile-Sierra objection to the ROFR removal was not ripe because FERC had committed to consider the Mobile-Sierra arguments when it reviewed the public utility transmission providers’ tariffs that would be submitted in compliance with Order No. 1000.

Order No. 1000 also required public utility transmission providers to develop methods for allocating the costs of new transmission facilities to the entities that benefit from such facilities.  FERC did not impose a one-size-fits-all requirement dictating how such costs should be allocated; rather, FERC announced general cost allocation principles for the various regions to implement.  The court dismissed Petitioners’ argument that FERC does not have the authority to adopt cost allocation reforms.  In particular, the court rejected the argument that Section 206 does not authorize FERC to require utilities “to pay for the costs of transmission facilities developed by entities with whom they have no prior contractual or customer relationship and from whom they do not take transmission service.” 

Order No. 1000 further required that the transmission planning regions establish procedures to account for the impact that federal, state and local laws and regulations, including state renewable portfolio standards, have on the transmission system.  The court rejected Petitioners’ argument that FERC cannot require regions to take into account such public policy requirements because FERC does not have the statutory authority to generally promote the “public welfare.”  The court concluded that Order No. 1000 “does not promote any particular public policy or even the public welfare generally.  The mandate simply recognizes that state and federal policies might affect the transmission market and directs transmission providers to consider that impact in their planning decisions.”  The court also rejected Petitioners’ argument that the public policy mandate is too vague, finding that Order No. 1000 only required regions to establish the processes for evaluating public policies that may impact the transmission grid.

Finally, the D.C. Circuit rejected jurisdictional challenges to Order No. 1000 from non-public utilities such as municipal utilities.  Prior to Order No. 1000, in Order Nos. 8886 and 890,7 FERC required non-public utility transmission providers that seek access to a public utility’s transmission system on an open-access basis to provide reciprocal transmission service over their own systems on comparable terms.  Order No. 1000 included as part of this “reciprocity condition” that, in exchange for open access, such non-public utilities must also participate in regional transmission planning and cost allocation processes.  The court affirmed FERC here as well, finding that the Order No. 1000 reciprocity condition was “fundamentally the same” as that contained in earlier FERC orders and that FERC reasonably relied on the reciprocity condition to encourage non-public utility transmission providers to participate in regional transmission planning processes.


1 Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, FERC Stats. & Regs. ¶ 31,323 (2011) (“Order No. 1000”), order on reh'g, Order No. 1000-A, 139 FERC ¶ 61,132, order on reh'g, Order No. 1000-B, 141 FERC ¶ 61,044 (2012) (collectively, “Order No. 1000”).

2 16 U.S.C. § 824e.

3 Order No. 1000 at P 52.

4 The elimination of the federal ROFR was one of the most controversial aspects of Order No. 1000.

5 United Gas Pipe Line Co. v. Mobile Gas Serv. Corp., 350 U.S. 332 (1956); FPC v. Sierra Pac. Power Co., 350 U.S. 348 (1956).

6 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996)

7 Preventing Undue Discrimination & Preference in Transmission Serv., Order No. 890, FERC Stats. & Regs. ¶ 31,241 (2007).

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.