D.C. Circuit Upholds Order No. 1000, FERC’s Landmark Transmission Planning and Cost Allocation Rulemaking Order

Aug 18, 2014

Reading Time : 3 min

FERC determined in Order No. 1000 that “the narrow focus of [the pre-Order No. 1000] planning requirements and shortcomings of [the pre-Order No. 1000] cost allocation practices create an environment that fails to promote the more efficient and cost-effective development of new transmission facilities, and that addressing these issues is necessary to ensure just and reasonable rates.”3 The D.C. Circuit agreed, concluding that there was “substantive evidence of a theoretical threat” to justify FERC’s adoption of the Order No. 1000 pursuant to an FPA Section 206 rulemaking proceeding.

In Order No. 1000, FERC mandated that a regional transmission planning process consider and evaluate transmission projects proposed by “non-incumbent” developers.  FERC therefore required that public utility transmission providers remove certain rights of first refusal (ROFR) from their federal tariffs and contracts, thereby eliminating the public utilities’ automatic right to construct transmission facilities within their service territories, including proposals submitted by third parties.4 In the wake of Order No. 1000, regional transmission planning groups across the country have adopted a variety of competitive processes for selecting transmission proposals and assigning construction rights.  The court held that FERC has the authority under FPA Section 206 to require removal of the federal ROFR and rejected Petitioners’ argument that the relationship between the federal ROFR and FERC-jurisdictional rates is too attenuated to trigger FERC’s Section 206 authority. 

The court also rejected Petitioners’ argument that the removal of the federal ROFR violated the so-called Mobile-Sierra doctrine,5 “which presumes that freely-negotiated wholesale-energy contracts are just and reasonable unless found to seriously harm the public interest.”  The court found that Petitioners’ Mobile-Sierra objection to the ROFR removal was not ripe because FERC had committed to consider the Mobile-Sierra arguments when it reviewed the public utility transmission providers’ tariffs that would be submitted in compliance with Order No. 1000.

Order No. 1000 also required public utility transmission providers to develop methods for allocating the costs of new transmission facilities to the entities that benefit from such facilities.  FERC did not impose a one-size-fits-all requirement dictating how such costs should be allocated; rather, FERC announced general cost allocation principles for the various regions to implement.  The court dismissed Petitioners’ argument that FERC does not have the authority to adopt cost allocation reforms.  In particular, the court rejected the argument that Section 206 does not authorize FERC to require utilities “to pay for the costs of transmission facilities developed by entities with whom they have no prior contractual or customer relationship and from whom they do not take transmission service.” 

Order No. 1000 further required that the transmission planning regions establish procedures to account for the impact that federal, state and local laws and regulations, including state renewable portfolio standards, have on the transmission system.  The court rejected Petitioners’ argument that FERC cannot require regions to take into account such public policy requirements because FERC does not have the statutory authority to generally promote the “public welfare.”  The court concluded that Order No. 1000 “does not promote any particular public policy or even the public welfare generally.  The mandate simply recognizes that state and federal policies might affect the transmission market and directs transmission providers to consider that impact in their planning decisions.”  The court also rejected Petitioners’ argument that the public policy mandate is too vague, finding that Order No. 1000 only required regions to establish the processes for evaluating public policies that may impact the transmission grid.

Finally, the D.C. Circuit rejected jurisdictional challenges to Order No. 1000 from non-public utilities such as municipal utilities.  Prior to Order No. 1000, in Order Nos. 8886 and 890,7 FERC required non-public utility transmission providers that seek access to a public utility’s transmission system on an open-access basis to provide reciprocal transmission service over their own systems on comparable terms.  Order No. 1000 included as part of this “reciprocity condition” that, in exchange for open access, such non-public utilities must also participate in regional transmission planning and cost allocation processes.  The court affirmed FERC here as well, finding that the Order No. 1000 reciprocity condition was “fundamentally the same” as that contained in earlier FERC orders and that FERC reasonably relied on the reciprocity condition to encourage non-public utility transmission providers to participate in regional transmission planning processes.


1 Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, FERC Stats. & Regs. ¶ 31,323 (2011) (“Order No. 1000”), order on reh'g, Order No. 1000-A, 139 FERC ¶ 61,132, order on reh'g, Order No. 1000-B, 141 FERC ¶ 61,044 (2012) (collectively, “Order No. 1000”).

2 16 U.S.C. § 824e.

3 Order No. 1000 at P 52.

4 The elimination of the federal ROFR was one of the most controversial aspects of Order No. 1000.

5 United Gas Pipe Line Co. v. Mobile Gas Serv. Corp., 350 U.S. 332 (1956); FPC v. Sierra Pac. Power Co., 350 U.S. 348 (1956).

6 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996)

7 Preventing Undue Discrimination & Preference in Transmission Serv., Order No. 890, FERC Stats. & Regs. ¶ 31,241 (2007).

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.