Federal Court Finds California PURPA Programs Non-Compliant

Dec 14, 2017

Reading Time : 3 min

Background

Congress enacted PURPA to promote the use of domestic renewable energy resources. The law requires electric utilities, under certain circumstances, to purchase power produced from small generating facilities called “Qualifying Facilities,” or “QFs.”2 PURPA directs the Federal Energy Regulatory Commission (FERC) to prescribe rules to carry out this objective.

One such rule prescribed by FERC requires that QFs be given a choice in the pricing and delivery options for their PURPA sales. Under 18 C.F.R. § 292.304(d) (2017), each QF has the option to (1) provide energy as the QF determines, in which case the rate for such sales shall be based on the purchasing utility’s “avoided costs”3 calculated at the time of delivery; or (2) provide energy pursuant to a legally enforceable obligation over a specified term, in which case the rate for such sales shall be based on either (i) avoided costs calculated at the time of delivery or (ii) avoided costs calculated when the obligation is incurred. PURPA directs each state regulatory authority to implement FERC’s rules for the electric utilities over which the state authority has jurisdiction.4

Winding Creek Decision

Winding Creek sued the CPUC commissioners in their official capacities, challenging California’s Renewable Market-Adjusting Tariff (Re-MAT) procurement program. Re-MAT, which became operational in 2013, provides a feed-in tariff for renewable generating facilities up to three megawatts (MW) in size. It requires California utilities such as Pacific Gas and Electric Company (PG&E) to purchase power from QFs under long-term contracts at prices established through a complex administrative process. California’s utilities may purchase no more than 750 MW of generation, collectively, through the Re-MAT program.

Winding Creek argued in its suit that two aspects of the Re-MAT program prevent Winding Creek from obtaining a contract consistent with its entitlement under PURPA. First, Winding Creek argued that the state-wide 750 MW cap is inconsistent with PURPA and FERC’s implementing regulations, which require utilities to buy all of the energy offered by QFs.5 Winding Creek also challenged the program’s pricing mechanism, which Winding Creek argued differed from the “avoided cost” methodology established in FERC’s regulations.

The State of California’s primary defense was that another California program, the Standard Contract for QFs that are 20 MW or less (“Standard Contract”), satisfies the requirements of PURPA, and therefore the CPUC may implement additional non-compliant programs.6 Indeed, FERC held in its order declining Winding Creek’s request for a PURPA enforcement action that a state may offer rates and terms for QFs that differ from the PURPA rules so long as the state offers another PURPA-compliant option.7

The problem with that argument, the court held, is that the Standard Contract also does not comply with PURPA.8 While the Standard Contract program imposes no limit on the total procurement quantity, as the Re-MAT program does, it fails to offer both of the pricing options that FERC’s PURPA regulations require. Specifically, the Court determined that the program fails to offer a rate based on the utility’s avoided costs calculated at the time of delivery.

The court stopped short of granting the full relief sought by Winding Creek, however. Winding Creek had asked the court to direct the CPUC to award Winding Creek a contract worth $89.23 per MWh (Megawatt Hours)—the price offered in PG&E’s initial Re-MAT program period. The court instead held that Winding Creek will need to pursue any such “as-applied” challenge in a state forum.9

The court’s decision, nevertheless, means that, at least for small QFs under 20 MW, California does not have an existing program that is PURPA-compliant. California may decide to appeal the decision, but the ruling, if upheld, would likely result in the CPUC taking some action to bring the Standard Contract program into compliance with PURPA.

 


1 Winding Creek Solar LLC v. Peevey, No. 13-cv-04934-JD (N.D. Cal. Dec. 6, 2017) (“Winding Creek Decision”).

2 See, e.g., FERC, What is a Qualifying Facility?, https://www.ferc.gov/industries/electric/gen-info/qual-fac/what-is.asp (last visited Dec. 11, 2017).

3 “Avoided costs” are the costs that would have been paid by the electric utilities either to generate the electricity themselves or purchase it from another source.

4 16 U.S.C. § 824a-3(f)(1) (2012).

5 See 16 U.S.C. § 824a-3(a); 18 C.F.R. § 292.303(a)(1).

6 California has several programs available for QFs, but Winding Creek’s facility only qualified for the Re-MAT and Standard Contract programs.

7 See Winding Creek Solar LLC, 151 FERC ¶ 61,103, at PP 6-7 (2015).

8 Winding Creek Decision at 14-18.

9 Id. at 19-20.

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.