Federal Court Finds California PURPA Programs Non-Compliant

Dec 14, 2017

Reading Time : 3 min

Background

Congress enacted PURPA to promote the use of domestic renewable energy resources. The law requires electric utilities, under certain circumstances, to purchase power produced from small generating facilities called “Qualifying Facilities,” or “QFs.”2 PURPA directs the Federal Energy Regulatory Commission (FERC) to prescribe rules to carry out this objective.

One such rule prescribed by FERC requires that QFs be given a choice in the pricing and delivery options for their PURPA sales. Under 18 C.F.R. § 292.304(d) (2017), each QF has the option to (1) provide energy as the QF determines, in which case the rate for such sales shall be based on the purchasing utility’s “avoided costs”3 calculated at the time of delivery; or (2) provide energy pursuant to a legally enforceable obligation over a specified term, in which case the rate for such sales shall be based on either (i) avoided costs calculated at the time of delivery or (ii) avoided costs calculated when the obligation is incurred. PURPA directs each state regulatory authority to implement FERC’s rules for the electric utilities over which the state authority has jurisdiction.4

Winding Creek Decision

Winding Creek sued the CPUC commissioners in their official capacities, challenging California’s Renewable Market-Adjusting Tariff (Re-MAT) procurement program. Re-MAT, which became operational in 2013, provides a feed-in tariff for renewable generating facilities up to three megawatts (MW) in size. It requires California utilities such as Pacific Gas and Electric Company (PG&E) to purchase power from QFs under long-term contracts at prices established through a complex administrative process. California’s utilities may purchase no more than 750 MW of generation, collectively, through the Re-MAT program.

Winding Creek argued in its suit that two aspects of the Re-MAT program prevent Winding Creek from obtaining a contract consistent with its entitlement under PURPA. First, Winding Creek argued that the state-wide 750 MW cap is inconsistent with PURPA and FERC’s implementing regulations, which require utilities to buy all of the energy offered by QFs.5 Winding Creek also challenged the program’s pricing mechanism, which Winding Creek argued differed from the “avoided cost” methodology established in FERC’s regulations.

The State of California’s primary defense was that another California program, the Standard Contract for QFs that are 20 MW or less (“Standard Contract”), satisfies the requirements of PURPA, and therefore the CPUC may implement additional non-compliant programs.6 Indeed, FERC held in its order declining Winding Creek’s request for a PURPA enforcement action that a state may offer rates and terms for QFs that differ from the PURPA rules so long as the state offers another PURPA-compliant option.7

The problem with that argument, the court held, is that the Standard Contract also does not comply with PURPA.8 While the Standard Contract program imposes no limit on the total procurement quantity, as the Re-MAT program does, it fails to offer both of the pricing options that FERC’s PURPA regulations require. Specifically, the Court determined that the program fails to offer a rate based on the utility’s avoided costs calculated at the time of delivery.

The court stopped short of granting the full relief sought by Winding Creek, however. Winding Creek had asked the court to direct the CPUC to award Winding Creek a contract worth $89.23 per MWh (Megawatt Hours)—the price offered in PG&E’s initial Re-MAT program period. The court instead held that Winding Creek will need to pursue any such “as-applied” challenge in a state forum.9

The court’s decision, nevertheless, means that, at least for small QFs under 20 MW, California does not have an existing program that is PURPA-compliant. California may decide to appeal the decision, but the ruling, if upheld, would likely result in the CPUC taking some action to bring the Standard Contract program into compliance with PURPA.

 


1 Winding Creek Solar LLC v. Peevey, No. 13-cv-04934-JD (N.D. Cal. Dec. 6, 2017) (“Winding Creek Decision”).

2 See, e.g., FERC, What is a Qualifying Facility?, https://www.ferc.gov/industries/electric/gen-info/qual-fac/what-is.asp (last visited Dec. 11, 2017).

3 “Avoided costs” are the costs that would have been paid by the electric utilities either to generate the electricity themselves or purchase it from another source.

4 16 U.S.C. § 824a-3(f)(1) (2012).

5 See 16 U.S.C. § 824a-3(a); 18 C.F.R. § 292.303(a)(1).

6 California has several programs available for QFs, but Winding Creek’s facility only qualified for the Re-MAT and Standard Contract programs.

7 See Winding Creek Solar LLC, 151 FERC ¶ 61,103, at PP 6-7 (2015).

8 Winding Creek Decision at 14-18.

9 Id. at 19-20.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.