FERC Accepts CAISO’s Proposed Generator Interconnection Process Enhancements To Facilitate Project Downsizing

Aug 7, 2014

Reading Time : 3 min

The Amendments

When it proposed the tariff amendments to FERC in a May 2014 filing, the CAISO recognized that the then-existing downsizing mechanisms in its tariff included various eligibility, timing and other limitations that continued to cause concern for project developers.  In particular, the tariff limited downsizing opportunities to the following:

  • between the Phase I and Phase II interconnection studies or at any time during the study process if the reduction would “improve the costs and benefits” of the interconnection
  • after the study process if the modification of the interconnection customer’s generating facility was deemed “nonmaterial”
  • under a “safe-harbor” provision that allowed for capacity reduction of up to 5 percent for any reason before a project’s commercial operation date or for larger reductions if warranted by certain limited conditions beyond its control
  • by certain interconnection customers who had been allocated transmission plan deliverability under the CAISO’s Generator Interconnection and Deliverability Allocation Procedures or
  • pursuant to a “one-time” opportunity for interconnection customers that entered the CAISO’s interconnection queue before a certain point.

In addition, the CAISO noted in its filing that it had filed, and FERC had accepted, several non-conforming interconnection agreements that included “partial termination” provisions for phased projects.

Going forward under the revised tariff provisions, all reductions to the capacity of generating facilities in the CAISO interconnection queue must occur through the annual generator downsizing process unless explicitly exempted.  Beginning on the date that the first annual downsizing request window opens, all proposed capacity reductions will be subject to the new annual downsizing request process, except for those made pursuant to the following pre-existing mechanisms:  (1) while interconnection studies are ongoing; (2) under the existing “safe-harbor” threshold; (3) through use of nonconforming partial termination provisions included in interconnection agreements; and (4) under the CAISO tariff’s interconnection request “parking” option, which allows an interconnection request to remain in the queue until the next transmission planning deliverability allocation cycle.

Interconnection customers seeking to downsize projects using the new process, which will be open annually from October 15 to November 15, must be in “good standing” with the CAISO.  Among other things, the customer must be in compliance with all applicable tariff and interconnection agreement requirements, including timely posting of required interconnection financial security.  Eligible applicants must submit a downsizing request form and pay a $60,000 deposit to cover restudy and interconnection agreement amendment costs.  However, unlike the pre-existing “one-time” downsizing process, which required downsizing interconnection customers to pay a portion of the costs of amending interconnection agreements affected by their proposed downsizing, interconnection customers that participate in the new process will be responsible only for the costs of amending their own interconnection agreements.

The tariff amendments also allow all interconnection customers the flexibility to make de minimis reductions in capacity without risking breach of their interconnection agreements and without having the reductions studied in the generator downsizing process.  Specifically, if, at the time an interconnection customer achieves final build-out of its project, “the actual capacity . . . is reduced by no more than the greater of 5 percent . . . or 10 MW, but not greater than twenty-five percent of the capacity of the generating facility, as compared to the capacity in the customer’s current interconnection agreement,” the reduction will not constitute a breach of the customer’s interconnection agreement or the CAISO tariff.  Any reductions larger than the amended de minimis threshold will only be allowed pursuant to the new annual downsizing process, subject to the exceptions noted above.

Implications

The revised downsizing tariff provisions are intended to encourage additional renewable project development and reduce project development risk by simplifying the process by which planned capacity can be adjusted to maintain project viability.  In addition, as FERC found in its order approving the amendments, the annual downsizing process provides a balanced approach to eliminating nonviable interconnection requests from the congested interconnection queue while protecting non-downsizing generators from harm resulting from the downsizing of other projects.  FERC believes that the amendments should promote the completion and achievement of commercial operation of projects that would be viable but for their developers’ inability—for whatever reason—to construct the full capacity of the projects set forth in their interconnection requests.  Finally, the streamlining of the CAISO interconnection queue, which includes hundreds of proposed projects, some of which are not viable as originally designed, could expedite the study of and execution of interconnection agreements for projects that remain in the queue.

Share This Insight

Previous Entries

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.