FERC Accepts CAISO’s Proposed Generator Interconnection Process Enhancements To Facilitate Project Downsizing

Aug 7, 2014

Reading Time : 3 min

The Amendments

When it proposed the tariff amendments to FERC in a May 2014 filing, the CAISO recognized that the then-existing downsizing mechanisms in its tariff included various eligibility, timing and other limitations that continued to cause concern for project developers.  In particular, the tariff limited downsizing opportunities to the following:

  • between the Phase I and Phase II interconnection studies or at any time during the study process if the reduction would “improve the costs and benefits” of the interconnection
  • after the study process if the modification of the interconnection customer’s generating facility was deemed “nonmaterial”
  • under a “safe-harbor” provision that allowed for capacity reduction of up to 5 percent for any reason before a project’s commercial operation date or for larger reductions if warranted by certain limited conditions beyond its control
  • by certain interconnection customers who had been allocated transmission plan deliverability under the CAISO’s Generator Interconnection and Deliverability Allocation Procedures or
  • pursuant to a “one-time” opportunity for interconnection customers that entered the CAISO’s interconnection queue before a certain point.

In addition, the CAISO noted in its filing that it had filed, and FERC had accepted, several non-conforming interconnection agreements that included “partial termination” provisions for phased projects.

Going forward under the revised tariff provisions, all reductions to the capacity of generating facilities in the CAISO interconnection queue must occur through the annual generator downsizing process unless explicitly exempted.  Beginning on the date that the first annual downsizing request window opens, all proposed capacity reductions will be subject to the new annual downsizing request process, except for those made pursuant to the following pre-existing mechanisms:  (1) while interconnection studies are ongoing; (2) under the existing “safe-harbor” threshold; (3) through use of nonconforming partial termination provisions included in interconnection agreements; and (4) under the CAISO tariff’s interconnection request “parking” option, which allows an interconnection request to remain in the queue until the next transmission planning deliverability allocation cycle.

Interconnection customers seeking to downsize projects using the new process, which will be open annually from October 15 to November 15, must be in “good standing” with the CAISO.  Among other things, the customer must be in compliance with all applicable tariff and interconnection agreement requirements, including timely posting of required interconnection financial security.  Eligible applicants must submit a downsizing request form and pay a $60,000 deposit to cover restudy and interconnection agreement amendment costs.  However, unlike the pre-existing “one-time” downsizing process, which required downsizing interconnection customers to pay a portion of the costs of amending interconnection agreements affected by their proposed downsizing, interconnection customers that participate in the new process will be responsible only for the costs of amending their own interconnection agreements.

The tariff amendments also allow all interconnection customers the flexibility to make de minimis reductions in capacity without risking breach of their interconnection agreements and without having the reductions studied in the generator downsizing process.  Specifically, if, at the time an interconnection customer achieves final build-out of its project, “the actual capacity . . . is reduced by no more than the greater of 5 percent . . . or 10 MW, but not greater than twenty-five percent of the capacity of the generating facility, as compared to the capacity in the customer’s current interconnection agreement,” the reduction will not constitute a breach of the customer’s interconnection agreement or the CAISO tariff.  Any reductions larger than the amended de minimis threshold will only be allowed pursuant to the new annual downsizing process, subject to the exceptions noted above.

Implications

The revised downsizing tariff provisions are intended to encourage additional renewable project development and reduce project development risk by simplifying the process by which planned capacity can be adjusted to maintain project viability.  In addition, as FERC found in its order approving the amendments, the annual downsizing process provides a balanced approach to eliminating nonviable interconnection requests from the congested interconnection queue while protecting non-downsizing generators from harm resulting from the downsizing of other projects.  FERC believes that the amendments should promote the completion and achievement of commercial operation of projects that would be viable but for their developers’ inability—for whatever reason—to construct the full capacity of the projects set forth in their interconnection requests.  Finally, the streamlining of the CAISO interconnection queue, which includes hundreds of proposed projects, some of which are not viable as originally designed, could expedite the study of and execution of interconnection agreements for projects that remain in the queue.

Share This Insight

Previous Entries

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

Speaking Energy

July 17, 2025

On July 15, 2025, the Federal Energy Regulatory Commission (FERC or Commission) issued an order1 proposing to eliminate the soft price cap of $1,000 per megawatt-hour (MWh) for bilateral spot sales in the Western Electricity Coordinating Council (WECC) that was implemented following the California energy crisis. If adopted, the Commission’s proposal would eliminate the requirement that sellers make a filing with FERC cost justifying spot market sales in excess of the soft price cap, which have become increasingly common in recent years as market conditions have continued to tighten throughout the West. Eliminating the WECC soft price cap would provide sellers that make sales during periods when prices exceed the cap greater certainty that their sales will not be second guessed after the fact.

...

Read More

Speaking Energy

June 25, 2025

On June 4–5, 2025, the Federal Energy Regulatory Commission (FERC or Commission) hosted a commissioner-led technical conference to discuss resource adequacy challenges facing regional transmission organizations and independent system operators (RTO). The conference is a response to the growing concern that multiple RTO regions across the country may not have sufficient supply available in the coming years to meet demand due to resource retirements, the pace of new generation entry and higher load growth arising from the construction of data centers and reindustrialization.

...

Read More

Speaking Energy

June 12, 2025

We are pleased to share the presentation slide deck and a recording of Akin’s recently presented webinar, “Navigating U.S. Policy Shifts in the Critical Minerals Sector.”

...

Read More

Speaking Energy

June 10, 2025

On June 4, 2025, the U.S. Department of Transportation’s (DOT) Pipeline and Hazardous Materials Safety Administration (PHMSA) announced revisions to its procedures for pipeline safety enforcement actions. The changes, outlined in two new policy memoranda from PHMSA’s Office of the Chief Counsel (PHC), aim to enhance due process protections for pipeline operators by clarifying how civil penalties are calculated and expanding the disclosure of agency records in enforcement proceedings.

...

Read More

Speaking Energy

May 22, 2025

On May 19, 2025, the Department of Energy (DOE) finalized its 2024 LNG Export Study: Energy, Economic and Environmental Assessment of U.S. LNG Exports (the 2024 Study) through the release of a Response to Comments on the 2024 Study. The Response to Comments concludes that the 2024 Study, as augmented through public comments submitted on or before March 20, 2025, supporting a finding that liquefied natural gas (LNG) exports serve the public interest. With the comment process complete, DOE will move forward with final orders on pending applications to export LNG to non-free trade agreement (non-FTA) countries.

...

Read More

Speaking Energy

May 20, 2025

On Thursday, May 15, the Senate Commerce, Science & Transportation Subcommittee on Surface Transportation, Freight, Pipelines and Safety held a hearing titled, “Pipeline Safety Reauthorization: Ensuring the Safe and Efficient Movement of American Energy.” The hearing examined legislative priorities for reauthorizing the Pipeline and Hazardous Materials Safety Administration (PHMSA).

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.