IRS Comments on its PTC Start of Construction Guidance

Aug 21, 2014

Reading Time : 5 min

Below are highlights of Mr. Kelley’s remarks. Many remarks provide helpful clarifications of the rules or insight into the policy rationales for the rules. This post was prepared without the benefit of a transcript or a recording.  Please feel free to contact the author to request corrections. Also, it is important to note that these remarks were informal and are not binding on the IRS.

As background, Notice 2014-46 primarily clarified three points:

1. For projects that did not meet the safe harbor of spending 5 percent of their cost in 2013 and instead undertook “significant physical work” in 2013, there is no minimum threshold of work required as long as the work performed in 2013 was significant as provided for in the IRS notices.

2. Transfers of grandfathered projects are permissible, as long as either (a) the transfer includes contracts or land rights or (b) the transferee and transferor are more than 20 percent related.

3. If a project fell short of the 5 percent safe harbor, but at least 3 percent was spent in 2013, then the number of turbines included in the project that are tax-credit-eligible may be prorated accordingly.

Significant Physical Work

Mr. Kelley confirmed that the wind industry’s reading of the physical work requirement in Notice 2014-46 was accurate: “The significant physical work standard is a qualitative standard, rather than quantitative. There is no minimum amount of work that must have been done in 2013.  There is no bright line. The test is somewhat nebulous. A lot of the test comes from the 1603 start of construction FAQs, bonus depreciation rules and investment tax credit rules going back to the 1960s.”

Mr. Kelley was asked if the level of “physical work” required increased proportionately with the size of the project. He responded, “The size of the project does not matter. The work must be significant and done in 2013.”

Mr. Kelley was asked if excavating a single turbine site was sufficient.  He responded, “I don’t want to speculate about specific fact patterns. You get some comfort from the language in the two notices.”

Mr. Kelley was asked if it was necessary to excavate, pour concrete and install bolts for one or more turbine sites in 2013 to achieve significant physical work in 2013. He said, “It is fair reading that just starting excavation is enough without pouring concrete or installing bolts. The language says ‘or,’ rather than ‘and.’1 Any one activity is sufficient.”

Mr. Kelley was asked if “excavation has begun,” if, at the end of 2013, a project owner started excavating a turbine site but did not “finish off” the excavation due to the pending winter being likely to damage the finishing work. His response was “sounds like excavation has begun and is significant.”

Mr. Kelley was asked why examples were not included in Notice 2104-46. He said, “Additional examples might perhaps cause more confusion than they help.”

No Binding Written Contract Requirement for On-Site Work

Mr. Kelley was asked if a “binding written contract” was required for physical work that was conducted on the project site. After an apparent sidebar with his IRS colleagues, he responded, “I don’t think so if the work is done on site and is significant.” This interpretation is helpful because section 4.02 of Notice 2013-29 provides, “Both on-site and off-site work (performed either by the taxpayer or by another person under a binding written contract) may be taken into account for purposes of demonstrating that physical work of a significant nature has begun.”  Based on Mr. Kelley’s comment, the parenthetical clause is intended to only modify “off-site work.”

Changes in the Location of the Project in Which Safe Harbored Equipment Will Be Used

Mr. Kelley was asked whether, if a developer has a master turbine contract with a manufacturer that was entered into 2013 and the 5 percent cost was incurred under that contract in 2013, the five percent safe harbor was met even if the developer did not know at what project site the turbines would be deployed. He responded, “You do not have to know the address of the project in 2013. That’s the point of the relocation provision of the notice.”2 

He added that it is permissible to have purchased equipment for the 5 percent safe harbor and had “multiple projects in mind” for the same equipment. Further, he was asked if the reference in section 4.03 of Notice 2014-46 to a “taxpayer also may begin construction of a facility in 2013 with the intent to develop the facility at a certain site” requires a developer to be able to demonstrate that, in 2013, it had an intent to develop a particular site. His response was that the reference did not require that.

Transfers

Mr. Kelley made it clear that it is possible for one taxpayer to transfer only safe harbored equipment to a transferee that is more than 20 percent related to the transferor. The transferee can then undertake additional development work, such as obtaining land rights, permits, interconnection agreements or a power purchase agreement and then transfer the safe-harbored equipment plus those rights or agreements to an unrelated party. That unrelated party could then claim tax credits based on its ownership of the safe-harbored equipment.

Mr. Kelley was asked for detail with respect to the requirement in section 4.03 of Notice 2014-46 that a transfer to an unrelated party include more than merely “tangible personal property” (i.e., equipment). He replied, “The right way to look at it is to include land, a land lease, a power purchase agreement or an interconnection agreement. This rule is following the 1603 start of construction FAQs.”

The “master contract” rules in section 4.03(2) of Notice 2013-29 refer to transferring safe-harbored equipment to “an affiliated special-purpose vehicle.”  Mr. Kelley was asked what the relationship is between “an affiliated special-purpose vehicle” and the 20-percent-related party standard with respect to transferees in section 4.03 of Notice 2014-46. He responded, “The affiliated special-purpose vehicle language is borrowed from the 1603 start of construction FAQs. I don’t have a comment on how to tie it to the related party rules.”

Three Percent Standard for Prorating Tax Credits

Mr. Kelley was asked for the policy rationale for including section 5.01 of Notice 2014-46 that provides rules with respect to projects that are unable to meet either (a) the 5 percent spend in 2013 safe harbor or (b) the significant physical work requirement but for which at least 3 percent was spent in 2013. He noted that some project owners had explained to the IRS that they were building extremely large projects for which the 5 percent spend was not feasible; however, for reasons he did not specify, the projects were unable to meet the significant physical work standard. He explained that the government was persuaded that it was unreasonably harsh for such projects to be eligible for zero tax credits while a project for which “excavation of a single turbine site” occurred in 2013 would be eligible for full tax credits under the significant physical work standard. Thus, the IRS made a “policy call to provide some relief but put in a three percent floor.”

A tangential ramification of this statement is that Mr. Kelley appears to have implicitly endorsed excavating a single turbine site as being sufficient for the start of significant physical work, although he sidestepped that question the first time it was asked.


1 See Notice 2014-46, § 3; Notice 2013-29, § 4.02.

2 See Notice 2014-46, § 4.02.

Share This Insight

Previous Entries

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

Speaking Energy

August 6, 2025

In Sierra Club v. FERC, No. 24-1199 (D.C. Cir. Aug. 1, 2025), the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) upheld the Federal Energy Regulatory Commission’s (FERC) approval of a 1,000-foot natural gas pipeline segment crossing the United States-Mexico border (the Border Pipeline) under section 3 of the Natural Gas Act (NGA), rejecting environmental groups’ challenges that FERC improperly limited its analysis under both the NGA and the National Environmental Policy Act (NEPA), as related to a 155-mile intrastate “Connector Pipeline” constructed upstream of the Border Pipeline in Texas.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.