United States Solar – The Shift from Utility Scale to Distributed Generation

Mar 24, 2014

Reading Time : 2 min

In recent years, fewer power purchase agreements (PPAs) have become available for potential projects. In some states, utilities are issuing fewer requests for proposals for large scale PPAs as they come closer to achieving their state-mandated renewable portfolio standards with current PPAs. For example, the three major California utilities (San Diego Gas & Electric, Pacific Gas & Electric and Southern California Edison) have a surplus of MWs contracted under PPAs that will allow them to meet their 33 percent RPS requirement even if all of the projects do not move forward. In other states, the lack of enforcement mechanisms for renewable portfolio mandates have not required the utilities to make power purchase agreements available for renewable projects. 

In addition, the significant drop in PPA prices for renewable energy projects in the past five years1 makes large-scale solar projects less attractive to investors and more difficult to finance. Utilities have even reopened the PPA price in certain cases as projects move from the development stage to the construction stage. The uncertainty caused by the lack of supply of PPAs and lower PPA prices have made large scale projects more difficult to finance. Distributed generation projects have a guaranteed offtaker and, due to their lower costs, are easier to finance or do not require financing at all.

Reduced equipment and installation costs are another impetus for the shift of the market to distributed generation. The cost of utility scale solar decreased by 15 percent in 2013 from $2.27/W in Q4 2012 to $1.96/W in Q4 2013.2  As the cost of equipment declines, the economies of scale once gained from large-scale solar projects are dampened by the cost of acquiring land and navigating difficult regulatory regimes. Distributed generation projects are not subject to environmental, permitting or biological testing requirements.

Finally, the reduction of the ITC from 30 percent to 10 percent at the beginning of 2017 is another driving force. The ITC has been an important piece of financing for utility scale projects. The decrease will create a gap in financing for projects that are not online by the end of 2016. In sum, any utility scale project not currently under development will only be able to qualify for the reduced ITC rate.

The distributed generation market is not without challenges. A number of states (including Arizona, Colorado and California) are considering changes to their net metering policies that could adversely impact the benefit of distributed generation systems to homeowners and businesses. However, the distributed generation market is not anticipated to be significantly harmed by these changes since the decreasing cost of solar system installation is expected to offset these impacts.


1 For example, in the western United States, PPA prices for PV solar projects were approximately $150/MW in 2008 and recently were approximately $60/MW. 

2 U.S. Solar Market Insight Report: 2013 Year-in-Review, GTM Research and Solar Energy Industries Association.

Share This Insight

Previous Entries

Speaking Energy

November 12, 2025

On November 7, 2025, the New York Department of Environmental Conservation (NYSDEC) and the New Jersey Department of Environmental Protection (NJDEP) reversed their prior positions and approved Clean Water Act (CWA) Section 401 Water Quality Certifications and other environmental permits for the Transcontinental Gas Pipeline Company’s (Transco) Northeast Supply Enhancement Project (NESE). NESE is a 25-mile natural gas pipeline expansion project certificated by the Federal Energy Regulatory Commission (FERC) that is intended to deliver 400,000 dekatherms per day of natural gas produced in Pennsylvania to local distribution company customers in New York City through new facilities in Middlesex County, New Jersey and an underwater segment traversing the Raritan and Lower New York Bays.

...

Read More

Speaking Energy

November 6, 2025

The market for the direct procurement of energy by commercial and industrial buyers has been active in the U.S. for a decade.  In years past, buyers often engaged in such purchases on a voluntary basis to achieve their goals to use renewable energy.  These days, C&I buyers are turning to direct procurement or self-supply to obtain a reliable source of energy.  Sufficient and accessible energy from a local utility may not be available or may be materially delayed or trigger significant capital costs.  This is a material change driven in part by increased demand for electricity, including demand from data centers, EV infrastructure and industrial development.       

...

Read More

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.